Total 18,380
148+800 148+950 LHS MCW Milling for DBM Feb-24 1.00 150
151+900 152+650 LHS MCW Milling for DBM Feb-24 750
153+300 153+450 LHS MCW Milling for DBM Feb-24 150
160+800 160+900 LHS MCW Milling for DBM Feb-24 100
176+800 177+400 LHS MCW Milling for DBM Feb-24 600
Total 1,750
Page 7 of 12
PATEL INFRASTRUCTURE LIMITED
HIGHWAY Work FEB'24
Ch. From Ch. To Side CW Item Month Nos Length Width Depth Quantity
186+710 188+000 LHS MCW Milling for BC Feb-24 1.00 1,290
Total 39,960
Page 8 of 12
PATEL INFRASTRUCTURE LIMITED
HIGHWAY Work FEB'24
Ch. From Ch. To Side CW Item Month Nos Length Width Depth Quantity
Page 9 of 12
PATEL INFRASTRUCTURE LIMITED
HIGHWAY Work FEB'24
Ch. From Ch. To Side CW Item Month Nos Length
109+450 109+600 RHS MCW Milling for DBM Feb-24 1.00 150
109+700 109+800 RHS MCW Milling for DBM Feb-24 1.00 100
112+620 112+800 RHS MCW Milling for DBM Feb-24 1.00 180
115+900 116+420 RHS MCW Milling for DBM Feb-24 1.00 520
116+850 117+250 RHS MCW Milling for DBM Feb-24 1.00 400
119+050 119+500 RHS MCW Milling for DBM Feb-24 1.00 450
123+050 123+300 RHS MCW Milling for DBM Feb-24 1.00 250
124+600 124+700 RHS MCW Milling for DBM Feb-24 1.00 100
127+850 128+000 RHS MCW Milling for DBM Feb-24 1.00 150
129+700 130+490 RHS MCW Milling for DBM Feb-24 1.00 790
130+850 131+550 RHS MCW Milling for DBM Feb-24 1.00 700
132+750 132+850 RHS MCW Milling for DBM Feb-24 1.00 100
132+900 134+000 RHS MCW Milling for DBM Feb-24 1.00 1,100
135+000 135+700 RHS MCW Milling for DBM Feb-24 1.00 700
136+000 136+500 RHS MCW Milling for DBM Feb-24 1.00 500
136+900 141+000 RHS MCW Milling for DBM Feb-24 1.00 4,100
138+100 138+310 RHS MCW Milling for DBM Feb-24 1.00 210
139+600 140+200 RHS MCW Milling for DBM Feb-24 1.00 600
142+430 145+050 RHS MCW Milling for DBM Feb-24 1.00 2,620
145+300 146+200 RHS MCW Milling for DBM Feb-24 1.00 900
146+950 147+500 RHS MCW Milling for DBM Feb-24 1.00 550
147+500 147+700 RHS MCW Milling for DBM Feb-24 1.00 200
148+500 148+700 RHS MCW Milling for DBM Feb-24 1.00 200
149+200 149+500 RHS MCW Milling for DBM Feb-24 1.00 300
149+800 150+100 RHS MCW Milling for DBM Feb-24 1.00 300
150+700 151+000 RHS MCW Milling for DBM Feb-24 1.00 300
151+200 152+000 RHS MCW Milling for DBM Feb-24 1.00 800
152+450 152+550 RHS MCW Milling for DBM Feb-24 1.00 100
153+000 153+350 RHS MCW Milling for DBM Feb-24 1.00 350
153+900 154+100 RHS MCW Milling for DBM Feb-24 1.00 200
155+250 155+500 RHS MCW Milling for DBM Feb-24 1.00 250
160+900 161+200 RHS MCW Milling for DBM Feb-24 1.00 300
161+850 162+050 RHS MCW Milling for DBM Feb-24 1.00 200
PATEL INFRASTRUCTURE LIMITED
HIGHWAY Work FEB'24
Ch. From Ch. To Side CW Item Month Nos Length
163+100 163+600 RHS MCW Milling for DBM Feb-24 1.00 500
165+400 166+200 RHS MCW Milling for DBM Feb-24 1.00 800
167+000 167+150 RHS MCW Milling for DBM Feb-24 1.00 150
167+400 167+800 RHS MCW Milling for DBM Feb-24 1.00 400
169+000 169+200 RHS MCW Milling for DBM Feb-24 1.00 200
171+000 171+950 RHS MCW Milling for DBM Feb-24 1.00 950
173+400 173+900 RHS MCW Milling for DBM Feb-24 1.00 500
175+400 175+500 RHS MCW Milling for DBM Feb-24 1.00 100
175+600 175+900 RHS MCW Milling for DBM Feb-24 1.00 300
177+500 177+600 RHS MCW Milling for DBM Feb-24 1.00 100
178+150 178+250 RHS MCW Milling for DBM Feb-24 1.00 100
178+350 178+500 RHS MCW Milling for DBM Feb-24 1.00 150
178+850 178+950 RHS MCW Milling for DBM Feb-24 1.00 100
183+700 183+800 RHS MCW Milling for DBM Feb-24 1.00 100
Total 23,120
108+700 109+100 LHS MCW Milling for DBM Feb-24 1.00 400
109+300 110+350 LHS MCW Milling for DBM Feb-24 1.00 1,050
110+700 110+900 LHS MCW Milling for DBM Feb-24 1.00 200
111+100 111+240 LHS MCW Milling for DBM Feb-24 1.00 140
111+900 112+300 LHS MCW Milling for DBM Feb-24 1.00 400
112+500 112+950 LHS MCW Milling for DBM Feb-24 1.00 450
112+900 113+090 LHS MCW Milling for DBM Feb-24 1.00 190
116+500 116+710 LHS MCW Milling for DBM Feb-24 1.00 210
117+400 117+756 LHS MCW Milling for DBM Feb-24 1.00 356
118+000 118+120 LHS MCW Milling for DBM Feb-24 1.00 120
118+300 118+400 LHS MCW Milling for DBM Feb-24 1.00 100
119+580 119+700 LHS MCW Milling for DBM Feb-24 1.00 120
119+900 120+290 LHS MCW Milling for DBM Feb-24 1.00 390
121+100 121+600 LHS MCW Milling for DBM Feb-24 1.00 500
121+850 122+200 LHS MCW Milling for DBM Feb-24 1.00 350
123+200 123+520 LHS MCW Milling for DBM Feb-24 1.00 320
PATEL INFRASTRUCTURE LIMITED
HIGHWAY Work FEB'24
Ch. From Ch. To Side CW Item Month Nos Length
150+400 150+600 LHS MCW Milling for DBM Feb-24 1.00 200
152+400 152+500 LHS MCW Milling for DBM Feb-24 1.00 100
153+000 153+450 LHS MCW Milling for DBM Feb-24 1.00 450
160+400 160+600 LHS MCW Milling for DBM Feb-24 1.00 200
160+800 160+900 LHS MCW Milling for DBM Feb-24 1.00 100
161+950 162+200 LHS MCW Milling for DBM Feb-24 1.00 250
164+300 164+560 LHS MCW Milling for DBM Feb-24 1.00 260
165+600 165+800 LHS MCW Milling for DBM Feb-24 1.00 200
166+400 166+600 LHS MCW Milling for DBM Feb-24 1.00 200
168+000 168+500 LHS MCW Milling for DBM Feb-24 1.00 500
176+300 177+400 LHS MCW Milling for DBM Feb-24 1.00 1,100
177+500 177+650 LHS MCW Milling for DBM Feb-24 1.00 150
180+200 180+400 LHS MCW Milling for DBM Feb-24 1.00 200
183+800 185+080 LHS MCW Milling for DBM Feb-24 1.00 1,280
185+200 185+500 LHS MCW Milling for DBM Feb-24 1.00 300
Total 10,786