31 FORMWORKS/STAGINGS/BATTER BOARD Scaffoldings (for rental only) 50.00 sets 1,500.00 75,000.00 Lumber : 2" x 2" x 12 300.00 pcs 240.00 72,000.00 Lumber : 2" x 4" x 12 200.00 pcs 480.00 96,000.00 Phenolic Board, 1/2" x 4' x 8' 40.00 pcs 1,200.00 48,000.00 CWN, 3" 40.00 kgs 55.00 2,200.00 CWN, 2" 40.00 kgs 57.50 2,300.00 Used Oil 10.00 gals 30.00 300.00 GI Tie Wire #16 50.00 kgs 90.00 4,500.00
Projected Material Cost : 2,215,183.70
Projected Labor Cost : 901,203.88
Projected Construction Cost : 3,116,387.57
Approved by: Certified by:
AR. JOBIL L. FERRERAS, UAP
Owner Architect TIN No. 412 170 050 000 PRC No. 27040 PTR. No. SF 3669794 Date : 07-23-2020 Place : City Of San Fernando IAPOA No. 23126 269173 082919
Printed : 3/26/2021 3:51 AM Page 5 of 5
Bill of Materials Project : PROPOSED TWO-STOREY RESIDENCE Location : Bulaon, CSFP Owner : Michelle Jo S. Gutierrez/Mario Lloyd P. Gutierrez Date : March 26, 2021