Patel Infrastructure Ltd.

NAME OF WORK :- Strengthening / Overlaying on Six lane Gurgaon -Kotputli-Jaipur section of NH 48 (Old NH-8) from Km 107+100 to Km 188+000 in the State of Rajasthan
CLIENT :- NATIONAL HIGHWAYS AUTHORITY OF INDIA
Engineer : - L.N. MALVIYA INFRA PROJECTS PVT. LTD.
CONTRACTOR :- Patel Infrastructure Ltd.
Date of Submission 28/Mar/24 RFI Summary Date of Inspection 29/Mar/24

Date of Date of
SL R.F.I. No. Component B.O.Q. Item No. Work Description From To Location Side Time Remarks
Submission Inspection
Highway
1 GKJ/NH-48/AE/HWY/2023-24/3415 28/03/2024 29/03/2024 Highway M-1.01 Milling of distress bitumenous layer ( Median Side ) 138+500 139+500 MCW RHS 08:00AM
2 GKJ/NH-48/AE/HWY/2023-24/3416 28/03/2024 29/03/2024 Highway M-1.01 Milling of distress bitumenous layer ( Shoulder Side ) 138+500 139+500 MCW RHS 08:10AM
3 GKJ/NH-48/AE/HWY/2023-24/3417 28/03/2024 29/03/2024 Highway M-4.02 Applying of Tackcoat on Milling 115+585 115+790 Toll Plaza LHS 08:30AM Offset 25.0 MTR
4 GKJ/NH-48/AE/HWY/2023-24/3418 28/03/2024 29/03/2024 Highway M-4.03 (B) Laying of DBM Top Layer Grade-II 115+585 115+790 Toll Plaza LHS 09:30AM Offset 25.0 MTR
5 GKJ/NH-48/AE/HWY/2023-24/3419 28/03/2024 29/03/2024 Highway M-4.02 Applying of Tackcoat on Milling ( Median Side ) 115+790 115+980 MCW LHS 08:00AM
6 GKJ/NH-48/AE/HWY/2023-24/3420 28/03/2024 29/03/2024 Highway M-4.03 (B) Laying of DBM Top Layer Grade-II ( Median Side ) 115+790 115+980 MCW LHS 09:00AM
7 GKJ/NH-48/AE/HWY/2023-24/3421 28/03/2024 29/03/2024 Highway M-4.02 Applying of Tackcoat on Milling ( Shoulder Side ) 115+790 115+980 MCW LHS 08:30AM
8 GKJ/NH-48/AE/HWY/2023-24/3422 28/03/2024 29/03/2024 Highway M-4.03 (B) Laying of DBM Top Layer Grade-II ( Shoulder Side ) 115+790 115+980 MCW LHS 09:30AM
9 GKJ/NH-48/AE/HWY/2023-24/3423 28/03/2024 29/03/2024 Highway M-4.02 Applying of Tackcoat on Milling ( Median Side ) 157+450 158+300 MCW LHS 08:30AM
10 GKJ/NH-48/AE/HWY/2023-24/3424 28/03/2024 29/03/2024 Highway M-4.03 (B) Laying of DBM Top Layer Grade-II ( Median Side ) 157+450 158+300 MCW LHS 09:00AM
11 GKJ/NH-48/AE/HWY/2023-24/3425 28/03/2024 29/03/2024 Highway M-4.02(a) Applying of tack coat 123+920 124+040 SR LHS 08:45AM
12 GKJ/NH-48/AE/HWY/2023-24/3426 28/03/2024 29/03/2024 Highway M-4.03(b) Laying of DBM top layer Grade-II 123+920 124+040 SR LHS 10:45AM
13 GKJ/NH-48/AE/HWY/2023-24/3427 28/03/2024 29/03/2024 Highway M-4.02(a) Applying of tack coat 124+580 124+800 SR RHS 08:45AM
14 GKJ/NH-48/AE/HWY/2023-24/3428 28/03/2024 29/03/2024 Highway M-4.03(b) Laying of DBM top layer Grade-II 124+580 124+800 SR RHS 10:45AM
15 GKJ/NH-48/AE/HWY/2023-24/3429 28/03/2024 29/03/2024 Highway M-4.02(a) Applying of tack coat 126+900 127+000 SR RHS 08:45AM
16 GKJ/NH-48/AE/HWY/2023-24/3430 28/03/2024 29/03/2024 Highway M-4.03(b) Laying of DBM top layer Grade-II 126+900 127+000 SR RHS 10:45AM
17 GKJ/NH-48/AE/HWY/2023-24/3431 28/03/2024 29/03/2024 Highway M-4.02(a) Applying of tack coat 127+400 127+600 SR RHS 08:45AM
18 GKJ/NH-48/AE/HWY/2023-24/3432 28/03/2024 29/03/2024 Highway M-4.03(b) Laying of DBM top layer Grade-II 127+400 127+600 SR RHS 10:45AM
19 GKJ/NH-48/AE/HWY/2023-24/3433 28/03/2024 29/03/2024 Highway M-4.01(a) Applying of primecoat 122+800 123+570 SR RHS 05:00 PM
20 GKJ/NH-48/AE/HWY/2023-24/3433 28/03/2024 29/03/2024 Highway M-4.01(a) Applying of primecoat 123+880 124+020 SR RHS 05:15 PM