Professional Documents
Culture Documents
Project Management Review
Project Management Review
(a) Vinamilk
(b House construction co.
(c) Red Cross
(d) Bull Investment consultants
(a) Context
(b) Complexity
(c) Customer focus
(d) All of the above
3. Which of the following is NOT one of the elements of the ICOM model?
(a) Inputs
(b) Competitiveness
(c) Outputs
(d) Mechanisms
4. The capital expenses needed to carry out the project are presented on the:
(a) TRUE
(b) FALSE
7. "Managing risks and opportunities" belongs to the "Do it - D3" stage of the 4D model
managing the project process.
(a) TRUE
(b) FALSE
8. Time, people and performance are three major categories for risk analysis
(a) TRUE
(b) FALSE
9. PERT (Programme Evaluation and Review Technique) requires 3 time estimates for each
activity
(a) TRUE
(b) FALSE
(a) TRUE
(b) FALSE
- Brief the 4 perspectives on business projects according to the balanced scorecard. And
analyse the “Customers and Suppliers”
ICOM Model
• ‘chunking’ or ‘unbundling’
• Breaking down large activities into comprehensible or manageable units
– Gives people responsibility for each manageable part
– Facilitates financial control, individual parts can have their consumption of
resources tracked
– Bottom level will be a list of work packages
• A grouping of project elements or components into a logical hierarchy which defines the
total project scope
• Essentially a “to-do list” of all the deliverables (not time sequenced activities)
• Creates a linked set of hierarchical activities
– Need to build up individual activities to make them work together
– Independent units, but which are still part of the whole
• Decisions made at this stage are fundamental to success!
Critical Path Method (CPM)
‘The longest sequence of dependent activities that must be completed in order for a project to
finish’
• Critical Path: The sequence of tasks that must be completed on time in order to ensure
that a project is finished by its deadline.
• It is the longest path through a project network diagram that determines the earliest
possible completion date for a project.
• Tasks on the critical path are those that have no slack or float time, meaning that they
cannot be delayed without delaying the entire project. Any delay in completing a critical
path task will automatically delay the project's completion date.
PERT
u Likely a single value for ‘time for completion’ will have an error
u Three estimates for each activity are required
u Optimistic (o) – if conditions are ideal
u Most probable (m) – if conditions are ‘normal’
u Pessimistic (p) – if things go wrong
u Expected time is (o + 4m + p)/6
u Use expected time in critical path analysis
u May effect the duration, may change the critical path
u The downside
u Shows outcome (partial picture) but does not indicate probability
u Additional complexity may not be justified by a return in accuracy of the plans
u Relies on people being accurate in their forecasting
4 D’s Model
Complexity Analysis
Risk Analysis
2. Sensitivity analysis
u Use expected, optimistic and pessimistic value of inputs (e.g. costs)
u Shows effect on the outcome of a change in the variable
u Shows where management attention and control is needed
u Example
u Prices on materials and labour likely to fluctuate
u Contract price is fixed in advance
u Need to see effect of fluctuations on profit
u Costs of materials say £0.6m
u Costs of direct labour say £0.2m
u Contribution to overheads say £0.35m (175% of direct labour)
u Revenues: fixed at £1.2m
u Profit = revenue – material costs – (labour + overheads)
• A framework that many organisations use to determine the nature of the return on an
investment is the balanced scorecard.
• The BSC is based on the balance and alignment between the elements of the overall
strategy and its operational elements. This also includes projects within an organization.
• The universal elements are the mission (the purpose), the vision (what the organization
aspires to), the core values (what the organization believes in), the perspectives, and
the objectives.
• On the other hand, the operational elements are the key indicators or KPI (whether
induction or result indicators) and strategic initiatives (projects that help you achieve
your objectives).
(Mỗi cái này lại có slide riêng cơ ở Week 10, cái Customers and Suppliers là câu trong mock test
đấy, you mở ra xem lại nha, dài quá t k paste ra đây)
Key Activities
Overall, these combine to provide a notion of the value proposition from a project. Such
terminology has become commonplace in the justification of time, energy and resources on
business projects. The originators of the balanced scorecard promote a logical cause–effect
building of benefits from project work, with the objective to demonstrate how each project will
impact organizational strategy.
Demonstrating such benefits is the purpose of an approach known as benefits mapping. Using
this, it is possible to work back from the business benefit required, see how this maps to
organizational objectives and then determine the changes and supporting actions required to
yield those benefits.
Stakeholder dài vkl nma t nghĩ n sẻ hỏi cái này, you hảy xem lại slide Week 3 nha