Professional Documents
Culture Documents
Beles Hydro Power Plant ICTinf 2016
Beles Hydro Power Plant ICTinf 2016
The ICT infrastructure in Beles HEPP currently has Hardware setups, Fiber optics cables; LAN
connectivity and Ethio telecom provided internet connectivity. The current internet connection isn’t
working due to Beles Bahir-Dar 400 KV line and fiber optics problems. There must be additional ICT
hardware and upgrading the LAN and internet configuration issues in other area like clinic power house
store area and VATech store area needs the internet infrastructure structures.
7. Internet Connectivity
Bandwidth Assessment Needs to be upgraded
Availability Assessment Adequate
Propose strategies for increased availability: Creating good communication and
agreement with Ethio telecom for fast response time
8. Recommendation and justification
Clearly state each recommendation
Increase the band width;
Supply necessary hardware and spare parts that meets the demand;
The EEP have to see other communication option if the internet may failed like us for
long period of times;
Reconfigure computer networks to make them in the same domain;
Replace outdated hardware; software.
Upgrade data connectivity line to fiber optic;
Configure the firewall for protection;
The update Antiviruses for office computers to protect malware and viruses;
Highlight benefits and potential risks
Benefits:
It facilitates the plant technical and nontechnical operations for easily create training in
SAP system for employee.
Employee can access new technology about the daily work activity.
Potential risk: