Professional Documents
Culture Documents
Environment Impact Assessment
Environment Impact Assessment
Environment Impact Assessment
The modern technological state intensifies the conflict between environmental values and
developmental needs. Legal strategies are necessary to reconcile this conflict and to
augment sustainable development. Environmental Impact Assessment (EIA) is an
instrument of reconciliation. The Council on European Economic Committee, in their
directive to the member states, highlights the objectives of EIA in the following words:
1) The effects of a project on the environment must be assessed in order to take account
of the concerns to protect human health,
2) to contribute by means of a better environment to the quality of life,
3) to ensure maintenance of the diversity of species and
4) to maintain the reproductive capacity of the ecosystem as a Basic resource of life.
Eg. EIA under NEPA, in force in the USA, In one case, the Supreme Court followed
is the best illustration of a mandatory model this method and held that indiscriminate
of EIA mining had caused ecological imbalance in
the Doon valley and hence, the operations
were to be closed.
In another case, hazardous industries near
the capital city of Delhi were found to be a
danger and the court asked them to be
shifted to distant locations."
In still another case, functioning of tanneries
identified by experts as a hazard to
groundwater was ordered to be stopped,
unless they opted for common treatment
plant.
The courts used to give occasional warnings
that closure orders would be issued if
treatment plants were not set up.
In cases of obvious violations, they
cancelled licences. In a few cases, they sent
projects for further study and review before
implementation.
ADVANTAGES: public participation and ADVANTAGE: Quick, expert and timely
judicial review decision-making is the advantage of this
DISADVANTAGES: too lengthy, model.
cumbersome, unintelligible, DISADVANTAGE: EXPERTS may fall
environmentalist may delay development by prey to various kinds of bias and prejudices
false pleas of defects.it may impose instead of being committed to
procedural burden. It may lead to flood of environmental and social values. Reasons
objection before decision making for decision may not be disclosed. Interest
authorities, increase in litigation before of vulnerable groups may be disregarded.
courts, and thus delay in developmental Alternative opinions may be overlooked.
process.
EIA NOTIFICATION 1994 EIA NOTIFICATION 2006
A notification was published in the year The EIA Notification 1994 gave way to a
1994 with provisions for central clearance notification in 2006 with a fundamental
or projects listed in the schedule. The change.
notification was not applicable to most of Both the Central agency and the state
the projects if the quantum of investment agency are given the power to make
were below the threshold limits impact study for projects of separate types
The applicants for new projects or for with prescribed threshold limits.
modernisation of existing industry were to MoEF and the State Environment Impact
submit an EIA report along with the Assessment Authority (SEIAA) are the
management plan. regulatory authorities to render clearance at
A committee of experts would evaluate and the Centre and the states respectively, All
assess them and make recommendations decisions of the state authority should
based on a technical assessment of the ordinarily be unanimous.
document and data furnished. The notification" provides for prior
. In 1997, an amendment incorporated environmental clearance before
public inquiry into the process. However, undertaking projects and activities
there was a provision for rapid EIA. This scheduled therein. Expansion or
would be done on an EIA report submitted modernisation of existing projects or
by the project proponent and based on one activities requires clearance. Any change
season data. A detailed EIA report could be in product-mix in an existing
submitted and evaluated later if the manufacturing unit beyond the specified
assessing agency so desires. range also needs an impact study.
APPRAISAL
The EAC and SEAC make the appraisal of
all materials and evidences available after
screening, scoping and public consultation.
In this proceeding, the applicant shall
furnish necessary clarifications in person or
through an authorised representative. After
appraisal, the EAC and SEAC make
categorical recommendations to the
regulatory authority, They also make
appraisal of projects or activities, not
required to undergo public consultation.
Where a public consultation is not
mandatory, the appraisal is made on the
basis of materials in application and EIA
report. However, there are exceptions.
Category "B2" projects are exceptions.
Building and construction projects and
township and area development-projects,
coming under items 8(a) and 8(b)
respectively in the Schedule, are also
exceptions. A time limit is fixed for
completing appraisal, i.e., within 60 days of
the final EIA report and other documents.
Then the appraisal report is placed before
the competent authority for final decision
within the next 15 days.
EXPANSION OR MODERNISATION
In the case of expansion or modernisation or
change of product mix in existing projects,
the EAC or SEAC will make the appraisal
within 60 days, decide "on the due diligence
necessary including preparation of EIA and
public consultations" and appraise the
application accordingly for grant of
environmental clearance.
GRANT OR REJECTION
The regulatory authority shall normally
accept the recommendations of the appraisal
authorities and convey its decision to the
applicant within the prescribed time limit. In
cases of its disagreement, the regulatory
authority can ask for reconsideration of the
recommendations and make the final
decision after getting the reconsidered views
of the expert appraisal authorities. Prior
environmental clearance shall be on
stipulated terms and conditions. When the
application is rejected, reasons for rejection
shall be given.
If the decision of the regulatory authority is
not communicated to the applicant within
the stipulated time, the applicant may
proceed as if the environment clearance
sought for has been granted or denied in
terms of the final recommendations of the
expert appraisal authority concerned.
This deemed prior-environmental-clearance
is tantamount to a bouquet stealthily given
to the project applicant by the regulatory
authorities in their sheer negligence or
deliberate disregard of the materials before
them.
On expiry of the period specified, the
decision of the regulatory authority and the
final recommendations of the appraisal
authorities shall be public documents.
POST-CLEARANCE MONITORING
AND TRANSFERABILITY
A post-environmental clearance monitoring
on the basis of half-yearly mandatory
compliance reports by the project
management is a novel feature of the EIA
Notification 2006 Compliance reports shall
be public documents available on the
website of the concerned regulatory
authority.
The notification specifies that prior
environmental clearance granted to an
applicant may be transferred during its
validity to another legal person on the same
terms and conditions. No reference to the
appraisal authorities is necessary in such
cases.
PROJECTS and Activities Requiring
Environmental Clearance
There are originally 39 categories placed
under eight heads with separate threshold
limits and conditions with which clearance
is to be given.
30YRS- MINING