Minutes of meeting (07/03/2024)

Meeting Purpose:

To discuss technical QC concerns for Tanks :4.1-T-001, 002 & 6.4-T-003

Attendees:

Name Company Name Company


Ahmed Ashour SMD Tarek Hendy EMC
Marwan Khalil SMD Mohamed Tawfik EMC
Hossam ElHosseiny ENPPI

Action
S.N Subject Due date
By
The nozzle (C) still not completely fabricated due to shortage of material
1 EMC Closed
(Elbow 6 inch).
Name plate has been installed left side the manhole MH1(Beside the
manhole) which vary from the location and orientation mentioned in the
drawing.
2 EMC 10/03/2024
EMC is waiting for Engineering reply and will issue a TQR after
receiving

In one portion, A buckling in the plates between the 2nd and 3rd course
3 with variation 12mm has been detected (Required Engineering advice). EMC 10/03/2024
EMC will submit a technical justification from API 650 TQs
The manhole MH1 has been manufactured from a plate 8mm instead on
pipe 24in SCH STD “9.53mm” (Required Engineering advice).
4 EMC 10/03/2024
TQ supported by engineering approval will be submitted by EMC to
SMD
The manhole door lifting mechanism is vary from the required in the
drawing (Required Engineering advice).
5 EMC 10/03/2024
TQ supported by engineering approval will be submitted by EMC to
SMD
The deviation between the drawing orientation and actual fabrication
(Nozzlez and Anchor chairs)
6 EMC 10/03/2024
TQ supported by engineering approval will be submitted by EMC to
SMD
Plumbness of the tank due to that the tank has been stored unleveled After
7 Plumbness test will be performed on site after tank settlement and EMC EMC settlement
will issue a report on site
The roof nozzles and manhole location (Dimension from the tank
centerline), flanges tilt, and flanges bolt hole orientation are not verified
8 EMC 11/03/2024
due to unavailability of the required temporary scaffolding.
Check will be performed on 11/3/2024 using man lift