F.L. RAMOS CONSTRUCTION CO., INC.

OWNER: PHINMA PRISM PROPERTY DEVELOPMENT CORPORATION


PROJECT: Likha Residences (Alabang)-CP-01 (STRUCTURAL WORKS of SIX (6) UNITS)
LOCATION: Likha Residence, Km. 19, Brgy. Cupang, Muntinlupa

CONSTRUCTION PHASING PLAN

STAGES OF CONSTRUCTION DURATION

1.00 EARTHWORKS
» March 18, 2024 to May 9, 2024 41 days

2.00 SUBSTRUCTURE
a. Footings
» March 29, 2024 to April 17, 2024 8 days

b. Footing Tie Beams


» April 10, 2024 to April 23, 2024 12 days

c. Columns from Foundation to Ground Floor Level


» April 6, 2024 to April 17, 2024 9days

d. Slab-on-grade
» June 15, 2024 to June 22, 2024 7 days

3.00 SUPERSTRUCTURE
a. Columns from Ground Floor to Roofs
a.1 Ground Floor to Second Floor
» April 18, 2024 to April 26, 2024 8 days

a.2 Second Floor to Third Floor


» May 13, 2024 to May 21, 2024 8 days

a.3 Third Floor to Roof Beam


» June 08, 2024 to June 15, 2024 6 days

b. Suspended Beams and Slabs


b.1 Second Floor
» May 1, 2024 to May 13, 2024 10 days

b.2 Third Floor


» May 28, 2024 to June 7, 2024 10 days

4.00 MASONRY WORKS


a. CHB Laying
a.1 Second Floor
» June 15, 2024 to June 29, 2024 13 days

a.1 Third Floor


» June 20, 2024 to July 3, 2024 12 days

a.1 Ground Floor


» July 3, 2024 to July 13, 2024 10 days

b. Plastering Works
b.1 Interior Second Floor
» June 17, 2024 to June 29, 2024 12 days

b.2 Interior Third Floor


» July 4, 2024 to July 17, 2024 12 days
b.3 Interior Ground Floor
» July 6, 2024 to July 17, 2024 10 days

b.4 Exterior Second Floor


» June 17, 2024 to June 29, 2024 12 days

b.5 Exterior Third Floor


» July 6, 2024 to July 19, 2024 12 days

b.6 Exterior Ground Floor


» June 30, 2024 to July 11, 2024 10 days

5.00 MEPF Rough-ins


a. Plumbing Rough-in works
a.1 Second Floor
» May 8, 2024 to July 6, 2024 51 days

a.1 Third Floor


» June 3, 2024 to August 1, 2024 51 days

a.1 Ground Floor


» June 20, 2024 to July 24, 2024 30 days

b. Electrical Rough-in works


a.1 Second Floor
» May 8, 2024 to July 6, 2024 51 days

a.1 Third Floor


» June 3, 2024 to August 1, 2024 51 days

a.1 Ground Floor


» June 20, 2024 to July 24, 2024 30 days

c. Utilities
» June 7, 2024 to July 25, 2024 41 days

DATE OF TURN-OVER: AUGUST 10, 2024