Proposal For Golf Course Project 06.04.2024
Proposal For Golf Course Project 06.04.2024
CONTENTS
CHAPTER - I...........................................................................................................................1
INTRODUCTION......................................................................................................................1
AIM............................................................................................................................................2
OBJECTIVES............................................................................................................................2
SCOPE.......................................................................................................................................2
PROPOSED SITE......................................................................................................................3
PROPOSED 18 HOLES GOLF COURSE AT SLAF STATION SIGIRIYA..........................3
CHAPTER II............................................................................................................................5
MACHINERY REQUIREMENT FOR THE PREPARATION OF GOLF COURSE.............6
VEHICLE REQUIREMENT FOR PROPOSED GOLF COURSE...........................................6
MACHINERY AND EQUIPMENT REQUIREMENTS FOR MAINTENANCE...................6
GRASS AND OTHER MATERIAL REQUIREMENT FOR GOLF COURSE
PREPARATION WORKS.........................................................................................................7
PLUMBING AND OTHER MATERIAL REQUIREMENT FOR THE INSTALLATION OF
IRRIGATION SYSTEM AND OTHER CONSTRUCTION WORKS AT GOLF COURSE..7
CHAPTER - III........................................................................................................................8
BUDGETARY REQUIREMENT.............................................................................................9
CHAPTER - IV........................................................................................................................9
MANPOWER REQUIREMENT.............................................................................................10
CHAPTER – V.......................................................................................................................12
EXPECTED FUND ALLOCATION AND ROI PLAN..........................................................12
ROI PLAN...............................................................................................................................13
CHAPTER - VI......................................................................................................................14
LIMITATIONS AND CHALLENGES...................................................................................14
THE AIR FORCE EAGLES’ GOLF LINKS & COURSE – SCHEDULE OF FE.................14
REVENUE DETAILS OF THE EAGLES’ CATALINA GOLF COURSE AT SLAF STN
KGL IN 2023...........................................................................................................................15
RESTRICTED
RESTRICTED
CHAPTER - I
INTRODUCTION
1. Sri Lanka is a beautiful island which is rich in stunning landscape and cultural
heritage. In connection with the tourism, it is established several golf courses all over the
country and this offers unique experiences for the locals as well as the foreigners. Golf is not
popular among Sri Lankan peoples as it’s often seen as a game for the elite while enjoyed.
But some of foreign peoples come to Sri Lanka specially for playing golf here. Golfers are
not normal travelers; they are high net worth individuals who spend three to four times that of
an average tourist, when they travel to anywhere in the world. The Sri Lankan tourism sector
has witnessed a remarkable growth in the last year, with cumulative tourist’s arrivals reaching
1.27 million, generating a revenue of $ 1.8 billion. Moreover, Sri Lanka Air Force Station
Sigiriya is an important destination for both local and foreign community. During the year
2023, a total of 56 of military aircrafts and 168 of civil aviation aircrafts have been landed to
the station Sigiriya with approximately 500 passengers. Since Sigiriya is an attractive tourist
destination in Sri Lanka, the proposed golf course will be very much benefited to the golf
lovers all around the World.
2. The proposed golf course project at this Station will consist with 18-holes, which is
tucked away in the center of our immaculate camp and offers the perfect combination of
luxury and adventure golfing. The obstacles strategically placed within short distances,
testing your precision and strategic ability. This short, but tough, around 6–7-kilometer
course is nestled in the gorgeous surroundings of station Sigiriya. The world class hospitality
coverage will create that will last a lifetime.
AIM
3. The aim of this project is to establish an international level golf course for the both
local and foreign golf players under exclusive historical environmental background with the
spirit of warm hospitality provided by the proposed Hotel project.
4. To provide another welfare activity for the SLAF personnel.
OBJECTIVES
RESTRICTED
RESTRICTED
7. The management will be done under supervision of the CO SLAF Stn Sgr.
PROPOSED SITE
8. The proposed 18- Holes Golf course will be located inside the premises of the SLAF
Stn Sgr.
Figure 1. Aerial View of the Selected Site for proposed 18 Holes Golf Course.
RESTRICTED
RESTRICTED
RESTRICTED
RESTRICTED
9. The following map indicates the distances for the nearby golf courses located around
the proposed golf link.
RESTRICTED
Nuwara Eliya Golf Club –
Nuwara Eliya (109 Km)
RESTRICTED
10. The machinery requirement for the land preparation and other construction works of
the proposed Golf course project is as follows.
01. Backhoe 01
11. The various golf machineries will be used for the Golf course maintenance activities.
Therefore, it is required below mentioned new machineries in order to function the
maintenances works after the construction.
RESTRICTED
RESTRICTED
Approximate Approximate
S/ No Description Req. Qty
Unit Price Unit Price
01. Golf Mower Machine 01 15,000,000.00 15,000,000.00
12. Land preparation works will be stared after the land survey process and material such
as soil, sand, cement, metal etc will be obtain/purchased as per the requirement. The
approximate expenditure for the land preparation and other construction works will be Rs.
1111111. The works scope is as follows;
a. Earth filling works -Transit 01 road (Fairway 1), Road adjoin to lake (Fair way 2)
Alpha 4 (View point), Lion monument (Tee 12)
b. Construction of Caddies huts -03 Qty
c. Construction of Bridge
d. Preparation of sand bunkers – 05 Qty
e. Land preparation of Golf course- Green 18 Qty, Tees 72 Qty, 18 Fairways
f. Installation of irrigation system for the Course
RESTRICTED
RESTRICTED
13. Proper irrigation systems should be applied for the proposed golf course and it helps
to maintain the quality of the turf land. The approximate cost for the installation of irrigation
system will be Rs. 8,274,245.00 and the works scope is as follows.
RESTRICTED
RESTRICTED
Figure 5. Aerial View of the Proposed Irrigation Plan for the Golf Course
CHAPTER - III
BUDGETARY REQUIREMENT
14. Considering the above requirements, golf course budget is a comprehensive financial
plan outlining the anticipated revenues, expenses, and financial goals for a specific period. A
well-structured golf course budget considers various factors such as membership fees, food
and beverage income, Pro shop sales, cause fees, tournament income and etc. By
meticulously detailing income sources and outlining planned expenditures, a golf course
budget provides valuable insights for decision-making, cost control, and overall financial
stability within the golf course project.
15. The detailed breakdown for the proposed golf course project is as follows;
RESTRICTED
RESTRICTED
CHAPTER - IV
MANPOWER REQUIREMENT
Total Strength
S/No Trade Remarks
requirement
01. Agro Asst 18 -For preparation works of 72 Qty of Tees, 18 Qty of
02. Ops Grd 16 Golf Greens and Fairways of the Golf Course
03. Plumber 02
-For establishment of Irrigation System, installation
04. Mason 04 of tube wells and construction works of 03 Qty of
05. Welders 02 Caddy huts
- Required period is 03 months
06. Carpenters 04
Total 46
10
RESTRICTED
RESTRICTED
17. The proposed organization structure for the Golf Course at SLAF Stn Sgr is as
follows.
11
RESTRICTED
RESTRICTED
CHAPTER – V
18. As per the calculations done by respective stake holders, approximately cost of the
entire project including constructional charges (all inclusive), machinery & equipment cost,
vehicles cost and any other essential accessories for the above constructions will be about Rs.
46.734 Mn . Therefore, SLAF Stn Sgr is expecting a loan from CWF in order to
implementation of the constructions of the particular Golf course.
19. According to cost of the project, it is suggested to recover the loan obtained through
the CWF, will be recovered from 96 months as equal monthly instalments after two years
from commencement of the proper functioning of the subject project accordingly.
12
RESTRICTED
RESTRICTED
ROI PLAN
20. Following are the budget assumptions and ROI plan of the project;
Recovery Plan
13
RESTRICTED
RESTRICTED
CHAPTER - VI
21. Following are the limitations and expected challenges for this project;