Shell Price Page

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

COMPLETE REHABILITATION OF ONE SET, SINGLE FACE,

SHELL PECTEN LOGO - SOLARIS BUILDING


STRUCTURAL MATERIALS
1. Scaffolding Rentals ₱60,000.00
2. Scaffolding Tools and Equipment ₱140,000.00
3. Fabrication of Steel Platform ₱85,000.00
TRANSPORTING OF STRUCTURAL MATERIALS (PLANT TO SITE)
1. Delivery on Site ₱125,000.00
2. Loading & Unloading of Structural Tools, Materials, and Equipment ₱60,000.00
STRUCTURAL INSTALLATION, INSPECTION & DISMANTLING
1. Scaffolding Installation/Erection ₱150,000.00
2. Structural Inspection ₱30,000.00
3. Dismantling ₱150,000.00
TRANSPORTING OF DISMANTLED STRUCTURAL MATERIALS (SITE TO PLANT)
1.Delivery from Site to Plant ₱125,000.00
CIVIL/STRUCTURAL & SAFETY COMPLIANCE
1. Installation of Safety Precaution & Counter Measures ₱25,000.00
2. Safety Personnel on Site ₱30,000.00
3. Structural Engineer Supervision/Inspection ₱25,000.00
PERMIT & INSURANCE APPLICATION
1. Plan Reproduction ₱15,000.00
2. Professionals Fee - Structural Engineer Sign & Sealed ₱25,000.00
4. MACEA Clearance & Permit ₱50,000.00
5. Makati LGU Permit ₱130,000.00
6. Contractors All Risk Insurance (CARI) ₱20,000.00
7. Surety Bond ₱30,000.00
8. On-site Temporary Facility Essential Cost ₱40,000.00
SET IN MOTION FOR COMPLETE REHABILITATION
1.Replacement of Panagraphic Plex ₱80,000.00
2. Replacement of All Existing Electrical Wiring ₱50,000.00
3. Replacement of LED Modules & Power Supply ₱250,000.00
4. Repainting of the Shell Pecten Framing ₱100,000.00

TOTAL ₱1,795,000.00