Professional Documents
Culture Documents
Risk Assessment: Erection, Altering and Dismantling of Scaffolding Works
Risk Assessment: Erection, Altering and Dismantling of Scaffolding Works
RISK ASSESSMENT
Operation/ Task: Erection, Altering and Dismantling of Scaffolding Works Risk Assessment No: 2021-001
Location/ Area: Al Sadd, Doha, Qatar Revision No: 01
Applicable To Method Date:
Scaffolding Works Method Statement 04/05/2021
Statement Title & No:
LIKELIHOOD
Certain 5 5 10 15 20 25
Probable 4 4 8 12 16 20
Possible 3 3 6 9 12 15
Improbable 2 2 4 6 8 10
Negligible 1 1 2 3 4 5
CONSEQUENCES Slight 1 Minor 2 Significant 3 Severe 4 Major 5
INTOLERABLE (15 TO 25)
Operations must not proceed: alternative methods to conduct this task must be implemented.
INTERMEDIATE (4 TO 12)
Risks should be reduced to as low as reasonably practicable (ALARM). The higher the risk. The more effort must be given to reducing the risk.
This task should be reassessed at regular intervals to evaluate that the existing control measures are adequate.
TOLERABLE (1 TO 4)
This task may proceed with or without additional control measures. But if measures can be implemented to further reduce risk these should be
implemented.
Possible multiple deaths and/or serious structural An event which is certain to occur unless immediate
MAJOR CERTAIN
damage controls are applied
Possible death, severe multiple injuries (LTI – An event which is likely to occur unless control
SEVERE PROBABLE
Medevac) measures are improved
Possible significant injuries / multiple minor injuries An event which may occur despite existing control
SIGNIFICANT POSSIBLE
(Probable LTI) measures
Possible significant injuries (Medical treatment/first An improbable event, but could occur it control
MINOR IMPROBABLE
Aid) measures are disregarded
Possible slight/no potential risk of injuries(Possible
SLIGHT NEGLIGIBLE .A highly unlikely event
first Aid)
Any number 15 or above is intolerable and the task must not commence until alternative methods have been introduced. Any number 4 to 12 risks are deemed as
tolerable, risks must have been reduced to as low as reasonably practicable (ALARM). Additional control measures may be required and the tasks should be re-
assessed at regular intervals. Numbers 1 to 4 are tolerable, but risks should be reduced further if easily achievable.
Risk Rating Residual Risk Responsibility
Item Activity Potential Hazard Control Measures Monitoring
S L RR S L RR Compliance
1 1.
1.
1.
1.
Adverse weather condition 4 3 12 1. Ensure a proper supervision that will monitor the 4 1 4 Scaffolding
environmental working conditions to ensure that operatives supervisor,
are not put at risk. scaffolder and
2. Wet weather gear may be utilized, however supervision will workers
determine when work will cease due to environmental
conditions.
3. No scaffold erection will be allowed if there is any adverse
weather condition to ensure the safety of the workers.
Being struck by moving plant of 4 4 16 1. Drivers of vehicles will adhere to on site routes and speed 4 1 4 Supervisor,
vehicles movement limits. Driver, operator,
2. Materials to be delivered/ collected from pre-designated area scaffolder and
on site by HGV all loads are to be pre stropped. workers
3. Edge protection to be fitted to all Lorries.
4. Deliveries are to be pre booked and pick up points agreed.
5. Ensure that equipment (including packing) is stacked within
the perimeter s of the trailer/ vehicle
Slips, trips and fall 4 3 1 1. Ensure that all workers shall follow Company guidance for 4 1 4 Scaffolding
Management of Slips and Trips supervisor,
2. All site personnel are to ensure work area is clear and well-lit. scaffolder and
3. Ensure that working area to be restricted by physical barriers workers
and warning signage, at or underneath the work area to
segregate work from pedestrians, public, other trades, plant
and vehicles to reduce and/ or remove the risk from falling
objects.
4. All materials will be subject to good housekeeping by stacking
materials safely, securely, neatly, tidily and away from access/
egress routes.
5. Designated access/ egress routes only to be used.
6. Operatives to wear slip resistant safety boots. Ensure these
Page | 1
Risk Rating Residual Risk Responsibility
Item Activity Potential Hazard Control Measures Monitoring
S L RR S L RR Compliance
Page | 2
Risk Rating Residual Risk Responsibility
Item Activity Potential Hazard Control Measures Monitoring
S L RR S L RR Compliance
Adverse weather condition 4 3 12 1. Ensure a proper supervision that will monitor the 4 1 4 Scaffolding
environmental working conditions to ensure that operatives supervisor,
are not put at risk. scaffolder and
2. Wet weather gear may be utilized, however supervision will workers
determine when work will cease due to environmental
conditions.
3. No scaffold erection will be allowed if there is any adverse
weather condition to ensure the safety of the workers.
Being struck by moving plant of 4 4 16 1. Drivers of vehicles will adhere to on site routes and speed 4 1 4 Supervisor,
vehicles movement limits. Driver, operator,
2. Materials to be delivered/ collected from pre-designated area scaffolder and
on site by HGV all loads are to be pre stropped. workers
3. Edge protection to be fitted to all Lorries.
4. Deliveries are to be pre booked and pick up points agreed.
5. Ensure that equipment (including packing) is stacked within
the perimeter s of the trailer/ vehicle
Engr. Francis E. Tan Engr. Badawi Gaber Badawi Engr. Hany Riad
Page | 5
Risk Rating Residual Risk Responsibility
Item Activity Potential Hazard Control Measures Monitoring
S L RR S L RR Compliance
Page | 6
Risk Residual Responsi
Rating Risk bility
It
Monitori
e Activity Potential Hazard Control Measures
R R ng
m S L S L
R R Complian
ce