Professional Documents
Culture Documents
Draft Purchase Requisitions Rev 004
Draft Purchase Requisitions Rev 004
Purchase Requisitions
Rev. 004
Draft
MRP can also create Purchase Requisitions for materials needed for production or sales. These are
not usually subject to approval, since the company has already gone though the process of production
and sales planning.
Free Text Purchase Requisitions – used for material or services that are not very often
supplied and therefore, do not imply the creation of a material master;
LOGISTICS >> MATERIALS MANAGEMENT > PURCHASING >> PURCHASE REQUISITION >>
CREATE
Similarly to other SAP documents, Purchase Requisitions have a split structure. These documents are
composed by a Header and an Items Detail section.
The Header is dedicated only to the addition of text notes that apply to all of the items in the
Requisition.
Almost all Inventory Purchase Parts are controlled via Schedule Agreements and won’t be ordered
through a single Purchase Requisition and Purchase Order.
However, there will be some situations, in which this might happen, such as for example with ordering
samples from an inventory part in a different condition.
In order to create a Purchase Requisition, use transaction ME51N or follow the menu path:
LOGISTICS >> MATERIALS MANAGEMENT > PURCHASING >> PURCHASE REQUISITION >>
CREATE
as previously mentioned.
Initial Screen
The type of Purchase Requisition selected by default is NB. This corresponds to the standard
Purchase Requisition that will be used in most of the situations.
The other types, described below, will only be used in very specific cases:
ZCON Huf Confidential - will be used only for special and confidential orders. Only authourised users
can see this, and will have the permission to work on these type of PR.
The next step is to enter the intended texts in the Header section ( if needed):
A Purchase Requisition can have more than one line/material. In order to add a new line, follow the
steps previously described.
When adding a new line, a text refering only to the specific line may be added in the TEXT Tab in the
Item Details section, as shown below:
Note: If necessary the requisitioner can change the delivery address, that is usually, by default,
the plant or storage location address.
In Item Details section, click in the Delivery Address Tab and insert the intended Address:
If a red circle is found behind the line of your Purchase Requisition, this means that there is an error.
In order to access the information on the error, double click on the red circle and immediatelly a
window with the intended information pops up:
But if the requisitioner wants to assign a different source of supply, the following steps must be carried
out:
And a warning message pops up stating that the Desired Vendor is different from the Fixed Vendor.
When all relevant information is added, the last step is to click in the SAVE button:
All Non-Inventory-Handled material will be ordered via single Purchase Requisition and Purchase
Order.
Non-Inventory-Handled Material Types are materials without inventory management.
For all Non-Inventory-Handled material an account assignment is necessary.
The process for requisition of Non-Inventory-Handled material is the same as described in former
section, but with some additional settings.
In case Assignment is not clear for a determined material, it must be consulted with finance
department.
SAVE
In order to enter the Serial Number, click in Tab Material Data and in button Serial Numbers:
Project Assignment Purchase Requisitions are usually done within the Project System.
Also the Cost Center Assignment Purchase Requisition follows the same procedure as previously
described. Nevertheless, there are some additonal settings that need to be done, namely:
Although in the majority of the situations, a Purchase Requisition is associated to a material created in
the Material Master, the requistioner has also the possibility of requiring materials or services without
reference to the SAP Material Master.
These Purchase Requisitions are called Free-Text and they are essentially used to require materials
or services which are not regularly supplied.
In this case, when creating a free-text-requisition, the material number field can be left empty,
and the short text field must be entered manually.
Regarding:
A purchase requisition for services can be created with material number or without material number. In
the previous section, an example of a service without material number can be found (Free-Text
Purchase Requisition)
In a purchase requisition for Contingent Services, the quantity for the whole period of the offer or
contract must be entered. Also in this case, there is no difference from a purchase requisition for
Non-Inventory-Handled material.
For Contingent Services the receipt may be partially made: several partial receipts can be booked
in one purchase order during the whole contract period.
Whenever needed, a list of Purchase Requisitions can be shown through the use of transaction ME5A.
Here some filter types can be used to show ( by purchasing group, by number of PR, by delivery date,
etc) the intended information detail:
After the criteria has been provided, the intended list of Purchase Requisitions is displayed:
All Purchase Requisition must originate a purchase order. The Purchase Order will be made by
procurement.
The instructions on the process of transforming a Purchase Requisition into a Purchase Order will be
detailed in the Purchase Order manual.
Transaction ZMM_PURREQ
Requisitioner:
Press F8 – Execute
If you want to archive a Requisition, this requisition must “print” the document first with a archive
storage mode.
This can be only in ME52N or ME53N and you have to open the PR.
Than you can see a list of documents for this requisition. With double click on the icon the document
open.
To add in the right folder you can also use this way.
Please don’t use the Create attachment possibility, because the the storge will done on the SAP data
base and not in saperion archive which are archive with other security.