SOW For BF5 Annual Maintenace Jobs
SOW For BF5 Annual Maintenace Jobs
SOW For BF5 Annual Maintenace Jobs
NOTE: -
1. 100% Man power availability to be ensured. If not penalty will be imposed 0.5% of PO value. (Above
95% to 100%). Absent persons has to be replace within 3 to 5 days.
2. Equipment availability 98 % should be maintained. If any breakdown happens due to the inefficiency
of the workmanship same will be penalized based on the severity
3. All equipment’s check list has to be filled and signature with respective area in charge of as per the
schedule.
4. During breakdown man power must be continue up to completion of the work.
5. Technician can go on long leave after deploying the reliever
6. JVML approved technicians & supervisor only allowed to work for all concerned area.
1. SCOPE OF WORK FOR AIR COMPRESSORS & DRYERS MAINTAINANCE
WORK INSTRUCTION:
□ Periodical maintenance (Routine, Condition based, Preventive & Breakdown) of the equipment’s
in Compressor Air station.
□ Activity including hourly maintenance of the compressors & Dryers
□ Contract should own responsibility for complete maintenance and availability of all the
equipment’s to meet JVML targets for the quality air generation
□ Condition based maintenance using different techniques (like SPM etc.) to maintain equipment
healthiness good all the time. (Frequency every 2months) or As per OEM recommendations
□ Repair of Dryers ( gas filling, filter cleaning, brazing with required consumables & small fittings,
, leakage testing etc )
□ Team shall be available from 09:00 to 18:00 hours throughout the year for daily preventive
maintenance jobs.
□ Contractor should depute Sufficient and Skilled manpower (as per contract) to meet the daily
requirement.
□ Timings should not be the constraint during emergency or planned shutdown jobs execution.
Completion of the job and keeping system available all the time is important.
□ Contract Engineer should monitor all the equipment’s regularly & should interact with
JVMLofficials for planning and execution of jobs on regular basis
□ Manpower should be available round the clock for attending any emergency breakdowns
orsituations and also include small cpp activities
□ Contractor should ensure good housekeeping all the time in the related area.
□ Major jobs will be planned and contractor shall be informed well in before to arrange and
organize the resources for the successful execution within the time frame put by JVML.
□ All the procedures as per ISO 9001, 14001 and OSHAS 18001 to be strictly followed.
□ General Tools & Tackles (up to 46 mm spanner etc.), suitable welding machine, special testing
& condition check machine like SPM are under contractor scope. However, any lifting facilities,
lighting in unrestrictive access shall be in JVML Scope.
□ All safety PPE’s shall be under contractor’s scope & health check as per JVML norms
□ Contractor should submit Reports periodically & regularly as per JVML requirement to justify
the status the equipment. Contractor has to be submit all the preventive maintenance plans
and compliances.
□ Shifting of spares from central stores and CRS (required for maintenance of the system)
whenever required to be carried out by contractor itself and transportation facility to execute
above things will be under contractor scope only.
□ Cutting sets and welding machine should be brought by the contractor to meet the daily work
requirement.
□ Spares Parts, lubricants & cleaning material shall under JVML scope.
□ Competent authority should be deputed by the contractor all the time to ensure quality
maintenance
1. Preparatory Jobs:
□ All the tools required, spares required for particular work of compressor/dryer to be arrangedwell
in advance.
□ Communication to operation in charge/mechanical and electrical regarding service plan of
particular compressor.
□ Required lighting arrangement for the work area.
□ Trials of compressor/dryer & Wait until normal running condition achieved & Complete
housekeeping.
A. Tools Required:
□ Standard tool box, first aid kit, Gas welding/brazing set, Allen key set 1-10mm-1set, welding
machine, Cutting set along with trolley
C. Safety:
D. Up keeping:
□ During job execution and after completion of the job, site should be maintained neat and clean.
□ Scraps, oil and grease should be cleaned immediately after job completion.
□ All removed items should be shifted to designated place (Metallic /Nonmetallic)
E. Contractor scope:
F. JVML Scope:
□ Work permit.
□ Corporate standard safety certificates. Contractor has to full fill all the requirements which are
required for each safety certificate.
□ Drinking water at overhead tank zero meter.
□ All spares & Consumables as required for maintenance of Compressors & Dryers
□ Single phase power point at compressor house for vacuum pump.
□ Air hose.
2. SCOPE OF WORK FOR ELECTRICAL WIRE ROPE & CHAIN
HOISTMAINTENANCE
SlNo
Description of work UOM Qty Service code
1 MNTN:EQUIP,GNRC;MNTCE,HOIST & CRNE,SVC MON 12 SPM7315210101025
HIRE: MANPOWER;SKILL
2 LEVEL:HIGHSKILLED; mmn 12 SCS93141802 00370
TYPE:SUPERVISOR;
HIRE: MANPOWER;SKILL LEVEL:SKILLED;
3 TYPE:TECHNICIAN;JOB TITLE:SENIOR mmn 24 SCS9314180201027
TECHNICIAN;
HIRE: MANPOWER;SKILL SCS93141802 00029
4 LEVEL:SKILLED;TYPE:AS PERSOW;JOB
mmn 12
TITLE:HELPER
1. Preparatory Jobs:
□ Shifting of required spares from stores to work location.
□ Preparation of gaskets, shifting of all required fasteners.
□ All activities including arrangement for lifting like hook welding, beam welding
& smallmodification to be done by contractor.
□ All lifting tackles to be arranged by contractor.
□ All temporary approaches for work location required for fixing of new hinges to
be done bycontractor.
6. Spare parts:
□ OEM recommended spares & Consumables
B. Tools Required:
□ Welding machine with welding cables, power cable and plug tops as in BF: 5, welding
machinecheck list, Consumables as required for the job & welding face shield.
□ Gas cutting set with trolley, check list, spare gas cylinders as required for the job.
□ Standard tool box.
□ Certified chain pulley blocks, wire rope slings & D-Shackles.
□ Buffing machines with power cable and plug tops
C.Steel requirements: -NIL-
D.Safety:
1 PTW Applicable
2 CSE Not Applicable
3 WAH Applicable
4 LOTO Applicable
5 MG Applicable
6 ESS Applicable
7 PPE’s Applicable
8 Conveyor Safety Not Applicable
9 Scaffolding Applicable
10 L&H Applicable
11 G&A Applicable
12 Chemical safety Not applicable
13 Fall of object Applicable
14 Fire Prevention Applicable
G. JVML Scope:
□ Work to permit (For each working group one dedicated contractor supervisor should beavailable )
□ Corporate standard safety certificates (For each working group one dedicated
contractorsupervisor should be available) and contractor has to full fill all the requirements which
are required for each safety certificate.
□ Welding power point at respective working area.
□ One 2 phase power point respective working area. (Grinding, Buffing machine).
□ Air supply point for Pneumatic wrench (25 mm) with Chicago coupling at respective working area.
□ Contractor Scope:
□ Any material shifting from central store to BF#5 under contractor scope
□ While working area CO-monitor carry under contractor scope.
□ Welding machine with welding cables, power cable and plug tops as in BF:03, welding machine
check list, Consumables as required for the job & welding face shield
□ Gas cutting set with trolley, check list, spare gas cylinders as required for the job.
□ Standard tool box
□ Certified chain pulley blocks, wire rope slings & D-Shackles
□ Buffing machines with power cable and plug tops.
□ Cutting set and welding machine all contractor scope
□ Any modification to be done under contractor scope.
□ Certified chain pulley blocks, wire rope slings & D-Shackles
□ Daily attending 9.00 am to 6.00 pm and every month 26 days’ hoist maintenance to be done
□ If any break down and shutdown attending food and transportation under contractor scope.
□ Buffing machines with power cable and plug top under contractor scope
□□□□□□
1. Before planned shutdown respected hoists or cranes should check and take trail, availability must be 100 %.
2. During shutdown concerned area hoist maintenance technicians must available round the clock for emergency
maintenance work up to end of the shutdown.
3. If hoist & cranes not ready detailed discussion to be had with concerned area in charges and solve the problem on
priority basis.
A.Preparatory Jobs:
□ Shifting of materials from stores/ I-shop to work location.
□ Shifting of all required tools and tackles, jacks, slings-shackles, Welding machines etc.
□ All activities including arrangement for lifting like hook welding, beam welding &
small modification to be done by contractor.
□ All structural materials required to be shifted to site before work start.
□ All temporary approaches for work location required for fixing of new hinges to be done by
contractor.
B. Detail Job procedure for Torpedo ladle car PMI Daily activities: -
□ Welding machine with welding cables, power cable, plug tops as in BF:5, welding machine
check list, Consumables (welding rods) as required for the job & welding face shield
□ Gas cutting set with trolley, check list, spare gas cylinders as required for the job Standard tool box
& First aid kit
□ Certified chain pulley blocks(3Ton-2Nos,4Ton-2nos) wire rope slings (5Ton & 10Ton each 4
nos) & D-Shackles
□ Hammering Ring & D Spanners 30 & 46 & Pneumatic operated wrenches with hoses and
bits (1&11/2) as required for the job
□ Nylon rope 50mtrs required & Grinding & Buffing machines with power cable and plug top
D. Safety:
1 PTW Applicable
2 CSE Applicable
3 WAH Applicable
4 LOTO Applicable
5 MG Applicable
6 ESS Applicable
7 PPE’s Applicable
8 Conveyor Safety Not Applicable
9 Scaffolding Applicable
10 L&H Applicable
11 G&A Applicable
12 Chemical safety Not applicable
13 Fall of object Applicable
14 Fire Prevention Applicable
E . Housekeeping:
□ During job execution and after completion of the job, site should be maintained neat and
clean.
□ Scraps and grease should be cleaned immediately after job completion.
□ All removed items should be shifted to designated place (Metallic /Nonmetallic)
F . Contractor scope:
Indicative manpower: 4
Description Bagfilter & pulsing system Dust handling system equipment list
Of system
BF#5 Bagfilter Bags RAV
Cages Screw conveyor
Chamber Pulsing system & Pneumatic Manual slide gate
manifold Vibrating Screen
Compressed air system Drag Chain Conveyor
PCI Storage silo Vent filter monitoring & Pulsing system inspection
vent filters replacement Vent Valves and Control Valve
□ All false air suction to be arresting by using suitable gaskets /welding etc.
□ Checking of pulsing system & replacement of pulse valve & accessories of pulsing system
□ Sampling point provision if required for any reason the same nozzle to be welded & nozzle willbe
provided by JVML
□ Checking & replacement of bag filter chambers, pulsing pipes, inlet isolation valve,
poppet damper etc.
□ Minimum 1 time the total bag filter inspection/rectification is under contractor scope every 3
months. The bags will be provided by JVML. If required maximum100 bags replacement to be
done freeof cost whenever it is required.
□ If bags are damaged & there is dust emission, then contractor to mobilize additional
manpower to change bags on 24 hrs. Basis without disturbing routine manpower.
□ Any steel work less than or equal to 2 tons (bag filter baffle plate fixing/pad welding in bag
filter/manhole fixing etc.) to be done free of cost for every 6 months
□ All dust leakages from hopper /RAV/ screw conveyor/Gate Valve/any connection will have to be
attended on top priority only steel; gasket will be provided by JVML.
□ Rectification of RAV/screw conveyor /valve/bellow less than DN600 are to be done on top
priority. The actuator part of the slide to be replaced on need basis. The shifting of actuator
under contractor scope
□ Rectification of Air/N2 line less than 4 inch & other fittings are under contactor scope
□ Tightening of chimney base bolts, cleaning of chimney from small scarp, welding of duct
support of ID fan inlet & outlet etc. are in contactor scope
□ Repair of dust transport system including puncher arresting, bend replacement, pipe
replacement, valve replacements below DN250 including cylinder.
□ Storage silo vent filter maintenance / replacement
3. Bags changing
□ Shifting of new bags from store to bag filter top
□ Isolation of chamber from system by closing inlet valve & poppet damper
□ Isolation of compressed air system /pulsing system
□ Opening of bag filter top cover
□ Removal of pulsing pipes
□ Inspection of bags using hand lamp/torch & identifying of dirty bag/puncher bags
□ Removal of cages & insertion of new bags along with cages
□ Normalization of system
□ Shifting of old bags to designated dumping yard
□ All the precision tools like dial gauge, dial gauge stand, filler gauge etc to be brought by the
contactor
□ The contactor should provide skilled & experienced personal to carry out the activity
□ Leveling of area /backfilling of area /civil grouting under JVML scope
□ Small structural modification required to remove/shift material/Fan/motor under contractorscope,
the material will be issued free of cost by JVML
□ All chain blocks & slings to be under contractor scope
□ All normal tools/ tackles & welding m/c, cutting set, oxygen, welding rods, DA, chain block less
than 5 tons under contactor scope. Minimum 2 set of tools for BF#5 required ondaily basis
□ Consumables like cotton waste, grease, marking cloth, cleansing agent will be provided by
JVML
□ All preparatory jobs like puller fabrication, scaffolding where ever required, lifting
arrangement etc. to be done by contactor before starting the job
□ The contractor should stay till trail run & satisfactory running of equipment taken for repair
□ All PPE’s should be provided by contractor
□ General housekeeping to be done after completion of the work
□ Work permit/confined space permit system to strictly followed by contactor
12. Safety:
1 PTW Applicable
2 CSE Applicable
3 WAH Applicable
4 LOTO Applicable
5 MG Applicable
6 ESS Applicable
7 PPE’s Applicable
8 Conveyor Safety Applicable
9 Scaffolding Applicable
10 L&H Applicable
11 G&A Applicable
12 Chemical safety Not applicable
13 Fall of object Applicable
14 Fire Prevention Applicable
1. All JVML approved PPE’s should be provided to workforce by contractor.
2. All workers should undergotraining of JVML Corporatestandards also all of
them should have medical certificate. The same to furnished if asked.
3. For welding m/c and cuttingset, JVML standard checklistshould be followed.
4.
5. The following are the safetystandards are applicable during jobs. SCOPE OF WORK FOR
STOCK HOUSE MAINTENANCE
Indicative manpower: 10
Detail Job procedure for Monthly CLITA activities like Inspection conveyor components, all types of
gates, receiving & discharge chute. Lubrication of pulley bearings, gear couplings & gates, PMI jobs like
checking & tightening of all fasteners of components, 5 's activities, Plat form opening & closing,hand rail
fixing, conveyor belt tracking etc
2. Tools Required:
□ Welding machine with welding cables, power cable, plug tops as in BF:5, Consumables as
required for the job & welding face shield
□ Gas cutting set with trolley, spare gas cylinders as required for the job
□ Standard tool box.
□ First aid kit.
□ Certified chain pulley blocks 2nos 3T capacity (each 2nos) , wire rope slings & D-Shackles
□ Ring & D Spanners 24 to 36. Standard Hammer
□ Buffing machines with power cable and plug top as in BF:5
3. Safety
:
1 PTW Applicable
2 CSE Applicable
3 WAH Applicable
4 LOTO Applicable
5 MG Applicable
6 ESS Applicable
7 PPE’s Applicable
8 Conveyor Safety Applicable
9 Scaffolding Applicable
10 L&H Applicable
11 G&A Applicable
12 Chemical safety Not applicable
13 Fall of object Applicable
14 Fire Prevention Applicable
4. Housekeeping:
□ During job execution and after completion of the job, site should be maintained neat and clean.
□ Scraps and grease to be clean immediately after job completion.
□ All removed items should be shifted to designated place (Metallic / Nonmetallic) `
5. Contractor scope:
□ Contractor has to mobilize manpower in shifts on 8hrs basis and if require technicians has to
continue in breakdown /emergency situations on OT basis .
Shifting of required materials from Central stores /Sub stores /CTL /CRS
□ Any small modification required for the job.
□ All required Tools and tackles for the job is under contractor scope. (welding machine, cuttingset
with cylinders, hammers, standard tool box, slings with ‘D’ Shackles, Grinding machine etc.,).
Competent authority certification for Lifting machines tools & tackles.
□ All required and standard PPE’S for the job is under contractor scope.
6. JVML Scope:
□ Issue of Work to permit
□ Corporate standard safety certificates
□ And contractor has to full fill all the requirements which are required for each safety certificate
□ Drinking water at stock house operation office.
□ One welding power point at each platform.
□ One 2 phase power point at platform (Grinding, Buffing machine).
Indicative manpower: 10
A-Schedule of Quantity.
Sl Description of work Details UOM Quantity in terms of freeof Re
no cost activity / m
replacement ar
k
1 General up keeping & inspection As per SOW Lot Regular
/rectification of de sys
2 Bag filter Maintenance As per SOW Lot As & when required
3 Padding & rectification of de sys AS per SOW Meter As & when required /500
ducts square meter square
4 Fabrication of general structure As per SOW Tons 12 tons/6 months including
BF#3 & BF#4 de sys
5 RAV replacement As per SOW Nos As & when required
1. General
1. To check the operation of bag filter& report abnormality
2. Maintaining operational data of each system as per format approved by user dept
3. Planning for maintenance of de system including spare/inventory management/strictlyfollowing
work permit system
4. Coordination for timely disposal of dust with operations dept.
5. Maintaining of good housekeeping of de system area
6. Checking/repair of dampers & coordinating with respective control room/operations to get
better efficiency
7. Any steel, spare requirement to be submitted before 30 days to concerned JVML personal so asto
arrange the same
8. All equipment lubrication schedule & checklist for lubrication to be done as per approved list
provided by JVML
9. All equipment CLITA and PMI schedule provided by JVML should be followed strictly any
deviation on equipment’s should be informed.
10. Any leakage of oil /grease to be arrested as early as possible to maintain the cleanliness & alsoto
reduce oil/grease consumption. The party to submit monthly oil/grease consumption report.
11. All handrails /platform in de sys area to be maintained & should strengthen the same if
required.
12. The actuator removal to check the dampers & also changing the actuator is
Under contactor scope.
13. Compliance report of scheduled preventive maintenance activities and checklist
As per JVML format have to be submitted every month
14. Contractor has to maintain the equipment history log book.
15. Contractor has to inform the spare requirement well in advance at least 3 to 4 months,
considering the procurement time and maintain the record of spare consumed and available
spares.
16. Contractor has to ensure the availability of de dusting system > 99%, fails in which RS 10000per
hour shall be charged for the extra down time.
Supervisor scope:
1. Has to take daily work permit and maintain safe working culture of man power engaged injob.
2. Monthly manpower supply attendance list, Job list on each day, Daily PMI check list,
inspection check list to be submit.
Shift manpower:
1. Checking for normal running of equipment in site & report any abnormality with control room
2. Jam clearing of hoppers
3. Co-ordination with control room for starting /stopping of de system
4. Co-ordination with control room for damper operation & checking the same in site if any
problem is reported
5. Co-ordination with control room for dust unloading
6. Manual empty of dust from hopper if dust accumulation is more by running the drag chain
conveyor system in manual mode in coordination with control room
7. Shift report to be submitted on daily basis.
NOTE:
At any breakdown and shut down contractor has to mobilize manpower on 24 hour basis tillcompletion of
JOB.
2). Bag filter maintenance in BF#5.
a. Shifting of new bags from store to bag filter top
b. Contractor has to maintain emission level less than 50 PPM in stack.
c. Isolation of chamber from system by closing inlet valve & poppet damper LOTO to be
followed.
d. Isolation of compressed air system /pulsing system
e. Opening of bag filter top cover
f. Removal of pulsing pipes
g. Inspection of bags using hand lamp/torch & identifying of dirty bag/puncher bags
h. Removal of cages & insertion of new bags along with cages, Normalization of system.
i. Shifting of old bags to designated dumping yard
j. All false air suction to be arresting by using suitable gaskets /welding etc
k. Checking of pulsing system & replacement of pulse pipe and rectification of pipe and
replacement to be done.
l. Sampling point provision if required for any reason the same nozzle to be welded & nozzlewill
be provided by JVML
m. Checking & replacement of bag filters, pulsing pipes, inlet isolation valve, poppet damperetc
as per schedule.
n. Minimum 1 time the total bag filter inspection/rectification is under contractor
o. Scope every 4 months, the bags will be provided by JVML .bags replacement to be done by
contractor if any emission observed in stack and emission cross the 50mg/m³ limit.
p. Any steel work less than 1 ton for rectification in bag system, fixing of pipe /pad welding in bag
filter/manhole fixing etc to be done by contractor.
q. All dust leakages from hopper /RAV/chain conveyor/Gate Valve/any connection will have to be
attended on top priority immediately only steel; gasket will be provided by JVML.
r. Rectification/Replacement of RAV/Chain conveyor /valve/bellow /damper and actuator more
than DN 150 mm are to be done as per schedule or in case damage on top priority.
s. Rectification of Air/N2 line less than 4 inch & other fittings are under contactor scope
6). Chain conveyor chain replacement. (As per schedule provided by JVML)
Shifting of spare chain from store to location
Taking work permit to electrically isolate the drive of drag chain & the coupling to be
removed.
Plate to be fixed if required to isolate the chain conveyor from Hopper
After removal of top cover the De tensioning of the chain to be done by loosening of the non-
drive side screw .linkages to be removed of the damaged chain links .new chain links to be
added tensioning of the chain conveyor to be done by tightening the non-drive screw.
Fixing the covers & coupling of the chain conveyor drive unit
Shifting of removed chains for reconditioning to store
Chain assembly, shifting & replacement
8). Chain sprocket replacement/maintenance drive & non drive. (As per
schedule provided by JVML)
Shifting of spare chain drive & non drive sprocket assembly along with housing from storeto
location
Taking work permit to electrically isolate the drive of chain conveyor & the drive assemblyof
chain conveyor to be removed.
Temporary scaffolding or platform to be fabricated/fixed if required. Also if the drive
assembly/non drive units are to be taken out along with the segment of chain conveyor
housing same to be done by using suitable lifting devices like chain block /crane &
separating the housing segments at drive /non drive side .
After fixing of new drive shaft to chain conveyor along with chain conveyor housing segment
the housing segments to be fitted/aligned with existing housing. The alignment of gearbox
with chain conveyor ,drive shaft .Also the motor to gearbox to alignment to be
completed .Ensuring proper oil level the trail to be taken first by coupling motor to gear box&
then gearbox to chain conveyor .
Shifting of old removed drive /non drive chain sprocket unit to store for refurbishing
10) Lube oil system maintenance. (As per schedule provided by JVML)
□ Rectification/Replacement of lube oil system filters and maintaining healthiness.
□ Rectification/Replacement of coupling/Pump as per requirement and instructions.
□ Rectification/Replacement of valves and modification in pipe line lube oil system as required.
□ Rectification/Replacement of heat exchanger and cooling fan as required.
□ Arresting if any leakages in system.
General shift: (9AM to 6 PM) or Shift manpower (skilled) (A+B+C+R) shift hour (A: 6 am to
2 Pm,B: 2 Pm to 10Pm, C: 10pm to 6 Am) (As per schedule provided by JVML)
General shift: (9AM to 6 PM) In case of shut down or break down their man power should be
mobilized till completion of jobs without any extra cost.
□ Trials of equipment
□ Complete housekeeping.
a. Tools Required:
□ Welding machine with welding cables ,power cable ,plug tops as in BF:3 & 4 standard ,welding
machine check list, Consumables as required for the job & welding face shield
□ Gas cutting set with trolley , check list, spare gas cylinders as required for the job
□ Standard tool box
□ First aid kit
□ Certified chain pulley blocks, wire rope slings & D-Shackles
□ Hammering Ring & D Spanners 30,36 & 41
□ Pneumatic operated wrenches with hoses and bits as required for the job
□ Pullers, hydraulic jacks, and alignment device (fabricated).
b. Tools Required:
Welding machine with welding cables ,power cable ,plug tops as in BF:3 & 4 ,welding machine
check list, Consumables as required for the job & welding face shield
Gas cutting set with trolley , check list, spare gas cylinders as required for the job
Standard tool box
First aid kit
Certified chain pulley blocks, wire rope slings & D-Shackles
Hammering Ring & D Spanners required in job.
Pneumatic operated wrenches with hoses and bits as required for the job
Grinding and buffing machine.
e. Up keeping:
During job execution and after completion of the job, site should be maintained neat and clean.
Scraps and grease should be cleaned immediately after job completion.
All removed items should be shifted to designated place (Metallic /Non metallic
f. Contractor scope:
Shifting of required materials from Central stores /Sub stores /CTL
Any small modification required for the job.
All lifting tools & tackles chain blocks, d-shackle, slings etc…
All required Tools and tackles for the job is under contractor scope.(welding machine, Welding
electrodes heating oven, cutting set with spare cylinders, hammers, standard tool box, slings with
‘D’ Shackles, Grinding machine , hammering spanners etc.,). Competent authority certification for
Lifting machines tools & tackles.
Contractor has to provide two set of tools & tackles like Welding machine, cutting set, standard
spanners (One for stock house and one for cast house)
All required consumables for the job are under contractor scope (Welding electrodes and
grinding wheels etc.)
All required and standard PPE’S for the job is under contractor scope.
For Non-regular job, intimation /information will give to contractor one day before however
incase of emergency or breakdown contractor has to send manpower immediately.
CO monitor- 01 No (For each working group ) when required
Oxygen monitor - 01 No (For each working group ) when required
g. JVML Scope:
Work to permit (For each working group one dedicated contractor supervisor should be
available )
Spares, pipe, steel required for the job.
For Non-Regular activity crane/hydra/trailer should be given by M/s JVML.
Corporate standard safety certificates (For each working group one dedicated contractor
supervisor should be available ) And contractor has to full fill all the requirements which are
required for each safety certificate
Welding power point at work location.
2 phase power point at work location (Grinding, Buffing machine).
Performance parameters of De-dusting systems are as mentioned below.
1) System availability
2) Dust conveying system availability
3) Stack emissions
4) Differential pressure.
5) Solenoid Vale operation
6) Hopper build-up
7) Safety
1) System availability:
The Vendor has to maintain the availability of all individual units should be more than or equal to95%.
System availability = Total hours – (PM hours + Break down hours) x 100,
Total hours System availability will be calculated on monthly basis.
3) Stack emission:
The Vendor has to maintain the chimney emission, i.e. clear air emission from chimney and it is
observed visually for all individual units and it has to be noted on daily basis.
4) Differential pressure:
The Vendor has to maintain the differential pressure of all individual bag houses, which should be lessthan
150 mm WC 100% throughout the month.
5) Solenoid Valve operation – All solenoid valves of the system shall be in operation during
systemrunning.
6) Hopper build-up- The Vendor has to maintain hopper dust level below 10%.
7) Safety - For every major incident/accident reported on account of fault from vendor there will be
penalties.
Performance Parameters penalty clause will apply as per the below table.
Performanc UOM Weightag Penalty parameters Matrix
e e(%) 100% Payment Prorata Only
Parameters. Deductions with Manpower
Maximum payments
deductions willbe
limited to 15% of done as per
Monthly Invoice attendance,
value other elements
will not be paid
for the
below
mentioned
values of KPI
System >/= 95 % 25 Upto 95 % 50-95 % < 50 %
Availabilit
y
Dust conveying >/=90% 10 Upto 90 % 50-90 % < 50 %
system
availability
Visible < 5 times a 20 < 5 times/Month 05 to 15 > 15
sta month times
ckemissions /month
Differentia < 15 < 150mmWC. 150mmWC- >300mmWC
lPressure 150mmWC. 300mmWC
Solenoid Valve 100% 10 Upto 95 % 50-95 % < 50 %
Operation
Hopper <10% 10 <10% 10%-80% >80%
buil
d-up
INCIDENT/AC Zero 10 No LTI 2 Lakh Per LTI
CIDENT and 10 Lakhs for
Fatal
• Prorata payment shall be made with respect to weightage fixed to performance parameters.
• If any performance parameter is not achieved by the contractor due to non-availability of spares,
which are in the JVML scope, the penalty clause will not be
applicable.