ATTENTION
ATTENTION 1 :
Before operate the quilting machine,please read this operation and maintenance manual
And please remain and keep this operation and maintenance at the quilter machine for quick
reference of your operator
ATTENTION 2 :
Computer must be electrified for 8-10 hours each 30 days if the machine have been stopped
for an long time.Otherwise,all data saved in computer will be lost, then computer will be
unavailable.
ATTENTION 3 :
Make sure all electric should be grounded .
ATTENTION 4 :
Operator should be well trained ,Machine’s Maintenance and Adjustment should be operated
by experienced engineer.
ATTENTION 5 :
Damage Check:
When machine arrived your factory ,Please inspect the shipping containers ,record exterior
Damage and report it to shipping company .
1/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
CONTENTS
ATTENTION .................................................................................................................................................................. 1
CONTENTS ................................................................................................................................................................... 2
FORWARD ..................................................................................................................................................................... 3
COMANY INTRODUCTION ....................................................................................................................................... 4
Chapter 1 Installation ................................................................................................................................................... 5
ⅠTechnical Data(MM)........................................................................................................................................... 5
Ⅱ Site Preparation:................................................................................................................................................. 5
Ⅲ Power Requirements .......................................................................................................................................... 6
Ⅳ Test/Commissioning Machine: .......................................................................................................................... 6
Ⅴ Thread broken detector: ..................................................................................................................................... 6
Ⅵ How to choose good-quality thread ................................................................................................................... 6
Ⅶ How to do When Stitch Missing or jumping ..................................................................................................... 7
Ⅷ Machine Maintenance ........................................................................................................................................ 7
Ⅸ Fabric Loading Figure ....................................................................................................................................... 8
Chapter 2 Computer Screen and Function ................................................................................................................... 9
2-1 Computer Screen ........................................................................................................................................... 9
2-2 Drawing ....................................................................................................................................................... 13
2-2-1 Drawing............................................................................................................................................ 13
2-2-2 Draw Straight Line ........................................................................................................................... 15
2-2-3 Draw Round-arc ............................................................................................................................... 15
2-2-4 Curve Drawing ................................................................................................................................. 16
2-2-5 Circumrotate Moving ....................................................................................................................... 16
2-2-6 Drawing TACK&JUMP ................................................................................................................... 17
2-2-7 Save Pattern...................................................................................................................................... 18
2-2-8 Start Quilt ......................................................................................................................................... 18
2-3 Modify Pattern............................................................................................................................................. 18
Chapter 3 Machine Function introduction ................................................................................................................. 20
Chapter 4 Troubleshooting ........................................................................................................................................ 27
Chapter 5 Protective Function (Panasonic servo) ...................................................................................................... 29
Chapter 6 Troubleshooting and Fault information (Transducer) ............................................................................... 35
Chapter 7 Wiring Diagram ........................................................................................................................................ 38
7-1 Quilting machine signal input/output diagram ............................................................................................ 38
7-2 Quilting machine power supply diagram..................................................................................................... 39
7-3 CPU DIAGRAM ......................................................................................................................................... 40
7-4 Transducer Parameter & Panasonic Driver Parameter ................................................................................ 41
7-5 Electrical Connector diagram ...................................................................................................................... 42
Chapter 8 Spare Parts................................................................................................................................................. 43
2/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
FORWARD
The purpose of this operation and maintenance is to provide instructions for Newest High-speed Computerized
shuttle less Multi-Needle Quilting machine manufactured
Detailed procedures are supplied wherever required, where no specific direction is necessary, standard
procedures should be used.
We reserve the right for OPERATION AND MAINTENACE ,any changes in OPERATION AND
MAINTENACE will not be specially informed .
3/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
COMANY INTRODUCTION
Ⅰ. General Introduction
We specialize in manufacturing computerized quilting machine with more than 15 year‘s experience. All
machines adopt American‘s advanced technology and design, Thus our machines are more highly production
rate and efficiency, saving cost ad power consumption ,occupying less space and having longer life spans and
many other advantages, All long, our company has continuously import foreign advanced technology,
combining it with our own technology to produce generation of new machines ,All criterions always constant
heighten, Our products have sold all over the world: south-east Asia, American, Middle East, Europe, etc. We
are grateful to our customers for their support ad favor, we will keep innovating and working hard in order to
meet their needs and adapt to their cooperation with high-quality products, effective management and sincere
after service.
Ⅱ. Products Specification:
Ⅲ. After Service
As we know deeply after-service is of top importance. We will provide one-stop after services and
promise to sort all problems out with high speed; moreover, we could help our customer to draw new patterns
according to their different requirements. We will make every effort to supply our good service.
4/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
Chapter 1 Installation
ⅠTechnical Data(MM)
Paramete
Function Model High-speed Computerized Chain Stitch Quilting Machine
r
Main Size(L*W*H) 5100*1500*2000(mm)
Weight 4500kg
X Movement 450mm
Quilt Width 2450mm
Rotation Speed 600-1200RPM
Quilt speed 80-230m/h
Power 7KW
Ⅱ Site Preparation:
Computerized Quilting machine requires no extraordinary site preparation, the working place should be clean, level,
and well lighted .and requires space for operator movement and materials handling operations.
Fig. 1
5/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
Ⅲ Power Requirements
The Chain Stitch Quilter requires phase 380/220V 50HZ/60HZ 3 PHASE dedicated power-line. This line is
connected to the electrical cabinet which supplies the machine. Separate ground-wires must be installed
Ⅳ Test/Commissioning Machine:
Connect machine with power , display will enter into working screen(fig 4),move mouse to choose
pattern ,then click ,and press ―START‖,if machine worked stable and without abnormal noise. It
means machine run in good condition. Otherwise please check electrical wires and relevant installation.
6/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
Ⅷ Machine Maintenance
1.Computer should be kept in clean place ,the cleaner where you put computer ,the longer the computer could
worked ,if you find dust in the electrical board,please ask experienced electrical-engineer to clean it by blower.
2. Equipment movement parts(leading shaft,screw shaft) should be add oil each 5-10days in order to keep
lubricant and decrease abrasion, good quality lubricant is required.
3.Machine should be cleaned each day after machine worked full day
7/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
After installation and commissioning, then loading fabric and start to quilt
Fig 2
8/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
Fig. 4
【EDIT】Return to edit or edit the present pattern
【SAVE】Save the setting data (every adjustment if you made ,you must press【SAVE】
or what you reset is unavailable )
【FORWARD】Roller forward, new material will pull into roller when machine commissioning/test
【PRM:】 This icon show rotation speed, when machine start, value will be 11-12
【BREAK ON】 When machine stop , please keep brake on if you need to turn hand-wheel
9/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
【BACK】It is to adjust start/end back stitch when quilt TACK & JUMP
【LONG】It control the length for upper thread after thread cutting
【X】When quilt simple pattern ,if X is not on the position ,then adjust this button ‗+‘or ‗-‘
【Y】When quilt simple pattern,if Y is not on the position,then adjust this button ‗+‘or‗-‘
【STEP】It is to adjust the length of back stitch when you quilt TACK&JUMP
【THREAD】if this option is enabled,thread breaking test will start.The machine wil stop when the
thread broke.
【NEEDLE】if this option is enabled, the needle will go to the high position.
【PLATE】Timing handle-wheel slowly according to fig 9 ,speed measuring plate will turn,,When Magnet aim
at speed-measuring magnetic head through speed-measuring magnetic-hole, this button will be ‗ ‘,
when speed-measuring plate shield magnet, this button will be ‗ ‘。
【ZERO】if this option is enabled, the needle will go to the low position.
NOTE:2-1-1【TEST】 explanation:
10/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
※1 When press ―START‖ ,‗□‘ should be ‗ ‘;or you need to check the following data
※3
When needle is in the upper position, upper position sensor will give signal to computer, this button will be
‗ ‘
magnetic head will give resetting signal to computer ,this button will be ‗ ‘。
※5 When air pressure work normal‗ ‘,if press down thread loosing electromagnetism button,
※6 Timing handle-wheel slowly according to fig 9 ,speed measuring plate will turn,,When
Magnet aim at speed-measuring magnetic head through speed-measuring magnetic-hole, this button will
be ‗ ‘,when speed-measuring plate shield magnet, this button will be ‗□‘。
※7 Needle is in the upper position , when you press ― ‖,cylinder for upper thread
loosing ,down thread loosing and thread cutting will work to test air cylinder
NOTE:2-1-2 explanation:
11/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
※1 When finished TACK&JUMP, machine will pull fabric, the speed for pulling fabric
※2 After the first pulling fabric and thread cutting ,then machine will pull fabric to second
TACK& JUMP, it is the speed for go to the second one, higher the value is ,the quicker the speed will be
※3
Adjust the sensitivity for thread broken detector ,the higher this value is ,the lower sensitivity will be .
※10 The stability of the machine working, the data setting should be ―0‖
12/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
2-2 Drawing
2-2-1 Drawing
Fig 5
Save pattern
Draw curve
Empty
13/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
Curve edit
Empty
Full clearance
Circumvolve
Display smaller
Display bigger
Grids size
Copy pattern
Full-symmetry
Upright-direction symmetry
Horizontal-direction symmetry
Central symmetry
Positive symmetry
Opposite symmetry
Close symmetry
Partial symmetry
XY modify function
※where no specific direction is necessary, left key is certain key for draw start position.
When Cursor enter into Fig 7, press ― ‖,cursor move to drawing district, click ,then it will be the
new pattern‘s start position
。
Fig 6
Press ― ―,then click one point as straight line end point , after this straight line is certain , continue
next point and etc .
Fig. 7
Press ― ―,then click one point as round-arc end point ,click mouse to move round-arc ‗s
position ,then round arc is certain
15/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
。
Fig.8
Right key means delete the last round-arc you draw
Press ― ‖ and, click line end point to modify and change round arc size
Fig 9
After modify
Fig 10
16/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
Fig 11
Circumrotate
Fig 12
Click ― ‖,then move mouse to drawing district to decide start position(fig 14),click ― ‖ ,move
mouse to drawing district and click mouse continuously till pattern drawing finished(fig15-fig 18),then
Fig 13 Fig 14
17/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
Fig 15 Fig 16
Fig 17 Fig 18
2-2-7 Save Pattern
Click ― ‖, goes to and enter file name into here for sure.
When fabric loaded and choose pattern ,then press ―START‖ button in machine, machine will reset auto and
start quilt, if you find pattern in the fabric is not on the X position ,then adjust this button
‗+‘or ‗-‘ to change fabric‘s X position, if Y is not on the position, then adjust this
18/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
adjustment to 、
、 、
GX:When quilt TACK & JUMP/ bigger span pattern ,then adjust GX is necessary .
Just as quilt TACK&JUMP and PATTERN IN PATTERN,
pattern will have some differences in transverse ,then
19/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
Fig.20
20/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
Flywheel
Dial Plate
Dial Index
Fig21
Brake clutch
Fig.22 Dial handwheel & Clutch (The Value is O when Needle is in upper Position
Thread Clip
21/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
Needle Screw
Needle-ruler
Looper Shaft
Fig.26 Looper
22/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
Fig.27
Speed-measuring plate
Carriage shaft
Fig.29 Note: When Carriage come to protection switch, machine stop. Please drag strap X
Belt by hand till Carriage in the middle position, After, switch on machine
23/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
Electromagnetism-valve
Fig 30
Thread clip
Fig 32
24/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
Emergency Stop
(Switch off power)
Fig.33
Power switch
Electricity ON
Electricity OFF
Down Switch
Protect switch
Triangle switch
Hook Switch
Fig.34
X Driver
Y Driver
Fig 35
25/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
Power box
(Magnetic head, Infrared sensor)
` Fig 36
IO Connector
USB
Mouse
Display jack
Power connector
Fig 37
Inverter
Data display
Fig 38
26/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
Chapter 4 Troubleshooting
When you press RUN,RUN 1、 Carriage travel-block come to 1、 strap in X motor, then
light is on, after your photoelectricity protection carriage travel-block left
3 hand left this button, switch photoelectricity protection
RUN light off 2、 Emergency switch locked switch
immediately 2、 Keep emergency switch ON
1、 Mouse broken or mouse
Mouse is in the screen of 1、 Change an new mouse or
connect unwell with computer
4 display, but you can not connect mouse again
2、 Mouse line turnoff
move mouse. 2、 Check mouse line
27/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
28/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
29/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
Measure terminal-to-terminal
The P-N voltage of the main power voltages(between L1,L2and L3)
converter is lower than the specified Increase capacity of the main power or
value during Servo-ON. replace it with a larger one or remove the
① The main power voltage is too causes of the failure of the magnetic
Under
low,instantaneous outage occurs . contact , and then restart the power
voltage
13 The power source is small. Main source.
main
power is turned off .or the main Increase capacity of the main power.
power
power is not fed. Correct phase(L1,L2and L3)connections
② Too small power source: the line of the main power. if the main power is
voltage dropped due to the inrush single-phase 100V.use L1and L3
current at power on. Check the timing of power-on (for both
the main power and control power)
① Disconnect the motor wires, and enter
Servo-O,if this trouble happens
immediately, replace the driver with a
new one(that is working correctly)
② Check if the U>V and W wires are
The current flowing in the converter is shorted at the connections, reconnect
larger than the specified value them, if necessary.
① The driver failed(due to defective ③ Measure the insulation resistance
circuits or IGBT parts) between U/V/W and earth wire. If the
② Motor wires (U,V,and W) are resistance is not correct. Replace the
shorted. motor with a new one.
Over ③ Motor wires(U,V and W) are ④ Measure the resistance between U.V
current 14 grounded and W. if they are unbalanced replace
error ④ Motor burned the motor with a new one
⑤ Poor connection of motor wires ⑤ Check if the U/V and W connector
⑥ The relay for the dynamic brake is pins are firmly secured with
melted and stuck due to the screws .loosened pins should be fixed
frequent Servo-ON/OFF firmly
⑦ The motor is not compatible with ⑥ Replace the driver with a new one ,Do
the driver not start or stop the motor by entering
Servo-ON or OFF
⑦ Check the capacity of the motor and
driver on the nameplate .if the motor
is not compatible with the driver;
replace it with a correct one.
The radiator is heated up to exceed the
limit temperature. The power elements
Check the ambient temperature and
of the driver are overheated. overload
*Overheat cooling conditions, check the load rate.
15
error Make the environment under which the
driver operates .reduce the load.
30/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
31/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
32/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
encoder error,after the control power on ,the from rotating until the driver outputs
status error encoder rotates faster than the S-RDY, take measures to keep the motor
specified rate away from rotating until the driver
outputs S-RDY.
When an 11-wire encoder is used ,Pr
Full close Set the value of Pr02 to 0、1、2、3、4 or
97 02(control mode selection) is set to
selection 5。
7,8 or 9 (―full-close‖ control)
The control circuit operates Turn off the power and turn it on again, if
*other
incorrectly due to large noises or any the error can not be eliminated. The motor
error
other reasons。 and/or driver may be broken, disconnect
the power supply of these equipments,
The driver‘s self-diagnosing function
*other and replace them with new ones. Return
is activated, because an error happens
error the old equipment to the sales agent for
in the driver。
repair.
※ Routine maintenance and inspections are essential for proper and satisfactory operation of the driver
and motor
Notes to maintenance /inspections personnel
(1)power-on/off operations should be done by the operators themselves。
(2)for a while after power off, the internal circuits is kept charged at higher voltage, inspections should be
done a while(about 10 minutes)。After the power is turned off and the LED lamp on the panel is extinguished.
(3)do not take insulation resistance measures because the driver gets damaged.
Inspection items and cycles
normal (correct) operating conditions:
ambient temperature:30℃(annual average)load factor:max.80%
operating hours:max. 20 hours per day
Daily and periodical inspections should be done over the following instructions:
The AC drive has a comprehensive fault diagnostic system that includes several different alarms and fault
messages, once a fault is detected, the corresponding protective functions will be activated. The following faults
are displayed as shown on the AC drive digital keypad display, the four most recent faults can be read on the
digital keypad display.
Fault Fault descriptions Corrective actions
1.check whether the motors horsepower corresponds to the
AC drive output power
2.check the wiring connections between the AC drive and
motor for possible short circuits
The AC drive detects an abnormal 3.increase the acceleration time
increase in current IGBT protection 4.check for possible excessive loading conditions at the
motor
5.if there are any abnormal conditions when operating the
AC drive after short-circuit being removed .it should be1sent
back to manufacturer
1.check whether the input voltage falls within the rated AC
drive input voltage
2.check for possible voltage transients
The AC drive detects that the DC but
3.bus over-voltage many also be caused by motor
voltage has exceeded its maximum
regeneration, either increase the decel time or add an optional
allowable value
braking resistor
4.check whether the required braking power is within the
specified limits
1,ensure that the ambient temperature falls within the
specified temperature range
The AC drive temperature sensor 2. Make sure that the ventilation holes are not obstructed
detects excessive heat. 3.Remove any foreign objects on the heatsinks and check for
possible dirty heat sink fins
4,provide enough spacing for adequate ventilation
The Ac drive detects that the DC bus Check whether the input voltage falls within the rated AC
voltage has fallen drive‘s input voltage.
35/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
37/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
38/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
39/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
40/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
02-01-01 05-12-50
02-04-01 05-13-50
04-06-03 05-14-50
04-07-07 07-02-09
05-00-5.0 08-00-10
05-01-5.0 08-02-1.0
05-02-40.6 08-03-0.5
05-03-43 00-02-08(Locked)
05-04-45.4
41/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
42/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
1 Sliding arm
5 Speed plate
6 Bearing 51204
12 Bearing 1202
13 Cylinder 50*50
16 Eccentric wheel C
Left side/Right
18 Fulcrum base
side
43/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
19 Moving shaft
fine
21 Eccentric wheel cover A M18
thread
22 Connecting rod
25 Bearing NAP206
26 Bearing UCPA204
fine
29 Double-ended screw M18
thread
30 Belt 1148
32 Support base 12 寸
With
33 Roll support base Left side
hole
36 Connecting bearing
38 Oscillating bearing M8
39 Fulcrum rod M8
40 Bearing
44/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
44 Bearing ∮28
49 Adjustable gear 1
50 Adjustable gear 2
51 Adjustable gear 3
52 Adjustable gear 4
54 Belt 720H-8M-28
55 Belt 720H-8M-25
56 Belt 760H-8M-55
58 Bearing 1515F
45/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
69 Bearing New
71 motor
72 Manual valve
76 Bearing SALF206
77 Bearing SAFA206
78 Bearing UCF205
79 Bearing UCF206
80 Bearing NAP207
85 Long Retainer
86 Short Retainer
46/47
HENGCHANG MACHINERY OPERATION AND MAINTENANCE
90 Thread tension
91 Needle
47/47