Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 8

TAN, FRANCIS ENRIQUEZ

RISK ASSESSMENT
Operation/ Task: Erection, Altering and Dismantling of Scaffolding Works Risk Assessment No: 2021-001
Location/ Area: Al Sadd, Doha, Qatar Revision No: 01
Applicable To Method Date:
Scaffolding Works Method Statement 04/05/2021
Statement Title & No:
LIKELIHOOD
Certain 5 5 10 15 20 25
Probable 4 4 8 12 16 20
Possible 3 3 6 9 12 15
Improbable 2 2 4 6 8 10
Negligible 1 1 2 3 4 5
CONSEQUENCES Slight 1 Minor 2 Significant 3 Severe 4 Major 5
INTOLERABLE (15 TO 25)
Operations must not proceed: alternative methods to conduct this task must be implemented.

INTERMEDIATE (4 TO 12)
Risks should be reduced to as low as reasonably practicable (ALARM). The higher the risk. The more effort must be given to reducing the risk.
This task should be reassessed at regular intervals to evaluate that the existing control measures are adequate.
TOLERABLE (1 TO 4)
This task may proceed with or without additional control measures. But if measures can be implemented to further reduce risk these should be
implemented.
Possible multiple deaths and/or serious structural An event which is certain to occur unless immediate
 MAJOR  CERTAIN
damage controls are applied
Possible death, severe multiple injuries (LTI – An event which is likely to occur unless control
 SEVERE  PROBABLE
Medevac) measures are improved
Possible significant injuries / multiple minor injuries An event which may occur despite existing control
 SIGNIFICANT  POSSIBLE
(Probable LTI) measures
Possible significant injuries (Medical treatment/first An improbable event, but could occur it control
 MINOR  IMPROBABLE
Aid) measures are disregarded
Possible slight/no potential risk of injuries(Possible
 SLIGHT  NEGLIGIBLE .A highly unlikely event
first Aid)
Any number 15 or above is intolerable and the task must not commence until alternative methods have been introduced. Any number 4 to 12 risks are deemed as
tolerable, risks must have been reduced to as low as reasonably practicable (ALARM). Additional control measures may be required and the tasks should be re-
assessed at regular intervals. Numbers 1 to 4 are tolerable, but risks should be reduced further if easily achievable.
Risk Rating Residual Risk Responsibility
Item Activity Potential Hazard Control Measures Monitoring
S L RR S L RR Compliance

SCAFFOLDING WORKS ACTIVITY

1 1.

1.

1.

1.

Adverse weather condition 4 3 12 1. Ensure a proper supervision that will monitor the 4 1 4 Scaffolding
environmental working conditions to ensure that operatives supervisor,
are not put at risk. scaffolder and
2. Wet weather gear may be utilized, however supervision will workers
determine when work will cease due to environmental
conditions.
3. No scaffold erection will be allowed if there is any adverse
weather condition to ensure the safety of the workers.
Being struck by moving plant of 4 4 16 1. Drivers of vehicles will adhere to on site routes and speed 4 1 4 Supervisor,
vehicles movement limits. Driver, operator,
2. Materials to be delivered/ collected from pre-designated area scaffolder and
on site by HGV all loads are to be pre stropped. workers
3. Edge protection to be fitted to all Lorries.
4. Deliveries are to be pre booked and pick up points agreed.
5. Ensure that equipment (including packing) is stacked within
the perimeter s of the trailer/ vehicle
Slips, trips and fall 4 3 1 1. Ensure that all workers shall follow Company guidance for 4 1 4 Scaffolding
Management of Slips and Trips supervisor,
2. All site personnel are to ensure work area is clear and well-lit. scaffolder and
3. Ensure that working area to be restricted by physical barriers workers
and warning signage, at or underneath the work area to
segregate work from pedestrians, public, other trades, plant
and vehicles to reduce and/ or remove the risk from falling
objects.
4. All materials will be subject to good housekeeping by stacking
materials safely, securely, neatly, tidily and away from access/
egress routes.
5. Designated access/ egress routes only to be used.
6. Operatives to wear slip resistant safety boots. Ensure these
Page | 1
Risk Rating Residual Risk Responsibility
Item Activity Potential Hazard Control Measures Monitoring
S L RR S L RR Compliance

are kept in good condition.


2 Altering scaffold works Fall of materials during 5 3 15 1. Work must never take place over the heads of others. 4 1 4 Scaffolding
movement on site and during 2. Before scaffold work can commence Scaffold Supervisor to Inspector,
altering or adaption activities establish a suitable exclusion zone, with physical barriers and Scaffolding
warning signage, at or underneath the work area to segregate supervisor,
work from other trades, pedestrians, public, plant and vehicles scaffolder and
to reduce and / or remove the risk from falling objects. workers
3. Store materials securely to prevent inadvertent movement, i.e.
fittings to be bagged, long materials stored flat (never upright).
4. Materials must be raised/ lowered in a controlled, hand-to-
hand manner or using a gin wheel and rope.
5. Small and loose materials are to be transferred in bags or
stillages to prevent items falling.
Fall of person during altering or 5 4 20 1. Ensure that only trained operatives may carry out activities 4 1 1 Scaffolding
adaption activities while working at height. supervisor,
2. All scaffold operatives will hold a valid 3rd party training scaffolder and
certificate with. workers
3. Scaffold Supervisor to ensure the correct skills ratio of
operatives within each crew.
4. All work will be carried out following work safe method
statement and Company Preventing Falls in Scaffolding
Operations.
5. Collective fall prevention methods must be given precedence
over personal fall protection, reliance on personal fall arrest
equipment must be considered as a last resort only.
Collapsed of scaffold during 5 4 20 1. Ensure that scaffold will be altered or adapted progressively. 4 1 4 Scaffolding
altering or adaption activities 2. Scaffold to be altered and or adapted design carried out in Inspector,
accordance with work safe method statement with approved Scaffolding
designed drawing. supervisor,
3. Ensure that no any unauthorized modifications to be made to scaffolder and
the scaffold (including ties, structural members, warning workers
signage, barriers, etc.) by others, particularly by non-trained
scaffold operatives.
4. Ensure that scaffold tie anchorage will be tied to the structure
sufficiently as per design, tie anchorage altered or adopted
progressively with the scaffold with warning signage to
prevent inadvertent removal and sample tie proof tests as
scaffold procedure (i.e. 5%/ min. 3No ties). Tie warning

Page | 2
Risk Rating Residual Risk Responsibility
Item Activity Potential Hazard Control Measures Monitoring
S L RR S L RR Compliance

signage updated with test results.


Contact to electricity during 4 3 12 1. Ensure that scaffolding to be altered or adopted will far away 4 1 4 Scaffolding
altered or adoption activities or have a proper distance in high voltage wire to avoid contact supervisor,
to electricity. scaffolder and
2. Ensure that there is no any open circuit near to scaffold to be workers
altered or adopted to ensure workers are safe to any
electrocution.
3. Ensure that all power to be isolated near to scaffold work area
prior to commence the work
Slips, trips and fall 4 3 1 1. Ensure that all workers shall follow Company guidance for 4 1 4 Scaffolding
Management of Slips and Trips supervisor,
2. All site personnel are to ensure work area is clear and well-lit. scaffolder and
3. Ensure that working area to be restricted by physical barriers workers
and warning signage, at or underneath the work area to
segregate work from pedestrians, public, other trades, plant
and vehicles to reduce and/ or remove the risk from falling
objects.
4. All materials will be subject to good housekeeping by stacking
materials safely, securely, neatly, tidily and away from access/
egress routes.
5. Designated access/ egress routes only to be used.
6. Operatives to wear slip resistant safety boots. Ensure these
are kept in good condition.
Adverse weather condition 4 3 12 1. Ensure a proper supervision that will monitor the 4 1 4 Scaffolding
environmental working conditions to ensure that operatives supervisor,
are not put at risk. scaffolder and
2. Wet weather gear may be utilized, however supervision will workers
determine when work will cease due to environmental
conditions.
3. No scaffold erection will be allowed if there is any adverse
weather condition to ensure the safety of the workers.
3 Dismantling of Fall from heights. 1. Ensure that all scaffolds will be dismantled in the reverse
scaffolding order of the erection sequence.
2. Ensure that all scaffolders operatives shall received site
specific task instruction before starting the work activity.
3. Specific risk assessment shall be briefed to all individuals
prior to work commencing.
4. Ensure that scaffold to be erect are secured to prevent any
Page | 3
Risk Rating Residual Risk Responsibility
Item Activity Potential Hazard Control Measures Monitoring
S L RR S L RR Compliance

loose connection and fall from heights.


5. Scaffolding shall be inspected for defects or damage prior to
use at site.
6. Ensure a proper supervision.
7. Only competent and trained personnel shall erect the scaffold
structure.
8. Collective fall prevention methods must be given precedence
over personal fall protection, reliance on personal fall arrest
equipment must be considered as a last resort only.
Falls of materials 5 4 20 1. Scaffolds equipment must be transferred by hand or 5 1 5 Scaffolding
mechanical aids only and must never be dropped or thrown. supervisor,
2. Work must never take place over the heads of others. scaffolder and
3. Before scaffold work can dismantling, scaffold Supervisor to workers
establish a suitable exclusion zone, with physical barriers and
warning signage, at or underneath the work area to segregate
work from other trades, pedestrians, public, plant and vehicles
to reduce and / or remove the risk from falling objects.
4. Store materials securely to prevent inadvertent movement, i.e.
fittings to be bagged, long materials stored flat (never upright).
5. Materials must be raised/ lowered in a controlled, hand-to-
hand manner or using a gin wheel and rope.
6. Small and loose materials are to be transferred in bags or
stillages to prevent items falling.
Slips, trips and fall 4 3 1 1. Ensure that all workers shall follow Company guidance for 4 1 4 Scaffolding
Management of Slips and Trips supervisor,
2. All site personnel are to ensure work area is clear and well-lit. scaffolder and
3. Ensure that working area to be restricted by physical barriers workers
and warning signage, at or underneath the work area to
segregate work from pedestrians, public, other trades, plant
and vehicles to reduce and/ or remove the risk from falling
objects.
4. All materials will be subject to good housekeeping by stacking
materials safely, securely, neatly, tidily and away from access/
egress routes.
5. Designated access/ egress routes only to be used.
6. Operatives to wear slip resistant safety boots. Ensure these
are kept in good condition.
Poor manual handling 4 2 8 1. Ensure that all scaffolding operatives will have attended a 3 1 3 Scaffolding
Page | 4
Risk Rating Residual Risk Responsibility
Item Activity Potential Hazard Control Measures Monitoring
S L RR S L RR Compliance

manual handling for scaffolders training. supervisor,


2. When handling materials good manual handling technique to scaffolder and
be utilized. workers
3. All work areas will be barriered off and warning signs posted.
4. Avoid manual handling where possible by using the crane.
5. Unloading / loading / lifting of materials to be completed by
designated slingers/ banksman and crane operator.
6. Material transfer to working area manually where mechanical
means are unavailable.
7. Materials must be raised/ lowered in a controlled, hand-to-
hand manner or using a gin wheel and rope.
8. Heavy or hard to carry items (e.g. beams) should not be
handled by one operative alone, use a buddy system.

Adverse weather condition 4 3 12 1. Ensure a proper supervision that will monitor the 4 1 4 Scaffolding
environmental working conditions to ensure that operatives supervisor,
are not put at risk. scaffolder and
2. Wet weather gear may be utilized, however supervision will workers
determine when work will cease due to environmental
conditions.
3. No scaffold erection will be allowed if there is any adverse
weather condition to ensure the safety of the workers.
Being struck by moving plant of 4 4 16 1. Drivers of vehicles will adhere to on site routes and speed 4 1 4 Supervisor,
vehicles movement limits. Driver, operator,
2. Materials to be delivered/ collected from pre-designated area scaffolder and
on site by HGV all loads are to be pre stropped. workers
3. Edge protection to be fitted to all Lorries.
4. Deliveries are to be pre booked and pick up points agreed.
5. Ensure that equipment (including packing) is stacked within
the perimeter s of the trailer/ vehicle

Prepared by: Noted by: Approved by:

Engr. Francis E. Tan Engr. Badawi Gaber Badawi Engr. Hany Riad

Page | 5
Risk Rating Residual Risk Responsibility
Item Activity Potential Hazard Control Measures Monitoring
S L RR S L RR Compliance

HSE Manager Technical Office Manager Project Manager

Page | 6
Risk Residual Responsi
Rating Risk bility
It
Monitori
e Activity Potential Hazard Control Measures
R R ng
m S L S L
R R Complian
ce

1706‐DEC‐SEC‐GEN‐002 Rev. 2 Page | 7

You might also like