Project : San Mateo-Rodriguez Sewerage System-Package 1A-RD

Contractor : China International Water & Electric Corp.


Typical cycle of works : Horizontal Directional Drilling
Duration
Item Duration
Work Description Day Remarks
Work (Day)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42

I For 600mm diameter HDPE

Preparation works / Survey and lay-out 1

Ecavation for the Entry Pit / Exit Pit 6

Setting of HDD 6

Start drilling for pilot bore 4

Enlarging pilot bore 5

Installation of required pipe 6

Removal of HDD / Clearing 6

Tie-in (if No man-hole) 2

Back-filling works 4

Total = 40

NOTE !
TYPICAL CYCLE OF WORKS ARE MADE TO PRODUCE PROGRAMME/WORK SCHEDULE.
NUMBER OF DURATION MAY INCREASE OR DECREASE, IT DEFENDS ON THE ACTUAL SITE CONDITION.