Professional Documents
Culture Documents
Prohibitory Clauses - 11.01.24
Prohibitory Clauses - 11.01.24
Union of India:
4) The Arbitrator noted that the claim related to the losses caused
due to increase in prices of materials and costs of labour and
transport during the extended period of the contract.
6) The question before the Supreme was whether the Arbitrator had
travelled beyond his jurisdiction in awarding escalation costs
and charges.
c) It was held that the claim was not outside the purview of the
contract and arose as an incidence of the contract and the
Arbitrator had jurisdiction to make such award.
2. K.N. Sathyapalan vs. The State of Kerela
Facts:
b) The agreement relating to the handing over of the site was executed
on 10th October, 1985.
d) The Claimant moved to the site and commenced the work on 1st
November, 1985 but he was not allowed to proceed with the work
vi) Here, the Claimant made various claims which were awarded.
However, in an appeal filed by the State, some of the claims were
set aside by the High Court.
Claim (i) for compensation for the losses suffered because the
Department was unable to hand over a suitable quarry, for
Rs.24,86,574/-.
Government’s Arguments:
a) The case was squarely covered by the decision in P.M. Paul’s case.
b) The appellant had suffered heavy losses on account of the law and
order problem which had been created at the work site and that he
had been compelled to complete the work under duress.
d) The intention behind this letter was that the Department would
reciprocate his gesture and consider the special circumstances
under which he had given his consent for extension of the period
for completion of the work.
Court’s finding: