Professional Documents
Culture Documents
Works Programme ML To BBK
Works Programme ML To BBK
1 Construction Programme of Balance Works Railway Project ML to BBK 550 24-Aug-23 24-Feb-25 11% Construction Programme of Balance Works Railway Project ML to BBK
Milestone-1
5 A1010 Milestone-1 120 24-Dec-23 100%
Milestone-2
6 A1020 Milestone-2 270 24-May-24 0%
Milestone-3
7 A1030 Milestone-3 400 04-Oct-24 0%
Milestone-4
8 A1040 Milestone-4 540 24-Feb-25 0%
9 Design submission and approval 222 23-Sep-23 02-May-24 0% Design submission and approval
Submissions
10 Submissions 208 23-Sep-23 18-Apr-24
Alignment Design Report
11 A1050 Alignment Design Report 28 23-Sep-23 21-Oct-23 100%
L Section
12 A1050 L Section 28 23-Sep-23 21-Oct-23 100%
LWR Plans
13 A1070 LWR Plans 28 21-Mar-24 18-Apr-24 0%
GAD of Major Bridges
14 A1080 GAD of Major Bridges 150 21-Oct-23 19-Mar-24 100%
GAD of Minor Bridges
15 A1090 GAD of Minor Bridges 120 21-Oct-23 18-Feb-24 100%
GADs of FOB including launching Scheme
16 A1100 GADs of FOB including launching Scheme 90 04-Nov-23 02-Feb-24 100%
GAD of L-Xings
17 A1110 GAD of L-Xings 28 07-Oct-23 04-Nov-23 100%
Structural drawings of Major Bridges
18 A1120 Structural drawings of Major Bridges 28 19-Mar-24 16-Apr-24 100%
Structural drawings of Minor Bridges
19 A1130 Structural drawings of Minor Bridges 28 18-Feb-24 17-Mar-24 100%
Structural Drawings of FOBs
20 A1140 Structural Drawings of FOBs 28 02-Feb-24 01-Mar-24 100%
Signal Interlocking Plans(SIPs)
21 A1150 Signal Interlocking Plans(SIPs) 28 22-Dec-23 19-Jan-24 100%
Cable Core Plan
22 A1160 Cable Core Plan 28 30-Dec-23 27-Jan-24 100%
Cable Route Plan
23 A1170 Cable Route Plan 28 30-Dec-23 27-Jan-24 100%
Track Bonding Plan
24 A1180 Track Bonding Plan 28 21-Oct-23 18-Nov-23 100%
Final Layout Plan of OHE
25 A1190 Final Layout Plan of OHE 56 27-Jan-24 23-Mar-24 33%
Cross Sectioning Drawings of OHE
26 A1200 Cross Sectioning Drawings of OHE 56 27-Jan-24 23-Mar-24 33%
Long Section drawings of OHE
27 A1210 Long Section drawings of OHE 28 27-Jan-24 24-Feb-24 100%
RUB Drawings at LC-184C
28 A1220 RUB Drawings at LC-184C 28 04-Nov-23 02-Dec-23 100%
29 Approval 194 21-Oct-23 02-May-24
Alignment Design Report
30 A1230 Alignment Design Report 14 21-Oct-23 04-Nov-23 100%
L Section
31 A1240 L Section 14 21-Oct-23 04-Nov-23 100%
LWR Plans
32 A1250 LWR Plans 14 18-Apr-24 02-May-24 0%
GAD of Major Bridges
33 A1260 GAD of Major Bridges 14 19-Mar-24 02-Apr-24 67%
GAD of Minor Bridges
34 A1270 GAD of Minor Bridges 14 18-Feb-24 03-Mar-24 75%
GADs of FOB including launching Scheme
35 A1280 GADs of FOB including launching Scheme 14 02-Feb-24 16-Feb-24 0%
GAD of L-Xings
36 A1290 GAD of L-Xings 14 04-Nov-23 18-Nov-23 100%
Structural drawings of Major Bridges
37 A1300 Structural drawings of Major Bridges 14 16-Apr-24 30-Apr-24 100%
Structural drawings of Minor Bridges
38 A1310 Structural drawings of Minor Bridges 14 17-Mar-24 31-Mar-24 60%
Structural Drawings of FOBs
39 A1320 Structural Drawings of FOBs 14 01-Mar-24 15-Mar-24 0%
Signal Interlocking Plans(SIPs)
40 A1330 Signal Interlocking Plans(SIPs) 14 19-Jan-24 02-Feb-24 100%
Cable Core Plan
41 A1340 Cable Core Plan 14 27-Jan-24 10-Feb-24 100%
Cable Route Plan
42 A1350 Cable Route Plan 14 27-Jan-24 10-Feb-24 100%
Track Bonding Plan
43 A1360 Track Bonding Plan 14 18-Nov-23 02-Dec-23 100%
Final Layout Plan of OHE
44 A1370 Final Layout Plan of OHE 14 23-Mar-24 06-Apr-24 33%
Cross Sectioning Drawings of OHE
45 A1380 Cross Sectioning Drawings of OHE 14 23-Mar-24 06-Apr-24 33%
Long Section drawings of OHE
46 A1390 Long Section drawings of OHE 14 24-Feb-24 09-Mar-24 100%
RUB Drawings at LC-184C
47 A1400 RUB Drawings at LC-184C 14 02-Dec-23 16-Dec-23 100%
48 Civil Works 528 07-Sep-23 16-Feb-25 Civil Works
Super-Structure work
72 A1600 Super-Structure work 60 26-Sep-24 25-Nov-24 0%
Misc-Works
73 A1610 Misc-Works 28 25-Nov-24 23-Dec-24 0%
Bridge No-455A (OWG)
74 Bridge No-455A (OWG) 263 20-Apr-24 08-Jan-25
Test Pile
75 A1620 Test Pile 14 20-Apr-24 04-May-24 0%
Pile Load test
76 A1630 Pile Load test 14 04-May-24 18-May-24 0%
Working Pile
77 A1640 Working Pile 60 18-May-24 17-Jul-24 0%
Cosntruction Pile Cap
78 A1650 Cosntruction Pile Cap 28 17-Jul-24 14-Aug-24 0%
Constuction of Pier
79 A1660 Constuction of Pier 28 14-Aug-24 11-Sep-24 0%
Construction of pier cap
80 A1670 Construction of pier cap 28 11-Sep-24 09-Oct-24 0%
Assembly of OWG
81 A1680 Assembly of OWG 45 14-Aug-24 28-Sep-24 0%
Launching of OWG
82 A1690 Launching of OWG 60 12-Oct-24 11-Dec-24 0%
Misc-Works
83 A1700 Misc-Works 28 11-Dec-24 08-Jan-25 0%
Bridge No-459 (Composite)
84 Bridge No-459 (Composite) 263 20-Apr-24 08-Jan-25
Test Pile
85 A1710 Test Pile 14 20-Apr-24 04-May-24 0%
Pile Load test
86 A1720 Pile Load test 14 04-May-24 18-May-24 0%
Working Pile
87 A1730 Working Pile 60 18-May-24 17-Jul-24 0%
Cosntruction Pile Cap
88 A1740 Cosntruction Pile Cap 28 17-Jul-24 14-Aug-24 0%
Constuction of Pier
89 A1750 Constuction of Pier 28 14-Aug-24 11-Sep-24 0%
Construction of pier cap
90 A1760 Construction of pier cap 28 11-Sep-24 09-Oct-24 0%
Casting of PSC Slab
91 A1770 Casting of PSC Slab 28 14-Aug-24 11-Sep-24 0%
Assembly of OWG
92 A1780 Assembly of OWG 45 25-Sep-24 09-Nov-24 0%
Launching of OWG
93 A1790 Launching of OWG 60 09-Nov-24 08-Jan-25 0%
Misc-Works
94 A1800 Misc-Works 28 08-Jan-25 05-Feb-25 0%
95 Minor Bridges 320 10-Oct-23 25-Aug-24
Bridge no-442
96 Bridge no-442 90 10-Oct-23 08-Jan-24
Box Completed
97 A1810 Box Completed 90 10-Oct-23 08-Jan-24 100%
Bridge no-443
98 Bridge no-443 90 17-Oct-23 15-Jan-24
Box Completed
99 A1820 Box Completed 90 17-Oct-23 15-Jan-24 100%
Bridge no-444
100 Bridge no-444 98 10-Mar-24 16-Jun-24
Construction of Raft
101 A1830 Construction of Raft 28 10-Mar-24 07-Apr-24 50%
Construction of Wall
102 A1840 Construction of Wall 28 07-Apr-24 05-May-24 0%
Construction of Top slab
103 A1850 Construction of Top slab 28 05-May-24 02-Jun-24 0%
Misc. Works
104 A1860 Misc. Works 14 02-Jun-24 16-Jun-24 0%
Bridge no-445
105 Bridge no-445 90 24-Oct-23 22-Jan-24
Box Completed
106 A1870 Box Completed 90 24-Oct-23 22-Jan-24 100%
Bridge no-446
107 Bridge no-446 90 31-Oct-23 29-Jan-24
Box Completed
108 A1880 Box Completed 90 31-Oct-23 29-Jan-24 100%
Bridge no-447
109 Bridge no-447 98 24-Apr-24 31-Jul-24
Construction of Raft
110 A1890 Construction of Raft 28 24-Apr-24 22-May-24 0%
Construction of Wall
111 A1900 Construction of Wall 28 22-May-24 19-Jun-24 0%
Construction of Top slab
112 A1910 Construction of Top slab 28 19-Jun-24 17-Jul-24 0%
Misc. Works
113 A1920 Misc. Works 14 17-Jul-24 31-Jul-24 0%
Bridge no-448
114 Bridge no-448 98 24-Apr-24 31-Jul-24
Construction of Raft
115 A1930 Construction of Raft 28 24-Apr-24 22-May-24 0%
Construction of Wall
116 A1940 Construction of Wall 28 22-May-24 19-Jun-24 0%
Construction of Top slab
117 A1950 Construction of Top slab 28 19-Jun-24 17-Jul-24 0%
Misc. Works
118 A1960 Misc. Works 14 17-Jul-24 31-Jul-24 0%
Bridge no-449
119 Bridge no-449 98 15-Apr-24 22-Jul-24
Construction of Raft
120 A1970 Construction of Raft 28 15-Apr-24 13-May-24 0%
Construction of Wall
121 A1980 Construction of Wall 28 13-May-24 10-Jun-24 0%
Construction of Top slab
122 A1990 Construction of Top slab 28 10-Jun-24 08-Jul-24 0%
Misc. Works
123 A2000 Misc. Works 14 08-Jul-24 22-Jul-24 0%
Bridge no-449A
124 Bridge no-449A 98 22-Apr-24 29-Jul-24
Construction of Raft
125 A2010 Construction of Raft 28 22-Apr-24 20-May-24 0%
Construction of Wall
126 A2020 Construction of Wall 28 20-May-24 17-Jun-24 0%
Construction of Top slab
127 A2030 Construction of Top slab 28 17-Jun-24 15-Jul-24 0%
Misc. Works
128 A2040 Misc. Works 14 15-Jul-24 29-Jul-24 0%
Bridge no-450
129 Bridge no-450 90 07-Nov-23 05-Feb-24
Box Completed
130 A2050 Box Completed 90 07-Nov-23 05-Feb-24 100%
Bridge no-451
131 Bridge no-451 90 21-Nov-23 19-Feb-24
Box Completed
132 A2060 Box Completed 90 21-Nov-23 19-Feb-24 100%
Bridge no-452
133 Bridge no-452 90 05-Dec-23 04-Mar-24
Box Completed
134 A2070 Box Completed 90 05-Dec-23 04-Mar-24 100%
Bridge no-453
135 Bridge no-453 98 22-Apr-24 29-Jul-24
Construction of Raft
136 A2080 Construction of Raft 28 22-Apr-24 20-May-24 0%
Construction of Wall
137 A2090 Construction of Wall 28 20-May-24 17-Jun-24 0%
Construction of Top slab
138 A2100 Construction of Top slab 28 17-Jun-24 15-Jul-24 0%
Misc. Works
139 A2110 Misc. Works 14 15-Jul-24 29-Jul-24 0%
Bridge no-454
140 Bridge no-454 90 12-Dec-23 11-Mar-24
Box Completed
141 A2120 Box Completed 90 12-Dec-23 11-Mar-24 100%
Bridge no-454A
142 Bridge no-454A 98 15-Apr-24 22-Jul-24
Construction Programme of Railway Project ML to BBk Classic Schedule Layout
"2023 "2024 "2025
# Activiy ID Activity Name Duration Start Date Finish Date Physical (%) Q3 Q4 Q1 Q2 Q3 Q4 Q1
Construction of Raft
143 A2130 Construction of Raft 28 15-Apr-24 13-May-24 0%
Construction of Wall
144 A2140 Construction of Wall 28 13-May-24 10-Jun-24 0%
Construction of Top slab
145 A2150 Construction of Top slab 28 10-Jun-24 08-Jul-24 0%
Misc. Works
146 A2160 Misc. Works 14 08-Jul-24 22-Jul-24 0%
Bridge no-454B
147 Bridge no-454B 90 19-Dec-23 18-Mar-24
Box Completed
148 A2170 Box Completed 90 19-Dec-23 18-Mar-24 100%
Bridge no-455
149 Bridge no-455 98 28-Apr-24 04-Aug-24
Construction of Raft
150 A2180 Construction of Raft 28 28-Apr-24 26-May-24 0%
Construction of Wall
151 A2190 Construction of Wall 28 26-May-24 23-Jun-24 0%
Construction of Top slab
152 A2200 Construction of Top slab 28 23-Jun-24 21-Jul-24 0%
Misc. Works
153 A2210 Misc. Works 14 21-Jul-24 04-Aug-24 0%
Bridge no-456
154 Bridge no-456 98 05-May-24 11-Aug-24
Construction of Raft
155 A2220 Construction of Raft 28 05-May-24 02-Jun-24 0%
Construction of Wall
156 A2230 Construction of Wall 28 02-Jun-24 30-Jun-24 0%
Construction of Top slab
157 A2240 Construction of Top slab 28 30-Jun-24 28-Jul-24 0%
Misc. Works
158 A2250 Misc. Works 14 28-Jul-24 11-Aug-24 0%
Bridge no-457
159 Bridge no-457 98 12-May-24 18-Aug-24
Construction of Raft
160 A2260 Construction of Raft 28 12-May-24 09-Jun-24 0%
Construction of Wall
161 A2270 Construction of Wall 28 09-Jun-24 07-Jul-24 0%
Construction of Top slab
162 A2280 Construction of Top slab 28 07-Jul-24 04-Aug-24 0%
Misc. Works
163 A2290 Misc. Works 14 04-Aug-24 18-Aug-24 0%
Bridge no-458
164 Bridge no-458 98 19-May-24 25-Aug-24
Construction of Raft
165 A2300 Construction of Raft 28 19-May-24 16-Jun-24 0%
Construction of Wall
166 A2310 Construction of Wall 28 16-Jun-24 14-Jul-24 0%
Construction of Top slab
167 A2320 Construction of Top slab 28 14-Jul-24 11-Aug-24 0%
Misc. Works
168 A2330 Misc. Works 14 11-Aug-24 25-Aug-24 0%
169 Costruction of RUB/LHS 112 25-Sep-24 15-Jan-25
Construction of Raft
170 A2340 Construction of Raft 28 25-Sep-24 23-Oct-24 0%
Construction of Wall
171 A2350 Construction of Wall 28 23-Oct-24 20-Nov-24 0%
Construction of Top slab
172 A2360 Construction of Top slab 28 20-Nov-24 18-Dec-24 0%
Misc. Works
173 A2370 Misc. Works 28 18-Dec-24 15-Jan-25 0%
174 Construction of FOB 144 25-Sep-24 16-Feb-25
Foundation
175 A2380 Foundation 28 25-Sep-24 23-Oct-24 0%
Sub-Structure
176 A2390 Sub-Structure 28 23-Oct-24 20-Nov-24 0%
Super-Structure
177 A2400 Super-Structure 60 20-Nov-24 19-Jan-25 0%
Misc. works
178 A2410 Misc. works 28 19-Jan-25 16-Feb-25 0%
179 Extension of of Level X-ing (4 Nos) 116 15-Feb-24 10-Jun-24
Road Proofing
180 A2420 Road Proofing 28 15-Feb-24 14-Mar-24 0%
Fencing
181 A2430 Fencing 28 14-Mar-24 11-Apr-24 0%
Other Misc. Works
182 A2440 Other Misc. Works 60 11-Apr-24 10-Jun-24 0%
183 Relay Room (2 Nos) 116 29-Feb-24 24-Jun-24
Foundation
184 A2450 Foundation 28 29-Feb-24 28-Mar-24 0%
Sub-Structure
185 A2460 Sub-Structure 28 28-Mar-24 25-Apr-24 0%
Super-Structure
186 A2470 Super-Structure 60 25-Apr-24 24-Jun-24 0%
Construction of Railway station
187 240 05-May-24 31-Dec-24
Foundation work
188 A2480 Foundation work 60 05-May-24 04-Jul-24 0%
Sub-structure
189 A2490 Sub-structure 60 04-Jul-24 02-Sep-24 0%
Suuper-Structure work
190 A2500 Suuper-Structure work 60 02-Sep-24 01-Nov-24 0%
Misc. Works
191 A2510 Misc. Works 60 01-Nov-24 31-Dec-24 0%
192 Track Works 403 10-Jan-24 16-Feb-25 Track Works
Final Adjustment
214 A2700 Final Adjustment 120 07-Oct-24 04-Feb-25 0%
215 Signalling & Telecommunication works 283 20-Jan-24 29-Oct-24
216 Location Box Foundation 248 20-Jan-24 24-Sep-24
Erection
217 A2710 Erection 180 20-Jan-24 18-Jul-24 19%
Cable termination & Wiring
218 A2720 Cable termination & Wiring 120 29-Apr-24 27-Aug-24 0%
Cable Trench
219 A2730 Cable Trench 120 13-May-24 10-Sep-24 0%
Cable Laying
220 A2740 Cable Laying 120 27-May-24 24-Sep-24 0%
221 Signalling work 167 15-May-24 29-Oct-24
Foundation work
222 A2750 Foundation work 120 15-May-24 12-Sep-24 0%
Erection
223 A2760 Erection 90 29-Jun-24 27-Sep-24 0%
Cable Termination & Wiring
224 A2770 Cable Termination & Wiring 60 13-Aug-24 12-Oct-24 0%
Point Machine Installation
225 A2780 Point Machine Installation 60 27-Aug-24 26-Oct-24 0%
Track Circuit Installation
226 A2790 Track Circuit Installation 60 30-Aug-24 29-Oct-24 0%
HASSDAC Installation
227 A2800 HASSDAC Installation 30 27-Sep-24 27-Oct-24 0%
LC Gate
228 A2810 LC Gate 90 29-Jun-24 27-Sep-24 0%
229 Indoor Relay Room 70 20-Aug-24 29-Oct-24
Electronics Interlocking Installation
230 A2820 Electronics Interlocking Installation 30 20-Aug-24 19-Sep-24 0%
Relay Rack Installation & Wiring
231 A2830 Relay Rack Installation & Wiring 60 20-Aug-24 19-Oct-24 0%
Cable Termination Rack Installation & Wiring
232 A2840 Cable Termination Rack Installation & Wiring 60 27-Aug-24 26-Oct-24 0%
UFSBI Single/Double Line
233 A2850 UFSBI Single/Double Line 60 30-Aug-24 29-Oct-24 0%
Data Logger
234 A2860 Data Logger 30 30-Aug-24 29-Sep-24 0%