Professional Documents
Culture Documents
WMS Streetlight (AutoRecovered)
WMS Streetlight (AutoRecovered)
Dokumen Rujukan
Nomor Dokumen Deskripsi
Sejarah Revisi
Tanda
tangan
Disetujui Oleh
CONSORTIUM 5OC KSK / OWNER
Tanda
tangan
Page 1 of 17
Method Statement
Page 2 of 17
Method Statement
DAFTAR ISI
1. INTRODUCTION..................................................................................................................................
1.1. Scope of Work........................................................................................................................................
1.2. Quality Verification Point:......................................................................................................................
4. WORK PREPARATION........................................................................................................................
4.1. Installation Environment........................................................................................................................
4.2. Technical Requirement...........................................................................................................................
5. REFERENCE DOCUMENT..................................................................................................................
5.1. The reference documents used are as follows:.........................................................................................
5.2 Job Risk Assesment................................................................................................................................
Page 3 of 17
Method Statement
Page 4 of 17
Method Statement
1. INTRODUCTION
2.1. Site Construction Manager shall be responsible for the coordination and
supervision of construction activities and coordinate with other agencies and
ensure that the work is done as per specification and approved drawings and all
safety measures are implemented.
2.2. Site Superintendent / Supervisor shall be supervising closely the activities
designated to them and ensure that all instructions are followed and all necessary
documents are in place prior to commencing the works and safety procedures of
the project is strictly adhered to.
2.3. EHS officer personnel are responsible for the enforcement of safety and ensure
that the works are carried out in accordance with company safety procedures on
the EHS authorities.
2.4. QA/QC personnel are responsible for the enforcement of quality and ensure that
the works are carried out in accordance with the approved procedures and the
Page 5 of 17
Method Statement
applicable codes, standards & specifications. All required inspection and testing
activities for the construction shall be carried out in accordance with the approved
Inspection Test Plan refer to:
a. INSPECTION AND TEST PLAN ELECTRICAL SYSTEM
b. Reference Approval Drawing
c. Request for Inspection (RFI) will be issued by the Contractor to the Owner at
least Three (3) days in advance to notify the readiness of inspection. All relevant
inspection test records will be prepared according to the applicable ITP and it will
be submitted to the Owner for review and verification as soon as possible after
completion of inspection / test.
3. SAFE WORK PLAN
CONTRACTOR is committed to achieve the goals for zero accidents and this can only be
achieved when all parties do their best in an integrated manner to maintain the safety
himself and others.
The following considerations will be incorporated into all planning activities and issued
of execution documentation.
3.1. Pre-job execution:
Correct Job Safety Assessment (JSA) will be done before executing the work
and communicating to all crews on daily basis
Page 6 of 17
Method Statement
3.4. Safety practice will be implemented but not limited to the following requirements:
Flagman will be in place to monitor the traffic.
A safety and toolbox meeting will be conducted prior to the commencement of
the work.
All cable megger tested will be performed using two people, one at either end
of the cable. Each equipped with radio communication and with the continuity
check being carried out first.
Barricade the entire area when a certain test is executed as the risk of a failed
test is that structural steel may become live (energized). The test will be
conducted after normal working hours.
Page 7 of 17
Method Statement
The following checks and confirmation will be made prior to starting the work.
Confirm safety and security regulations requirement (concerning work permit, safety
training, etc).
Confirm documents (project specifications, working drawings, work specifications,
etc.) required for executing the construction work.
Confirm whether the work schedules have been prepared.
Page 8 of 17
Method Statement
Ensure that the latest revision of the relevant drawing, specification, and
documentation are available and are in use.
To prevent mistakes during the fabrication of support street lighting fixture, make
sure the detail drawing is not different from the actual lighting detail.
Inspect the proposed location to ensure that adequate access/egress is available at all
times while work is being carried out.
Confirm the correct supervision and a team are available for the task.
5. REFERENCE DOCUMENT
a) T1_PP_000_ELE_CAL_00006_LIGHTING_ILLUMINATION_CALCULATION
_A_REV-2
b) T1-PP-000-ELE-DWG-00001_REV3_STD DWG FOR ELEC INSTALLATION
Page 9 of 17
Method Statement
Page 10 of 17
Method Statement
Page 11 of 17
Method Statement
d. Set out sigh rails at every 10 meters interval and at all change of grade and
alignment of utility service and maintain the pegs until works are completed.
e. No interruption shall be permitted. Where such interruption is unavoidable, it
shall only be carried out with permit obtained from relevant authorities
approval.
f. The work will only be commenced after MSA, MST and shop drawings are
approved.
Page 12 of 17
Method Statement
c. Ensure that the service door/handhole shall be along the direction of traffic or as
requested from Contractor.
d. Build Scaffolding side by side the planting area of the pole.
e. Attach Rope to the pole and pull it by the workers and hold the pole tightly so it
won’t fall back to the road.
f. After the pole is planted to the planting area, remove the rope from the pole using
scaffolding.
g. Bolt on set of nuts onto the foundation bolts. Place pole’s bottom pole flange the
foundation bolt nuts. Screw on the locking nots on to the foundation bolts at the top
of the base plate. Check and adjust the vertically of the pole with liquid level gauge
before the nut in place in tightly.
h. Check the underground loop in and out cable’s insulation with and earth insulation
test before terminating the cables into the light.
i. Carry out the adjustment to the aiming of the light fitting according to approved
calculations and drawing and lock fitting into placed by tightening all the
adjustment bolt/screw.
j. Terminate the internal cable ends into the cut-out box/handhole.
Page 13 of 17
Method Statement
Once connected, then the PJU lights are installed at the end of the pole with a set key
and terminated according to the cable that has been prepared. Also make sure the lights
and cables are working properly by testing the lights before lifting.
c. Bind the two support pipes to help hold the PJU pipes. The support pipe below tied to
form a small bar above to help when the PJU pole is half up.
e. After everything is ready and has been checked there are no problems with the lights
and cables, the pipe is pulled with a rope and there are personnel holding the pipe so
that it does not move from its position. Once it's high enough, a support pole will help
hold the pipe up when it half standing. Slowly the pole is pulled and adjusted to its
position by personnel who are near the foundation.
Page 14 of 17
Method Statement
f. After the PJU pole has entered the anchor hole, the previously prepared bolts and nuts
are installed below and above the baseplate.
c) Installation of Feeder Pillar
a. Identify and mark the locations at which feeder pillar is to be located. Excavate the
required plant dimension.
b. Construct the reinforcement bars and formwork for plinth according to the specified
design.
c. Place inside the centre of the formwork structure the PVC pipe for cable entry with the
foundation bolts place around it.
d. Pour in concrete mix and leave to set.
e. Back filled with sand inside the plinth until top of the plinth.
f. Extend the PVC pipe for cable entry.
g. Once concrete plinth is set, place the Feeder Pillar onto the plinth using backhoe and
screw the locking nuts to the foundation bolts.
h. Pull the earth conductor from the feeder pillar thought the PVC pipe until earth
chamber.
i. Back fill surrounding of the plinths to the desired ground level.
8. INSPECTION & TESTING
Page 15 of 17
Method Statement
After completion each of installation of street lighting fixture, ensure that cable
installation, proper dressing, and cable arrangements were properly done. The
installation shall be inspected to ensure that:
- All visual inspection requirements have been met and completed.
- Verify location installation for street lighting.
- Check all accessories installed properly.
- For panel installation, ensure all the wire inside the panel been dressing properly and
have proper earthing.
- Brightness should be measured after street lighting all properly installed.
After completion of each installation and inspection work, the document should be compiled
in electrical completion document dossier. Make sure that document compiling has been
completed with the sign of a dedicated person.
Page 16 of 17
Method Statement
LAMPIRAN
Page 17 of 17