Professional Documents
Culture Documents
MTRC NEC4 Training Level 2 - Module 1 Rev 0.2
MTRC NEC4 Training Level 2 - Module 1 Rev 0.2
Module 1 - Precontract
Ian Heaphy & Daniel Cheung
■ Tender assessment
Speakers
■ Emergency procedures
■ Facilities
■ Timings
■ Phones
■ Meeting protocols
■ Questions
Training modules
Roles &
responsibilities Compensation Time and the
Precontract Commercial
and risk events programme
management
Training modules
Roles &
responsibilities Compensation Time and the
Precontract Commercial
and risk events programme
management
■ ECC v PSC
■ PSC used by a client to engage a consultant to provide a service such as
design, project or commercial management, but excluding any physical
works such as site investigation
■ ECC used by a client to engage a contractor to undertake physical works of
any type, civils, E&M etc – with any level of design responsibility (build
only to EPC / turnkey)
■ Main contracts v sub contracts
■ Subcontracts are designed to operate “back to back” with the main
contracts
■ Client, Project Manager / Service Manager and Supervisor all become
Contractor
■ Timescales are changed to accommodate the timescales in the main
contract
■ Contractor does not have to use NEC subcontracts but it is recommended
Turner & Townsend MTRC NEC4 Level 2 – Module 1 11
Turner & Townsend Confidential
■ Short contracts
■ To be used for contracts that comprise lower risk and complexity
■ No stated maximum value for their use
■ Contracts that do not need the sophisticated management techniques in
the main contracts
■ For example no requirement for a programme in the ECSC, if one is required
the content is as detailed in the Scope
■ No option for target costs or payment on a cost reimbursable basis
■ Payment is lump sum or unit rate basis or a combination of the two
Core clauses - common to all options and form around 75% of the
contract:
1 - General
2 - The Contractor’s main responsibilities
3 - Time
4 - Quality Management
5 - Payment
6 - Compensation events
7 - Title
8 - Liabilities and insurance
9 - Termination
Option A
Option B
■ Remeasurement contract
■ Bill of Quantities (BQ) produced by the Client, rates priced by Contractor (see later
slides)
Option C & D
Target contracts
Pain
Share
Gain
Share Client
Pays
Final Final
Prices Client Prices Final
Pays Defined
Final
Cost
Defined
+ Fee
Cost
+ Fee
Option E
■ Client carries risk of cost increases & gets the benefit of all savings
Option F
Management Contract
■ Contractor tenders' rates or prices for any work it will undertake plus Fee
Max Min
A Lump sum
Flexibility of Client
B Bill of quantities
■ There are 3 dispute resolution option clauses which concern rules and
procedures for adjudication or a dispute review board and then review by
a subsequent tribunal, which is either litigation or arbitration
■ Client must select 1 of these:
■ W1 Adjudication - used outside of the UK
■ W2 Adjudication – used in the UK (to comply with UK Construction Act)
■ W3 Dispute avoidance board
■ In Hong Kong many users do not select any of the above and introduce
their own dispute resolution clauses based on local practice – Dispute
Resolution Advisor, Mediation, Arbitration
■ Security of Payment Ordinance to be introduced in Hong Kong may create
the need for Hong Kong specific dispute resolution Option
Regional specific secondary Options required to enable the contract to meet the
requirements of law
Z clauses
Z clauses
What main and secondary options could you select for the following
scenarios
1. An extension to an existing rail line comprising three new stations is to be
constructed, the detailed design of which has been completed and is unlikely
to be subject to major change post contract. There is requirement to open the
first station on the extended line as soon as possible to meet the opening of a
new housing development.
2. The need to urgently replace a rail bridge over a heavily trafficked road
junction in the centre of Kwon Tong. The design of the works has only just
started.
3. A set of sidings is no longer required and MTRC wish to remediate the site to
remove contamination so that is can be sold for development. The type of
contamination is known but not the extent. A developer is interested in
purchasing the site but wants assurance the contamination will be fully dealt
with.
What main and secondary options could you select for the following
scenarios
4. A new rail line is to be developed. The works will be complex, of high value
and will require innovative construction techniques. The works will take an
estimated 5 years to complete. Outline design is nearing completion. MTRC
are considering opening the new line in phases as it wants to start to generate
revenue as soon as possible.
Contract Data
Let us review the Contract Data template in the contract and consider what should be
included for some of the key entries
Scope
■ NEC4 ECC can be used for any type of construction work, this flexibility it
achieved by leaving the finer details of the work to be prescribed within the
Scope
■ Scope is the most important part of an NEC4 contract and as with any
contract form the client needs to be clear on what the supplier has to do and
any restrictions on how they do it
■ Scope is information which
■ specifies and describes the works or
■ states any constraints on how the Contractor Provides the Works
and is either
■ in the documents which the Contract Data states it is in or
■ in an instruction given in accordance with this contract
■ Scope will include a number of documents – general specification, particular
specification, preambles, client’s drawings, etc. as well incorporating by
reference local and international standards
Turner & Townsend MTRC NEC4 Level 2 – Module 1 44
Turner & Townsend Confidential
Scope
Scope
Scope
Site Information
Site Information
Activity Schedule
Activity Schedule
Activity Schedule
Fabrication
3 Fabrication of tunnel $1,000,000
of tunnel
boring machine boring
machine
4 Site clearance $300,000
Site
clearance
Activity Schedule
Fabrication
3 Fabrication of tunnel $1,000,000 of tunnel
boring machine boring
machine
4 Site clearance $300,000 Site
clearance
CE1 divert
Total of the Prices $3,800,000 water main
Bill of Quantities
■ The BQ is the bill of quantities identified in the Contract Data unless later
changed in accordance with the contract
■ BQ is produced by the Client
■ It is prepared and remeasured in accordance with the method of measurement
■ Method of measurement may be an industry standard or one amended or
created by the Client
■ A preamble will commonly form part of the BQ as required by the method of
measurement
■ The Client takes the risk of errors in the BQ including departures from the
method of measurement
■ Each rate contains the entire cost the Contractor will incur in undertaking that
item of work including direct cost, site running costs, overheads, profit and risk
■ Remeasurement is made on the basis of the actual quantities of work, or
proportion of any lump sums, the Contractor has completed – not construction
/ as built drawings
■ Information in the BQ is not Scope or Site Information
Risk
■ Contractors risk
■ The Contractor has to allow within the Prices for the risks they carry under
the contract
■ All risks that are not grounds for compensation events
■ Clients risk budget
■ This does not form part of the Prices and is an allowance for Clients risks i.e.
changes in Scope
Provisional sums
■ Provisional and prime costs sums are not included in the NEC4 ECC
■ They can be incorporated via a z clause that will need to detail how they
are evaluated and paid under each main Option
■ Alternatives
■ Exclude work that would normally be included as a Provisional Sum and add
the work in when the final scope is known as a compensation event
■ Include an assumed scope of work and possibly an assumed value at tender
stage, then omit and add back the work once the final scope is known
■ In both cases the actual work required will be priced based on Defined Cost
plus Fee – the same way most Provisional Sums are dealt with – plus any
time impact
In which part of the contract would you include the following information
■ Factory acceptance testing requirements
■ Factual data from a borehole
■ The boundaries of the Site
■ Constraint on working hours dictated by the Planning Department
■ Existing Site layout drawings
■ The order and timing of the work to be done by other contractors that will
interact with the Contractor Providing the Works
■ Exclusion of the Contracts (Right of Third Parties) Ordinance
■ An MTRC requirement to only use timber from a list of sustainable sources
■ A Sectional Completion Date
■ Requirements for the Contractor’s quality management system
Tender assessment
■ The tender assessment process will follow standard MTRC procedures and
tender evaluation processes
■ The commercial assessment will need to consider the main Option
selected and the data provided by the Contractor in Contract Data part
two
■ In main Options A to D there will be a tendered total of the Prices and this
will form a key part of the assessment however, consideration will need to
be given to the overall outturn cost
■ In Options A & B the overall outturn costs will be the tendered total of the
Prices plus or minus compensation events
■ Compensation events will be priced using Defined Cost plus Fee
■ Elements of Defined Cost plus the fee percentage will be tendered by the
Contractor in Contract Data part two
■ An outturn cost will need to be modelled considering the tendered total of
the Prices plus an allowance for compensation events evaluated using the
data in the Contract Data part two
Turner & Townsend MTRC NEC4 Level 2 – Module 1 59
Turner & Townsend Confidential
Tender assessment
■ In Options C & D the final outturn cost will need to be considered as with
Options A & B, however consideration will also need to be given to the
Defined Cost plus Fee the Contractor will be paid for the works and that
will determine the Contractor’s share
■ This will involve modelling the final Defined Cost plus Fee for the whole of
the works using the data in Contract Data part two
■ In main Options E & F there is no total of the Prices and the commercial
analysis will be based on the data in the Contract Data part two
■ In some cases Client’s may dictate some of the rates and percentages in
Contract Data part two or place limits on them i.e. set a minimum or
maximum fee percentage in order to simplify the tender assessment
process
Tender assessment
B
✔️ ✔️ ❌ ❌
C
✔️ ✔️ ✔️ ✔️
D
✔️ ✔️ ✔️ ✔️
E
❌ ❌ ✔️ ❌
F
❌ ❌ ✔️ ❌
© Turner & Townsend Limited. This content is for general information purposes only and does not purport to constitute professional advice. We do not make any
representation or give any warranty, express or implied, and shall not be liable for any losses or damages whatsoever, arising from reliance on information contained in this
document.
It must not be made available or copied or otherwise quoted or referred to in whole or in part in any way, including orally, to any other party without our express written
permission and we accept no liability of whatsoever nature for any use by any other party.