Master Week Number Beg INV.

1 2 3 4 5 6 7 8
Schedule
Dart Quantity 10 10 10 10 10

Master Week Number Beg INV. 1 2 3 4 5 6 7 8


Schedule
Arrow Quantity 15 15 15 15 15
Week 1 2 3 4 5 6 7 8
Arrow: Gross 15 15 15 15 15
Requirements
LT = 2 Scheduled 20
Receipts
Projected on 5 25 25 25 25 10 0 0 0
Hand
Lot-For-Lot Net 5 15 15 15
Requirements
Planned Order 5 15 15 15
Receipts
Planned Order 5 15 15 15
Releases

Week 1 2 3 4 5 6 7 8
Dart: Gross 10 10 10 10 10
Requirements
LT = 2 Scheduled 20
Receipts
Projected on 2 2 22 22 22 12 2 0 0
Hand
Lot-For-Lot Net 8 10 10
Requirements
Planned Order 8 10 10
Receipts
Planned Order 8 10 10
Releases

Week 1 2 3 4 5 6 7 8
X Gross 5 15 15 15
Requirements
LT = 1 Scheduled
Receipts
Projected on 5 5 5 5 0 10 20 5 5
Hand
Lot Size 25 Net 15 5
Requirements
Planned Order 25 25
Receipts
Planned Order 25 25
Releases

Week 1 2 3 4 5 6 7 8
M Gross 5 15 15 15
Requirements
LT = 2 Scheduled
Receipts
Projected on 0 0 0 0 0 0 0 0 0
Hand
Lot-For-Lot Net 5 15 15 15
Requirements
Planned Order 5 15 15 15
Receipts
Planned Order 5 15 15 15
Releases

Week 1 2 3 4 5 6 7 8
K(2) Gross 16 20 20
Requirements
LT = 2 Scheduled
Receipts
Projected on 3 3 3 3 3 0 0 0 0
Hand
Lot-For-Lot Net 13 20 20
Requirements
Planned Order 13 20 20
Receipts
Planned Order 13 20 20
Releases

Notes for K(2)

Gross Requirements (Week 4) = Planned-Order Releases of 8 Darts * 2 = 16.


Gross Requirements (Week 5) = Planned-Order Releases of 10 Darts * 2 = 20.
Gross Requirements (Week 6) = Planned-Order Releases of 10 Darts * 2 = 20.

Week 1 2 3 4 5 6 7 8
F Gross 25 33 10 10
Requirements
LT = 1 Scheduled 15
Receipts
Projected on 10 10 25 25 0 27 17 7 7
Hand
Lot Size 30 Net 33 0 0
Requirements
Planned Order 60
Receipts
Planned Order 60
Releases

Notes for F

Gross Requirements (Week 3) = Planned-Order Releases 25 X * 1 = 25.


Gross Requirements (Week 4) = Planned-Order Releases (8 Darts * 1) + (25 X * 1) = 33.
Gross Requirements (Week 5) = Planned-Order Releases of 10 Darts * 1 = 10.
Gross Requirements (Week 6) = Planned-Order Releases of 10 Darts * 1 = 10.

Week 1 2 3 4 5 6 7 8

W Gross 31 55 55 15
Requirements

LT = 2 or 3 Scheduled 18
Receipts

Projected on 2 20 20 20 1 6 11 8 8
Hand

Lot Size 12 Net 72 60 12


Requirements

Planned Order 60
Receipts

Planned Order 60
Releases

Notes for W

Gross Requirements (week 3) =


Planned-Order Releases of (5
Arrows *1) + (13 K * 2) = 5 +
26 = 3
Gross Requirements (week 3) = Planned-Order Releases of (5 Arrows *1) + (13 K * 2) = 5 + 26 = 31.
Gross Requirements (week 4) = Planned-Order Releases of (15 Arrows *1) + (20 K * 2) = 15 + 40 = 55.
Gross Requirements (week 5) = Planned-Order Releases of (15 Arrows *1) + (20 K * 2) = 15 + 40 = 55.
Gross Requirements (week 6) = Planned-Order Releases of (15 Arrows *1) = 15.

*Lead time = 2 weeks for orders < 36 & 3 weeks for orders ≥36.
Planned-Order Releases (week 1) = [Planned-Order Receipts (week3) = 12] + [Planned-order receipts
(week 4) = 60] = 70.

Week 1 2 3 4 5 6 7 8

Q Gross 13 20 20
Requirements

LT = 1 Scheduled
Receipts

Projected on 15 15 15 15 2 12 22 22 22
Hand
Lot Size 30 Net 18 8
Requirements

Planned Order 30 30
Receipts

Planned Order 30 30
Releases

Notes for Q

Gross Requirements (week 3) =


Planned-Order Releases of 13 K *
1 = 13.
Gross Requirements (week 4) =
Planned-Order Releases of 20 K *
1 = 20.
Gross Requirements (week 5) =
Planned-Order Releases of 20 K *
1 = 20.
Gross Requirements (week 3) = Planned-Order Releases of 13 K * 1 = 13.
Gross Requirements (week 4) = Planned-Order Releases of 20 K * 1 = 20.
Gross Requirements (week 5) = Planned-Order Releases of 20 K * 1 = 20.