Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

GENERAL NOTES:

COPYRIGHT RESERVED BY HOLLOWAY & HOUND ON ALL DESIGNS AND


DOCUMENTATION.

NO DRAWINGS TO BE SCALED.
ALL MEASUREMENTS, HEIGHTS AND LEVELS TO BE VERIFIED ON SITE PRIOR TO
COMMENCEMENT OF CONSTRUCTION AND ADAPTED TO SUGGESTED BUILDING WORK.
ANY DISCREPANCY OR CONTRADICTION TO BE DISCUSSED WITH THE ARCHITECT
IMMEDIATELY.
ALL DIMENSIONS INDICATED ON PLAN TO BE SET OUT ON A LEVEL HORIZONTAL PLANE .
ALL BRICKWORK TO BE SET OUT USING A PROFILE MARKED 85mm C/C.
THE CONTRACTOR IS RESPONSIBLE FOR THE CORRECT SETTING OUT OF THE BUILDING
WORK ON SITE WITH PARTICULAR REFERENCE TO SITE BOUNDARIES, SERVITUTES AND
BUILDING LINES.
THE CONTRACTOR IS TO BUILD IN APPROVED D.P.C's TO ALL EXTERNAL WALLS, UNDER
FLOORS AND UNDER WINDOW CILLS.
QUALITY OF ALL MATERIAL AND CRAFTMANSHIP TO COMPLY WITH THE RELEVANT S.A.B.S

building line
STANDARDS.
site boundary

site boundary
THE CONTRACTOR SHOULD HAVE A FULL SET OF DRAWINGS AVAILABLE ON SITE AT ALL
building line

TIMES.
THE CONTRACTOR IS RESPONSIBLE FOR HIS OWN QUALITY CONTROL.
ALL FLOOR LEVELS SHOWN ON THIS DRAWING REFER TO UNFINISHED FLOOR LEVELS.

28° pitch +35.835 top of apex

New chromadek
GENERAL:
DRAINAGE:
Boundry pegs to be pointed out by
corrugated iron roof All sewers to be 100mm dia. PVC
owner.
sheeting, colour dove min. fall 1:60, Max fall 1:10.
W19 Contractor must check all levels,
grey on approved dimentions, steps
timber trusses Open end of vent pipe to be min.
etc. on site, and report all
2,0m above any opening.
discrepancies to the designer.
Concrete ring beam to +34.280 wall plate height All work to comply with the National
Stub vents to be fitted with an
Building Regulations
Eng design and approved 2-way vent-valve.
purpose made aluminium window as per walls: plaster & paint specifications
schedule W16 D17 FLOORS AND SLABS: Stacks in ducts to be accessable for
Ground floor slab: 85mm thick,
ENCLOSED PATIO +33.600 underside slab cleaning purpouses.
20MPa minimum concrete, perfectly
Exist level, min 150mm above gl. on All bends and junctions in sewer to
reinforced concrete roof slab as per Engineers window properly compacted
D17 be fitted with ie's, all re's under
design with cement screed laid to fall and remains hardcore: 25mm thick screed and
paving to be fitted with marked
purpose made
finishes as indicated.
approved waterproofing by specialist walls: plaster & paint aluminium door as per covers.
schedule These floors must be cast on min
Protect drain under foundations in
50mm. thick
accordance with SANS 10400
purpose made aluminium polystyrene foam and foam is to be
sliding door +31.730 top of parapet installed around
All waste fittings to have reseal traps
perimeter of room to insulate floor
and pipe to be fully accessable if
from wall.
under floors, with ie's either end or
+31.220 underside slab clamped to wall.
DPC under all walls (except free
standing), floors &
Any sewer pipe not deeper than
Exist reinforced concrete window sills & to all vertical changes
350mm under ground level (il.-.46) to
slab as per Engineer to in floor levels. be covered with a concrete slab, wide
purpose made purpose made receive screed to fall to and strong enough to protect the
outlets and FOUNDATIONS AND sewer, with min 100mm soil between
aluminium sliding aluminium sliding
PASS. waterproofing as per BRICKWORK pipe and concrete.
BATHROOM door door PATIO Specialist All foundations to be minimum 10MPa
walls: plaster & paint walls: plaster & paint concrete (2 sacks cement: The radius at the centerline of bend
4 wheelbarrows river sand: 5 of the foot of discharge stack, shall be
Exist purpose made wheelbarrows 22mm stone) not less than 300mm and other bends
timber shutter as per at least 200mmx600mm, min. 600mm.
detail 200mm under ground level
or to eng. details. Where any waste or soil branches
floor finish on 85mm NOTE: THESE ARE MINIMUM are connected to a stack the centre
surface bed and +28.670 uffl REQUIREMENTS ONLY line of the waste branch shall not
150mm well intersect the stack within 200mm
compacted hardcore Lintels to be supported min. 150mm below the centre line of the soil
for openings up to branch.
3,0m and at least 220mm for
openings up to 4,8m. Sewer connection : as shown: with
rodding eye ormanhole within 1,5m
Brickforce to built in every course from connection.
SECTION B-B below floor level and above
window level, every third course
scale 1:50 between, in continuous bands.

IF IN DOUBT ASK
DONT ASSUME

SITE BOUNDARY

spot lights

spot lights spot lights


above door

7 8 9
6

10
4 5
2 3
1

D 200L spot lights


above door

32 Clarendon Crescent 021 510 0072 Daleen Holloway - PfSnrArch T


Ysterplaat 079 502 6645 SACAP Registration - PSAT 20714
Cape Town
7405 daleen@hollowayandhound.com
tv www.hollowayandhound.com
SITE BOUNDARY

SITE BOUNDARY
tel
BUILDING LINE

BUILDING LINE
D Beam over to Engineer design PROJEK PROJECT
spot lights
D D D D2
above lintel height

passage
D D
DB

DD D D
D2

W11 MR + MRS HUGO

tel
above door

ERF 1039
FERNKLOOF ESTATE
STAND NO 55

200L
HOME STUDY
200L

allow conduits as indicated,


wc
headboard design to be confirmed
200L
D
MAIN BATHROOM
above door above door

tv
TITEL TITLE
ELECTRICAL LAYOUT
@ 2400 height

SECTION B:B

BUILDING LINE
spot lights SKAAL AS INDICATED SCALE
above door NOTE: All electrical points indicated in red to be on battery
backup connected to solar system. Solar system by specialist GETEKEN DH DRAWN

NAGESIEN DH CHECKED
SITE BOUNDARY
DATUM 14.04.2024 DATE
NOTE: All electrical points indicated in red to be on battery
backup connected to solar system. Solar system by specialist
TEK. NO. DRWG. NR:
ARCHITECTURAL PROFESSIONAL
ELECTRICAL LAYOUT-GROUND FLOOR ELECTRICAL LAYOUT-FIRST FLOOR DALEEN HOLLOWAY
PSAT 20714 2024-11-003
SCALE 1.100 SCALE 1.100
CONTACT NR: 079 502 6645

You might also like