Professional Documents
Culture Documents
Main Dorm Repair 2020 Budgetary
Main Dorm Repair 2020 Budgetary
I.Demolition and disposal of existing roofing, roof framing, ceiling, doors & windows
Labor cost: Utilize:
Foreman 1.00 Manday 380.00 380.00
Carpenter 2.00 Mandays 330.00 660.00
Hauling Truck 0.50 rent day 8,000.00 4,000.00
Driver 0.50 manday 330.00 165.00
Laborer 5.00 Mandays 280.00 1,400.00
6,605.00
Duration = 15 day
Total Labor Cost 99,075.00
Total Cost for LAY OUT & STAKING 99,075.00
0.4mm thk x 1.03m E.W. X 7.20m Pre-painted Roofing 34.00 shts 3,240.00
0.4mm thk x 1.03m E.W. X 8.30m Pre-painted Roofing 196.00 shts 3,735.00
0.4mm thk x 1.03m E.W. X 6.30m Pre-painted Roofing 24.00 shts 2,835.00
0.4mm thk x 1.03m E.W. X 2.10m Pre-painted Roofing 61.00 shts 945.00
0.4mm thk x 0.45m x 2.40m Pre-painted, Pre-moulded, Ridge roll 62.00 shts 550.00
self drilling metal screw 10,500.00 pcs 2.00
Vulca Seal 15.00 sachet 120.00
Material Cost
Labor cost: Utilize:
Foreman 1.00 Mandays 380.00 380.00
Lather 1.00 Mandays 330.00 330.00
Laborer 3.00 Mandays 280.00 840.00
Electric Drill 1.00 Renday 300.00 300.00
1,850.00
Output 10.00 shts per day
Duration = 37.70 say
Total Labor Cost 70,300.00
Total Cost for ROOFING & ACC. 1,095,105.00
Summary
Material Description Qty Unit Unit Price Amount
4 bays x 1.50m x 5mm thk clear glass steel casement window (W1) 69.00 pcs 7,020.00 484,380.00
Material Cost 484,380.00
Area = 1,597.62
Latex Paint 191.71 gals 600.00 115,028.64
Skim Coat Primer 199.70 bags 500.00 99,851.25
Non Sag Concrete Epoxy 5.00 gals 1,200.00 6,000.00
6" Paint Roller w/ tray 20.00 sets 85.00 1,700.00
4" Paint brush 10.00 pcs 45.00 450.00
1/8 Liter Latex Tinting Color 10.00 cans 110.00 1,100.00
Carborandum Paper # 80 (1.00 sq.ft.) 100.00 pcs 18.00 1,800.00
Material Cost 225,929.89
Labor cost: Utilize:
Paintor 5.00 Mandays 330.00 1,650.00
1,650.00
Output: 150.00 sq.m. per coat day
Duration = 31.95 say
Total Labor Cost 52,800.00
pcs 1,375.32
pcs 987.22
pcs 1,268.56
pcs 813.89
pcs 876.06
pcs 587.81
pcs 1,444.40
pcs 1,017.36
pcs 1,017.36
pcs 562.69
pcs 788.14
pcs 542.59
pcs 631.14
pcs 391.87
pcs 304.58
pcs 140.67
pcs 7,564.16
pcs 282.60
pcs 402.80
pcs 455.80
pcs
pcs 266.96
pcs 176.72
pcs
23,057.36 kgs
110,160.00
732,060.00
68,040.00
57,645.00
34,100.00
21,000.00
1,800.00
1,024,805.00
38.00 days
20.00 days
14.00 days
82.00 days
57.00 days
sq.m.
32.00 days
sq.m.
27.00 days
sq.m.
sq.m.
cu.m.
4.00 days
2.00 days
3.00 days
sq.m.
sq.m.
sq.m.
t day
32 days for 3 coats
278,729.89
t day
46 days for 3 coats
243,510.82
Project: Boy's Dormitory Main Improvement
(Repainting, Ceiling and Tiling)
Subject: Detailed Estimates & Unit Cost Derivation
I Demolition of existing roof, bleachers & stage 1.00 lot 99,075.00 8.00% 10.00% 3.00% 21.00% 20,805.75 11,988.08 32,793.83 131,868.83 131,868.83
II Roof Framing 23,057.36 kgs 2,074,180.67 8.00% 10.00% 3.00% 21.00% 435,577.94 250,975.86 686,553.80 2,760,734.47 119.73
III Roofing & Accessories 2,203.60 sq.m. 1,095,105.00 8.00% 10.00% 3.00% 21.00% 229,972.05 132,507.71 362,479.76 1,457,584.76 661.46
IV Fiber cement board ceiling in Light Metal Frame
A. Exterior ceiling, Fascia Board and AV Grills 393.12 sq.m. 507,445.41 8.00% 10.00% 3.00% 21.00% 106,563.54 61,400.90 167,964.43 675,409.85 1,718.08
B. Interior Ceiling 1,634.40 sq.m. 733,070.33 8.00% 10.00% 3.00% 21.00% 153,944.77 88,701.51 242,646.28 975,716.61 596.99
V Doors & Windows
A. Wooden Doors on Steel Jambs 119.07 sq.m. 552,770.00 8.00% 10.00% 3.00% 21.00% 116,081.70 66,885.17 182,966.87 735,736.87 6,179.03
B. Steel Casement Windows 186.30 sq.m. 521,910.00 8.00% 10.00% 3.00% 21.00% 109,601.10 63,151.11 172,752.21 694,662.21 3,728.73
C. Glass Doors and Windows 60.21 sq.m. 173,103.75 8.00% 10.00% 3.00% 21.00% 36,351.79 20,945.55 57,297.34 230,401.09 3,826.63
D. Aluminum Mosquito Screen Windows 235.80 sq.m. 406,755.00 8.00% 10.00% 3.00% 21.00% 85,418.55 49,217.36 134,635.91 541,390.91 2,295.98
E. Steel Panel Door (Emergency Exit Door) 4.00 sets 44,840.00 8.00% 10.00% 3.00% 21.00% 9,416.40 5,425.64 14,842.04 59,682.04 14,920.51
VI Concrete Works (provision for doors, windows & elect. 10.54 cu.m. 52,335.00 8.00% 10.00% 3.00% 21.00% 10,990.35 6,332.54 17,322.89 69,657.89 6,606.40
VII Dry Wall and Air Vents 22.50 sq.m. 19,370.00 8.00% 10.00% 3.00% 21.00% 4,067.70 2,343.77 6,411.47 25,781.47 1,145.84
VIII Painting Works
A. CHB Wall & Concrete Surfaces 1,597.62 sq.m. 278,729.89 8.00% 10.00% 3.00% 21.00% 58,533.28 33,726.32 92,259.59 370,989.48 232.21
b. Wooden Surfaces 2,265.66 sq.m. 243,510.82 8.00% 10.00% 3.00% 21.00% 51,137.27 29,464.81 80,602.08 324,112.90 143.05
IX Electrical Works 1.00 lot 530,580.00 8.00% 10.00% 3.00% 21.00% 111,421.80 64,200.18 175,621.98 706,201.98 706,201.98
X Temporary Facilities 1.00 lot 45,000.00 8.00% 10.00% 3.00% 21.00% 9,450.00 5,445.00 14,895.00 59,895.00 59,895.00
TOTAL 7,377,780.87 1,549,333.98 892,711.49 2,442,045.47 9,819,826.34
Budgetary Estimates
Item No. Work Item / Description Quantity Unit Unit Cost Total Cost
I Demolition of existing roof, bleachers & stage 1.00 lot 131,870.00 131,870.00
II Roof Framing 23,060.00 kgs 120.00 2,767,200.00
III Roofing & Accessories 2,205.00 sq.m. 662.00 1,459,710.00
IV Fiber cement board ceiling in Light Metal Frame
A. Exterior ceiling, Fascia Board and AV Grills 395.00 sq.m. 1,720.00 679,400.00
B. Interior Ceiling 1,635.00 sq.m. 630.50 1,030,867.50
V Doors & Windows
A. Wooden Doors on Steel Jambs 119.10 sq.m. 6,180.00 736,038.00
B. Steel Casement Windows and window grills 187.00 sq.m. 3,830.00 716,210.00
C. Glass Doors and Windows 61.00 sq.m. 3,827.00 233,447.00
D. Aluminum Mosquito Screen Windows 236.00 sq.m. 2,350.00 554,600.00
E. Steel Panel Door (Emergency Exit Door) 4.00 sets 14,932.00 59,728.00
VI Concrete Works (provision for doors, windows & elect.) 18.80 cu.m. 6,607.00 124,211.60
VII Dry Wall and Air Vents 20.00 sq.m. 1,146.00 22,920.00
VIII Painting Works
A. CHB Wall & Concrete Surfaces (skim coat) 1,598.00 sq.m. 235.00 375,530.00
b. Wooden Surfaces 2,266.00 sq.m. 151.00 342,166.00
IX Electrical Works 1.00 lot 706,201.98 706,201.98
X Temporary Facilities 1.00 lot 59,895.00 59,895.00
Total Project Cost 9,999,995.08
say 10,000,000.00
VI Masonry Works
a. 4" CHB Wall w/ 10mm Ø rebars #REF! #REF! #REF! #REF!
70
b. Louver Wall #REF! #REF! #REF! #REF!
c. Plastering (Plain Cement Finish) #REF! #REF! #REF! #REF!
d. Tiles #REF! #REF! #REF! #REF! 60
Accomplishment 3.29 5.63 6.57 7.51 7.51 6.57 6.57 6.57 6.57 6.57 6.57 6.57 4.69 4.23 4.23 3.76 3.76 2.82
Commulative Accomplishment 3.29 8.92 15.49 23.00 30.51 37.08 43.65 50.22 56.79 63.36 69.93 76.50 81.19 85.42 89.65 93.41 97.17 100
Prepared by: Submitted by: Conforme: Recommending Approval: Approved:
Calendar Days
Category
5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90
Bagger Mixer 1 1 1 1 1
Concrete Vibrator 1 1 1 1 1
Plate Compactor 1 1
Bar Cutter 1 1 1 1
Welding Machine 1 1 1 1 1 1 1 1 1 1 1 1
Acy-Oxygen 1 1 1 1 1 1 1 1 1 1 1 1
Electric Grinder 1 1 1 1 1 1 1 1 1 1 1 1
Electric Planner 1 1 1 1 1 1 1 1 1 1 1 1
Pipe Threader 1 1
TOTAL 0 1 3 6 7 7 6 4 4 4 4 5 5 4 4 1 1 0
Calendar Days
Category
5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90
Project Engineer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Foreman 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Warehouseman 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Carpenters 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Mason 2 2 2 2 2 2 2 2 2 2
Steelman 2 2 2 2
Welder 1 1 1 1 1 1 1 1 1 1 1 1
Lather 1 1 1 1
Plumber 1 1
Electrician 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Laborer 2 5 5 5 5 5 5 5 5 5 5 3 2 2 2 2 2 1
TOTAL 7 12 14 16 16 14 14 14 14 14 14 14 11 10 10 8 8 6
Approved:
Approved:
ABDURRAHMAN T. CANACAN
ellor