Professional Documents
Culture Documents
R 03 Lifting and Shifting Work Permit
R 03 Lifting and Shifting Work Permit
List of Tools & Tackles to be used for Name(s) of workmen Documents attached:
the work: involved: 1. Test Certificates- 2. Lift Plan-
3. Load Chart- 4. JSA/HIRA-
4 Third party inspection certificates available for all tools & equipment’s.
The system to be isolated and proved dead as per LOTO procedure (Tick √
applicable)
5
Electrical Mechanical Specify any other Energy presence
7 Are the PUC Certificate and Vehicle Fitness Certificate from RTO, available?
Has the lifting equipment been examined at least once in the last 12
months by an authorized examiner (third party) and does it possess valid
8
lifting equipment certificate
Is the driver competent to handle the equipment? Does he have the license
9 for Heavy Transport Vehicle?
Has the actual weight of the load been handled, established and within the
10 Safe Work Load of the equipment? Wt. of load: ______
Is the hook of the equipment in good condition and has been provided with
11
a locking latch?
12 Is the Load Test Certificate of the hook available?
Is the load likely to clash with other structures or equipment along its
13
lifting path?
22 Supervisor present at the job site till the time the job is completed?
Permit Initiator
(Contractor PM / Engineer & safety)
Permit is issued based on work progress schedule & on the above declaration from the contractor. In case of any
NC noticed by M Moser/ consultant/client during site rounds, necessary actions as per Contract/Statutory
conditions shall be taken.
The safety precautions and safe conditions mentioned above have been verified and work can be started.
Permit is granted & valid up to date ………………………………& time: from………………. to ………………………..
B. Permit Closure:
The above-mentioned job has been completed satisfactorily. Date…………………………………. & Time ……………………………… this
permit is closed.
Permit Initiator
(Contractor PM / Engineer & Safety)