RWTP GB MNE MST 000041 Cable Management & Termination
RWTP GB MNE MST 000041 Cable Management & Termination
RWTP GB MNE MST 000041 Cable Management & Termination
Title : Installation of Cable Management & Termination for ELV & Telecommucation System
Doc. No. : RWTP-GB-MNE-MST-000041-00
Date : 19th March 2024
1 Scope definition /
2 Objective /
7 Pre-requisite approvals/permits /
9 Preparation /
15 Testing/inspection plan /
Checked by : Reviewed by :
Revision : 00
Consultant
Approved by Tan Jin Soon (Sepakat Setia
Perunding)
Construction
Reviewed by Ivan Lim Kien Aun
Manager
Sathyan A/L
Prepared by Project Manager
Anbalakan
RWTP
RASAU WATER TREATMENT PLANT
Table of Contents
1.0 SCOPE OF WORKS ................................................................................................................... 2
1.1 General Description .............................................................................................................. 2
1.2 Reference ............................................................................................................................... 2
1.3 Materials ................................................................................................................................. 2
1.4 Plant and Equipment ............................................................................................................ 2
1.5 Manpower............................................................................................................................... 4
1.6 Work Procedures .................................................................................................................. 5
1.6.1 Preparatory Work for Cable Management .......................................................................... 5
1.6.2 Installation of Tray/Trunking Installation ........................................................................... 6
1.6.3 Installation of Conduit .......................................................................................................... 7
1.6.4 Preparatory Work for Cable Termination ........................................................................... 8
1.6.5 Cable Termination ................................................................................................................ 9
1.6.6 Testing & Commissioning ................................................................................................. 10
2.0 SAFETY AND HEALTH REQUIREMENTS ............................................................................. 13
2.1 Job Safety & Health Analysis............................................................................................. 13
2.2 Information to Personnel .................................................................................................... 13
2.3 Emergency Arrangements ................................................................................................. 13
2.4 Permit Requirements .......................................................................................................... 14
2.5 Housekeeping ...................................................................................................................... 14
3.0 ENVIRONMENTAL ISSUES..................................................................................................... 15
3.1 Environmental Aspects, Impacts & Control Measures ................................................... 15
3.2 Air Quality and Noise Level................................................................................................ 15
3.3 Water Quality ....................................................................................................................... 15
3.4 Waste Management ............................................................................................................. 15
4.0 QUALITY ASSURANCE & QUALITY CONTROL ................................................................... 16
4.1 Contractual Requirements ................................................................................................. 16
4.2 Inspection and Testing ....................................................................................................... 16
5.0 APPENDICES ................................................................................................................................. 17
5.1 Job Safety Analysis................................................................................................................... 18
5.2 Emergency Response Flow Chart ........................................................................................... 19
5.3 Environmental Aspect & Impact Register ............................................................................... 23
5.4 Inspection & Test Plan .............................................................................................................. 24
5.5 QAQC .......................................................................................................................................... 25
1.2 Reference
1) Item 1.1.9.5 – Method Statement, Tender Document Vol 2: Need Statement &
Specifications
1.3 Materials
1.3.1 Materials for cable management and termination installation include the
following:
Item Materials
1. Wall Plug & Screw, Anchor bolt & Nut (M6, M8)
2. Female Type Connector
3. Cable Gland
4. Cable Marker
5. Colour Band
4. Wooden Hammer
5. Screw Driver
6. Open and Box Spanners
7. Base Cutters
8. Ladder/Scaffolding
9. Pipe Bender
10. Cutting Plier
11. Pipe Wrench
12. Cutting Plier
13. Pipe Wrench
14. Tripod Stand Wise
15. Sand Paper
1.5 Manpower
Item Designation Responsibilities
1. Project Manager Responsible for overall commercial, contractual
and technical performances associated with
specific
projects. Responsible to the Project Manager.
2. Construction Manager Planning, coordinating, scheduling and monitoring
of site activities.
3. Project Engineer Responsible for overall operation including liaison
with service provider.
4. Site Supervisor Supervising site construction activities
5. SHE Officer To control and ensure the Safety, Health and
Environmental is adhere at site.
6. SHE Supervisor Supervising site construction activities, organize
toolbox meeting and prepare all relevant permit
before start work.
7. Environment Manager To monitor and control environmental issue onsite
to ensure compliance to the regulation.
8. Environment Officer Control and ensure all site activities comply with
environmental plans and requirement.
9. Machineries Operator To operate the machineries.
10. Surveyor/Chainman Setting out works.
11. Traffic controller To control ingress and egress of construction traffic
at site.
12. General Worker & Conduct general works at site.
Observers
13. Flagmen To provide high visible to public traffic to slow down
when a crossing the working area.
14. Flagman & Traffic Control To control traffic and avoid public enter to the
workplace
15. Traffic management officer Make sure activity at site adhere to Traffic
Management Plan
i. Prior to starting work, Site engineer shall ensure installation material, shop drawing
and method statement of work are approved.
ii. Materials shall be inspected by QAQC team to ensure all material that are delivered
is as per approved brand, model, size and specification.
iii. Materials shall be stored on site under cover dry, well ventilated storage facilities in
designated area. Any damaged materials shall be return and send back
immediately.
iv. Site Engineer shall check the approved drawing for proposed locations of the
trunking and conduit installed and make sure does not obstruct or clashes with
other services.
v. Site Engineer shall conduct measurement for the trunking and conduit size required
lengths at site and instruct the workers for preparation of trunking and conduit to be
installed at site.
xx. Coordinate with other trades or contractors working in the vicinity to avoid conflicts
and ensure a smooth termination process.
i. Gather all necessary tools and equipment, including cable termination kit, crimping
tools, insulation tape, cable glands, and a multi-meter.
ii. Ensure that the work area is well-ventilated and free from potential hazards.
iii. Verify that the power supply to the cables is isolated, and appropriate lockout/tagout
procedures are in place.
iv. Use personal protective equipment (PPE), including gloves and safety glasses.
v. Carefully strip the outer insulation of the cable using a cable stripper, ensuring not to
damage the inner conductors.
vi. Strip the insulation of individual conductors to the specified length, exposing enough
for proper termination.
vii. Select the appropriate cable termination connector based on the cable type and size.
viii. Follow manufacturer guidelines to install the connector onto the stripped end of the
cable, ensuring a secure and snug fit.
ix. Employ a calibrated crimping tool to crimp the connector onto the cable, applying the
recommended force.
x. Inspect the crimped connection for any signs of irregularities or defects.
xi. Apply insulation tape or heat shrink tubing over the crimped area, ensuring complete
coverage and protection against environmental factors.
xii. If terminating into an enclosure, install a suitable cable gland to provide strain relief
and protection.
xiii. Tighten the cable gland securely, following manufacturer specifications.
xiv. Use a multi-meter to perform continuity checks, ensuring a proper electrical
connection.
xv. Conduct insulation resistance tests to verify that the termination meets specified
standards.
xvi. Record details of the termination, including cable type, size, termination connectors
used, and test results.
xvii. Ensure that all relevant standards and regulations are adhered to during the
termination process.
xviii. Inspect the entire termination for any signs of damage, loose connections, or
irregularities.
xix. Reinstate power supply only after confirming the termination's integrity and
conducting a final safety check.
xx. Remove any waste materials, tools, and equipment from the work area.
xxi. Ensure proper disposal of any remnants or packaging materials.
i. Perform a visual inspection of the entire cable management system, checking for
proper installation, secure fastening, and adherence to the cable management plan.
ii. Confirm that cables are correctly identified and labeled according to the labeling
conventions established during the preparatory work.
iii. Ensure that cable pathways are accessible for maintenance purposes and that any
access panels or covers are securely in place.
iv. Verify that safety measures, such as cable bundling to reduce tripping hazards, are in
place and effective.
v. Inspect cable bundling to ensure that cables are properly grouped, bundled, and
secured using appropriate cable ties or management clips.
vi. Check the integrity of support structures, such as cable trays or conduits, to ensure
that they adequately support the weight of the cables without sagging.
vii. Conduct checks for electromagnetic interference (EMI) and radiofrequency
interference (RFI), especially in areas sensitive to such interference.
viii. If applicable, perform load testing to simulate conditions where the cable
management system may be subject to increased stress, ensuring its resilience and
durability.
ix. Verify that the cable management system is suitable for the environmental conditions
of the site, considering factors such as temperature, humidity, and exposure to
chemicals.
x. Confirm that the cable management system integrates seamlessly with other building
services without causing conflicts.
xi. Cross-reference the as-built documentation with the installed cable management
system to ensure accuracy and completeness.
xii. Conduct functional tests to ensure that the cable management system functions as
intended, especially in cases where it includes features like cable retraction
mechanisms or automated routing.
xiii. Coordinate with the client or relevant stakeholders for final acceptance, ensuring that
the cable management system meets their specifications and requirements.
xiv. Provide training to maintenance personnel on the specifics of the cable management
system, including access points, labelling conventions, and any unique features.
xv. Complete the handover process, including the submission of test reports and
updated documentation to the client.
xvi. Implement a post-commissioning monitoring plan to assess the long-term
performance of the cable management system and address any issues that may
arise.
i. Perform a visual inspection of the cable termination, checking for any physical
damage, loose connections, or irregularities in the termination components.
ii. Use a multi-meter to conduct continuity tests on each terminated conductor to ensure
a continuous and unbroken path for electrical current.
iii. Conduct insulation resistance tests to verify that there is adequate insulation between
conductors and between conductors and the termination components.
iv. Verify the correct polarity of the cable termination, ensuring that the phase, neutral,
and ground conductors are connected in the right configuration.
v. Inspect crimped connections for proper integrity, ensuring that crimping tools were
applied with the correct force and that there are no signs of deformation.
vi. If required by standards or specifications, perform a dielectric withstand test to
assess the cable termination's ability to withstand voltage without breakdown.
vii. If applicable, conduct functional tests to ensure that the cable termination performs
its intended functions, such as switching, signalling, or communication.
viii. Measure the voltage drop across the cable termination under load conditions to
ensure it falls within acceptable limits.
ix. Cross-reference the test results with the documentation, including cable schedules
and termination diagrams, to ensure consistency.
2.5 Housekeeping
Housekeeping is an essential part of SHE for the daily routine. Housekeeping
would include the following items:
• Maintain the access way to all working area.
• Proper material arrangement.
• Park the machineries in orderly manner.
• No littering around the site.
5.0 APPENDICES
RWTP
RASAU WATER TREATMENT PLANT
PENGURUSAN AIR SELANGOR
SDN BHD JOB SAFETY & HEALTH ANALYSIS (JSA)
NO. JOB HAZARD CURRENT CONTROL RISK ASSESSMENT HIE ADDITIONAL LEGAL & REVISED RESIDUAL RISK RESPON
SEQUENCE / IDENTIFICATION MEASURES RAR CONTROL OTHER RATING SIBLE
STEPS CHY MEASURES/ REQ PERSON
Pro Sev Risk Rating OF OPPORTUNITIES
Hazard & Risk P S Risk Rating
babi erity CO (O)
PxS PXS
lity (S) NTR
(P) Sco Lev OL Sco Lev
re el re el
1. Mobilizing & Unstable/ soft ground, Supervisor to check 2 3 6 M 3 Put steel plate at the OSHA ‘94 1 3 3 L Engineer /
materials to work uneven access surrounding and prepare soft ground access FMA Supervisor
area (apply safe access area (BOWEC) / Traffic
throughout the 1986 Officer/
whole job Safety
sequence below) personnel
Slip, trip, fall into existing -Access way clear from 1 3 3 L 4 - OSHA ‘94 - - - - Engineer /
drain/manhole obstruction. FMA Supervisor
-Cover openings with sturdy (BOWEC) / Safety
materials. 1986 personnel
2. Transportation Unsafe access / Poor -Use dedicated access for 1 3 3 L 4 - OSHA ‘94 - - - - Engineer /
machinery & access machineries. FMA Supervisor
material to the -Materials must place away (BOWEC) / Safety
site from access way. 1986 personnel
-Inspection of ladder or
scaffold access before use.
Page 1 of 6
Rev. No:01 / Date: 18 JAN 2023
Appendix A to RWTP-GB-QSHE-MSP-0010-1
RWTP
RASAU WATER TREATMENT PLANT
PENGURUSAN AIR SELANGOR
SDN BHD JOB SAFETY & HEALTH ANALYSIS (JSA)
NO. JOB HAZARD CURRENT CONTROL RISK ASSESSMENT HIE ADDITIONAL LEGAL & REVISED RESIDUAL RISK RESPON
SEQUENCE / IDENTIFICATION MEASURES RAR CONTROL OTHER RATING SIBLE
STEPS CHY MEASURES/ REQ PERSON
Pro Sev Risk Rating OF OPPORTUNITIES
Hazard & Risk P S Risk Rating
babi erity CO (O)
PxS PXS
lity (S) NTR
(P) Sco Lev OL Sco Lev
re el re el
Transportation Flying dust Provide water browser, wear 1 3 3 L 3 - OSHA ‘94 - - - - Engineer /
machinery & face mask FMA Supervisor
material to the (BOWEC) / Safety
site (cont.) 1986 personnel
Soft & unstable ground Provide steel plate. 2 2 4 2 3 - OSHA ‘94 - - - - Engineer /
Supervisor to check ground FMA Supervisor
condition before park the (BOWEC) / Safety
machineries. 1986 personnel
3. Unloading Moving load - Use safety tag line to 2 4 8 M 3,4 -Stack materials OSHA ‘94 1 4 4 L Engineer /
machinery & control suspended load. properly before lift. FMA Lifting
material using -Barricade the lifting/work (BOWEC) Supervisor
crane/lorry crane area and display warning 1986 / Rigger/
signage. Safety
personnel
Defective lifting gears -Inspection of lifting gears 2 4 8 M 3,4 -Remove any OSHA ‘94 1 4 4 L Engineer /
before use. defection lifting gear FMA Lifting
-Colour coding tag for from site. (BOWEC) Supervisor
inspected lifting gears. 1986 / Rigger/
-Operator and rigger to Safety
ensure the lifting gears are personnel
in good condition.
Improper crane -Follow approved permit to 2 4 8 M 3,4 -All crane outriggers OSHA ‘94 1 4 4 L Engineer /
positioning work. must be fully FMA Lifting
-Follow approved Lifting extended. (BOWEC) Supervisor
Plan. -Use steel plates for 1986 / Rigger/
-Check ground condition crane outriggers. Safety
before park, crane / lorry personnel
crane.
Page 2 of 6
Rev. No:01 / Date: 18 JAN 2023
Appendix A to RWTP-GB-QSHE-MSP-0010-1
RWTP
RASAU WATER TREATMENT PLANT
PENGURUSAN AIR SELANGOR
SDN BHD JOB SAFETY & HEALTH ANALYSIS (JSA)
NO. JOB HAZARD CURRENT CONTROL RISK ASSESSMENT HIE ADDITIONAL LEGAL & REVISED RESIDUAL RISK RESPON
SEQUENCE / IDENTIFICATION MEASURES RAR CONTROL OTHER RATING SIBLE
STEPS CHY MEASURES/ REQ PERSON
Pro Sev Risk Rating OF OPPORTUNITIES
Hazard & Risk P S Risk Rating
babi erity CO (O)
PxS PXS
lity (S) NTR
(P) Sco Lev OL Sco Lev
re el re el
4. Installation of Falling from height -Use of safety harness for all 2 4 8 M 3,4 -Approved PTW for OSHA ‘94 1 4 4 L Engineer /
exposed/conceal work with fall of 3 meters or working at height. FMA Supervisor
ed conduit, cable more. -Monitoring and (BOWEC) / Safety
trunking, cable -Use of industrial type supervision. 1986 personnel
trays ladder. -Provide secured
-Installation of edge anchorage point for
protection. worker to hook the
-Buddy system during using body harness.
the ladder/scaffold access. -No body is allowed
on the mobile
scaffold during
mobile scaffold is
moving.
Unsafe access -Ensure access scaffold with 2 3 6 M 3 -Ensure that the OSHA ‘94 1 3 3 L Engineer/
scaffolding/working inspection tag before use. foundation of the FMA Scaffolder/
platform -Ensure the scaffolding is scaffold access is on (BOWEC) Supervisor
erected as per design. the firm ground. 1986 / Safety
personnel
Defective power tools -Check all equipment are in 2 2 4 L 4 - OSHA ‘94 - - - - Engineer /
good condition. FMA Supervisor
-Check all hoses / (BOWEC) / Safety
connectors are in good 1986 personnel
condition.
Page 3 of 6
Rev. No:01 / Date: 18 JAN 2023
Appendix A to RWTP-GB-QSHE-MSP-0010-1
RWTP
RASAU WATER TREATMENT PLANT
PENGURUSAN AIR SELANGOR
SDN BHD JOB SAFETY & HEALTH ANALYSIS (JSA)
NO. JOB HAZARD CURRENT CONTROL RISK ASSESSMENT HIE ADDITIONAL LEGAL & REVISED RESIDUAL RISK RESPON
SEQUENCE / IDENTIFICATION MEASURES RAR CONTROL OTHER RATING SIBLE
STEPS CHY MEASURES/ REQ PERSON
Pro Sev Risk Rating OF OPPORTUNITIES
Hazard & Risk P S Risk Rating
babi erity CO (O)
PxS PXS
lity (S) NTR
(P) Sco Lev OL Sco Lev
re el re el
Poor electrical -Use industrial plugs / cable. 2 3 6 M 3 -All electrical wire OSHA ‘94 1 3 3 L Engineer/
connection -Electrical equipment / wiring must hang up & do FMA Supervisor
to be inspected / connected not expose water. (BOWEC) / Safety
by electrician. -Check all cables 1986 personnel
-Display signages. Work before connection.
briefing prior to work start.
6. Test and Falling from height -Use of safety harness for all 2 4 8 M 3,4 -Approved PTW for OSHA ‘94 1 4 4 L Engineer /
commissioning work with fall of 3 meters or working at height. FMA Supervisor
more. -Monitoring and (BOWEC) / Safety
-Use of industrial type supervision. 1986 personnel
ladder. -Provide secured
-Installation of edge anchorage point for
protection. worker to hook the
-Buddy system for working body harness.
using ladder.
Page 4 of 6
Rev. No:01 / Date: 18 JAN 2023
Appendix A to RWTP-GB-QSHE-MSP-0010-1
RWTP
RASAU WATER TREATMENT PLANT
PENGURUSAN AIR SELANGOR
SDN BHD JOB SAFETY & HEALTH ANALYSIS (JSA)
NO. JOB HAZARD CURRENT CONTROL RISK ASSESSMENT HIE ADDITIONAL LEGAL & REVISED RESIDUAL RISK RESPON
SEQUENCE / IDENTIFICATION MEASURES RAR CONTROL OTHER RATING SIBLE
STEPS CHY MEASURES/ REQ PERSON
Pro Sev Risk Rating OF OPPORTUNITIES
Hazard & Risk P S Risk Rating
babi erity CO (O)
PxS PXS
lity (S) NTR
(P) Sco Lev OL Sco Lev
re el re el
Test and Trip & fall -Conduct daily 2 2 4 L 4 - OSHA ‘94 - - - - Engineer /
commissioning housekeeping and arrange FMA Supervisor
(cont.) the material accordingly. (BOWEC) / Safety
-No obstruction at the 1986 personnel
access way.
Electric shock -Use industrial plugs / cable. 2 3 6 M 3 -Work briefing prior OSHA ‘94 1 3 3 L Manager /
-Electrical equipment / wiring to work start. FMA Engineer /
to be inspected / connected -Check all cables (BOWEC) Supervisor
by electrician. before connection. 1986 /
-Display signages. -Cable hangs / not Electrician
trailing on ground / / Safety
in water. Personnel
Page 5 of 6
Rev. No:01 / Date: 18 JAN 2023
Appendix A to RWTP-GB-QSHE-MSP-0010-1
RWTP
RASAU WATER TREATMENT PLANT
PENGURUSAN AIR SELANGOR
SDN BHD JOB SAFETY & HEALTH ANALYSIS (JSA)
Page 6 of 6
Rev. No:01 / Date: 18 JAN 2023
RWTP
RASAU WATER TREATMENT PLANT
Fire Emergency
Identifier alert
Major Minor
Emergency
terminates
Debriefing by Conduct
Emergency investigation Finish
commander
Risk:
- Legal action by authorities
Generation of scheduled waste (including Opportunities: Immediately clear any spillage on the ground. Schedueld waste will be stored at
Land contamination N 2 2 4 Yes
disposal of waste) - NA scheduled waste storage area and disposed by licensed contractor
Risk:
- Public complaints
Opportunities:
- Regular maintenance of 1. The machinery will be maintained in good working order to ensure that exhaust
Generation of black smoke Air pollution A 2 2 4 Yes machinery emission is controlled.
- Increase the life span of the 2. Allow only machinery that is in good condition to enter the site.
machinery
1. Mobilisation /
Demobilization (Loading/
Unloading of plant, machinery
and materials) Risk: 1. Speed limits and traffic volume restriction within the site area willl be
- Public complaint implemented to reduce the dust dispersion.
- Legal action by authorities 2. Dampen all access. Water bowser need to standby for watering all the time.
Generation of dust Air pollution N 2 2 4 Yes
3. Vehicles to be installed with tailgate and covered with tarpaulin.
Opportunities: 4. To wash the construction vehicles wheels at a wash trough facility before leaving
- NA from construction site.
Risk:
- Public complaints 1. Wash through to be provided at the site exit with water jet and operator
Dirtying of public roads Public nuisance/public complaint N 3 2 6 Yes 2. Temporary drainage will be constructed to channel surface runoff to silt trap
Opportunities: 3. Water bowser need to be standby for watering purpose
- NA
Risk:
- Public complaints Maintenance of machinery to be conducted regulalry and work will be conducted
Generation of noise & vibration Noise/ vibration nuisance N 2 2 4 Yes within approved working hour. Installation of hoarding or temporary noise barrier. All
Opportunities: noise generating equipment and machinery will be shut down when not in use.
- NA
Risk:
- cost increase due to more
demand in diesel
• Natural resources depletion - climate change 1. Do not leave machineries unattended while machine in running condition.
Fuel Consumption N 3 2 6 Yes
• Increase carbon footprint 2. Turn off machine when no work to reduce use of diesel/ petrol.
Opportunities:
- ultilize other natural resources or
renewable energy
Appendix A
Risk:
- Legal action by authorities
1. A petroleum based machines or equipment be placed on the secondary
Generation of scheduled waste (including
Land contamination N 2 2 4 Yes Opportunities: containment/ tray.
disposal of waste)
- NA 2. Any spillage to be collected and treated as scheduled waste.
Risk:
- Public complaints
Limit working hour. Working hours are in accordance with permissible times as per
Generation of noise/ vibration Noise nuissance N 2 2 4 Yes
authority instructions.
Opportunities:
- NA
3. Cable Termination Risk:
- Public complaints
All type of waste will be segregated, stored and disposed in accordance with the
Generation of non-scheduled waste -Legal action by authorities
Land contamination N 2 1 2 No Construction Waste Management Plan. Open burning is strictly prohibited. Waste
(including disposal of waste)
will be disposed at the approved disposal site.
Opportunities:
- NA
Appendix A
Risk:
- Legal action by authorities
All type of waste will be segregated, stored and disposed in accordance with the
Generation of non-scheduled waste
Land contamination N 2 2 4 Yes Construction Waste Management Plan. Open burning is strictly prohibited. Waste
(including disposal of waste) Opportunities:
- NA will be disposed at the approved disposal site.
N* = Normal
Prepared by Reviewed By Approved By
A* = Abnormal
Ivan Lim Kien Aun E* = Emergency
Name Siti Norlissa Bt Ishak Siti Khairiah Mohd Hashim
L* = Likelihood (refer to Appendix B)
S* = Severity (refer to Appendix B)
# Risk Rating calculation shown in Appendix B
Signature
GAMUDA BERHAD
REF. NO: RWTP-GB-MNE-MST-000041-00 Page 1
ITP FOR INSTALLATION OF CABLE MANAGEMENT & TERMINATION
Document No. RWTP-GB-M&E-ITP-000041-00
Revision No. 00 Rev. Date 19/03/2024
3.0 Termination
Method Statement Upon Completion of Work Inspection Request
3.1 Network Cable Termination Shop Drawing H W S
(RWTP-GB-MNE-MST-000041) Work Checklist
Method Statement Upon Completion of Work Inspection Request
3.2 Control Cable Termination Shop Drawing H W S
(RWTP-GB-MNE-MST-000041) Work Checklist
Signature
Date
GAMUDA BERHAD
REF. NO: RWTP-GB-MNE-MST-000041-00 Page 2
RWTP
RASAU WATER TREATMENT PLANT
5.5 QAQC
Form detail
Forms
Location
Description
Due date
Status In progress
1. Form Details
1.4 Location
Created by zul nizam with Autodesk® Construction Cloud™ on Feb 1, 2024 at 9:28 AM UTC+08:00 Page 1 of 7
Rasau WTP Form detail report
1.9 Material
2. DESCRIPTION OF WORKS
D.O Copy attachment
2.1 Contractor
Pass Fail N/A
2.3 CA Representative
Pass Fail N/A
3. DESCRIPTION OF WORKS
Test certificate copy attachment
3.1 Contractor
Pass Fail N/A
3.3 CA Representative
Pass Fail N/A
Created by zul nizam with Autodesk® Construction Cloud™ on Feb 1, 2024 at 9:28 AM UTC+08:00 Page 2 of 7
Rasau WTP Form detail report
4. DESCRIPTION OF WORKS
Test certificate issued to the correct material delivered (refer to material tagging identification)
4.1 Contractor
Pass Fail N/A
4.3 CA Representative
Pass Fail N/A
5. DESCRIPTION OF WORKS
Brand / Type of material as per approved submission
5.1 Contractor
Pass Fail N/A
5.3 CA Representative
Pass Fail N/A
6. DESCRIPTION OF WORKS
Size, length & dimension as per D.O
6.1 Contractor
Pass Fail N/A
Created by zul nizam with Autodesk® Construction Cloud™ on Feb 1, 2024 at 9:28 AM UTC+08:00 Page 3 of 7
Rasau WTP Form detail report
6.3 CA Representative
Pass Fail N/A
7. DESCRIPTION OF WORKS
Color of material (if applicable)
7.1 Contractor
Pass Fail N/A
7.3 CA Representative
Pass Fail N/A
8. DESCRIPTION OF WORKS
Material unloading & delivery plan (any major equipment that require)
8.1 Contractor
Pass Fail N/A
8.3 CA Representative
Pass Fail N/A
Created by zul nizam with Autodesk® Construction Cloud™ on Feb 1, 2024 at 9:28 AM UTC+08:00 Page 4 of 7
Rasau WTP Form detail report
9. DESCRIPTION OF WORKS
Condition of material before & after unloading
9.1 Contractor
Pass Fail N/A
9.3 CA Representative
Pass Fail N/A
10.1 Contractor
Pass Fail N/A
10.3 CA Representative
Pass Fail N/A
11.1 Contractor
Pass Fail N/A
Created by zul nizam with Autodesk® Construction Cloud™ on Feb 1, 2024 at 9:28 AM UTC+08:00 Page 5 of 7
Rasau WTP Form detail report
11.3 CA Representative
Pass Fail N/A
12.1 Contractor
Pass Fail N/A
12.3 CA Representative
Pass Fail N/A
If any
Created by zul nizam with Autodesk® Construction Cloud™ on Feb 1, 2024 at 9:28 AM UTC+08:00 Page 6 of 7
Rasau WTP Form detail report
Remarks: If " Final Inspection" record Fail Status, Please refer to NCR.
Created by zul nizam with Autodesk® Construction Cloud™ on Feb 1, 2024 at 9:28 AM UTC+08:00 Page 7 of 7
Rasau WTP Form detail report
Form detail
Forms
Location
Description
Due date
Status In progress
1. Form Details
1.4 Location
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 12:02 PM UTC+08:00 Page 1 of 7
Rasau WTP Form detail report
1.9 Material
2. Description of works
Physical Inspection: Check layout & cable routing according to approved construction drawing.
2.1 Contractor
Pass Fail N/A
2.3 CA Representative
Pass Fail N/A
3. Description of works
Physical Inspection: Check all material brand and type are according to Approved Equipment and Material
List.
3.1 Contractor
Pass Fail N/A
3.3 CA Representative
Pass Fail N/A
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 12:02 PM UTC+08:00 Page 2 of 7
Rasau WTP Form detail report
4. Description of works
Physical Inspection: Inspect the cable to ensure no damage or defect to the jackets.
4.1 Contractor
Pass Fail N/A
4.3 CA Representative
Pass Fail N/A
5. Description of works
Physical Inspection: Check the cable labelling or tagging are done according to the installation drawing.
5.1 Contractor
Pass Fail N/A
5.3 CA Representative
Pass Fail N/A
6. Description of works
Network Cable Test: The CAT6 cable shall be crimped with the RJ45 connector or terminated to Ethernet
cable patch panel.
6.1 Contractor
Pass Fail N/A
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 12:02 PM UTC+08:00 Page 3 of 7
Rasau WTP Form detail report
6.3 CA Representative
Pass Fail N/A
7. Description of works
Network Cable Test: Both ends of the CAT6 cable are connected to the Cable Analyzer Main Tester and
Remote Tester according to the test configuration.
7.1 Contractor
Pass Fail N/A
7.3 CA Representative
Pass Fail N/A
8. Description of works
Network Cable Test: Follow the Cable Tester Screen Instruction, runtest from cable tester.
8.1 Contractor
Pass Fail N/A
8.3 CA Representative
Pass Fail N/A
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 12:02 PM UTC+08:00 Page 4 of 7
Rasau WTP Form detail report
9. Description of works
Network Cable Test: The Cable Tester will measure the following criteria automatically : 1) Wiremap 2)
Length 3) Propagation Delay 4) Delay Skew 5) Insertion Loss Margin 6) Frequency
9.1 Contractor
Pass Fail N/A
9.3 CA Representative
Pass Fail N/A
10.1 Contractor
Pass Fail N/A
10.3 CA Representative
Pass Fail N/A
11.1 Contractor
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 12:02 PM UTC+08:00 Page 5 of 7
Rasau WTP Form detail report
11.3 CA Representative
Pass Fail N/A
12.1 Contractor
Pass Fail N/A
12.3 CA Representative
Pass Fail N/A
13.1 Contractor
Pass Fail N/A
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 12:02 PM UTC+08:00 Page 6 of 7
Rasau WTP Form detail report
13.3 CA Representative
Pass Fail N/A
Created by project rasau wtp elec with Autodesk® Construction Cloud™ on Jan 5, 2024 at 12:02 PM UTC+08:00 Page 7 of 7
NETWORK CABLING (CAT6 & FIBRE OPTIC Cable) TEST
PROJECT NAME : Doc Ref. No : REVISION NO. : 00
NETWORK CABLING
TEST INSTRUMENT :
MANUFACTURER :