Bar chart for Erection, Oil Filling & Pre-commissioning Testing

Sr. no.I300299
Sr.NO. Activities/ Days 1 2 3 4
1 Inspection & Verification of Reactor & accessories
2 Facility inspection
3 Radiator assembly
4 Pre-Erection Testing Turret CT,Bushing Tan Delta etc. Sampling of oil
5 drums
Conservator support fixing & installation.
6 HV Turret, BR Pipeline, Breather pipeline.
7 Bushing mounting. HV, N
8 Pressure test.
9 Vacuum cycle (36 Hrs) less then 1 mbar.
10 Cabling.
11 oil filling & Filtration in storage Tank
12 oil filling in Reactor
13 Complete reactor filtration.
14 Settling time (48 Hrs)
15 Pre-commissioning testing.
16 Protection signal to be check upto marshalling box.

Pre- erection test


Bushing Tan-delta
Bushing IR
Core -Frame- Tank IR
CT test
IR Value measurement
Resistance Measurement
Current Ratio
Knee Point-
Polarity-
Note:
The above plan are considering that Reactor had been placed on final plinth before start of erection a
Suitable capacity and boom length crane to be provided at site as per requirement.
3 nos, 20 KL Oil storage tank to be arrange at site before start of erection
Minimum 10000 LPH capacity filter machine ( as per tool list)
Highly skilled manpower to be provided at site to assist the work
Given days may change as per site circumstances
The Schedule is for 1 no. Reactor installation work

Unrestricted
missioning Testing of 63 MVAr, 400kV REACTOR
no.I300299
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

before start of erection activates.

Unrestricted