Bar Chart - 63 MVAr Reactor
Bar Chart - 63 MVAr Reactor
Sr. no.I300299
Sr.NO. Activities/ Days 1 2 3 4
1 Inspection & Verification of Reactor & accessories
2 Facility inspection
3 Radiator assembly
4 Pre-Erection Testing Turret CT,Bushing Tan Delta etc. Sampling of oil
5 drums
Conservator support fixing & installation.
6 HV Turret, BR Pipeline, Breather pipeline.
7 Bushing mounting. HV, N
8 Pressure test.
9 Vacuum cycle (36 Hrs) less then 1 mbar.
10 Cabling.
11 oil filling & Filtration in storage Tank
12 oil filling in Reactor
13 Complete reactor filtration.
14 Settling time (48 Hrs)
15 Pre-commissioning testing.
16 Protection signal to be check upto marshalling box.
Unrestricted
missioning Testing of 63 MVAr, 400kV REACTOR
no.I300299
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20