IV. RESULT AND DISCUSSION ii.

Pload in KW
A. SITE LOCATION
Purok 02 Bancod, Indang, Cavite
Calculation of kW load
Number of Houses (considering of 50-60% Calculated kW load
B. TRANSFORMER TYPE RATING by 15 range of DF in increment per 15 houses
Single-phase Transformer with 50kVA rating order)

C. COMPUTATION 15 15 * 0.505 * 1kW 7.575 kW


i. Assumed KWload rating per House based on DT Rating 30 15 * 0.511 * 1kW 7.665 kW
@ 144 number of houses connected in a 50 kVA Distribution
Transformer 45 15 * 0.522 * 1kW 7.830 kW
@ 1 kW load per house (assumed value) 60 15 * 0.527 * 1kW 7.905 kW
@ 5.92 kW load of the reference house 75 15 * 0.533 * 1kW 7.995 kW
90 15 * 0.539 * 1kw 8.085 kW
Appliances Quantity Watts Wattage 105 15 * 0.544 * 1kW 8.160 kW

Rice Cooker 2 700 1400


120 15 * 0.553 * 1kW 8.295 kW
135 15 * 0.567 * 1kW 8.505 kW
Electric Stove 1 1000 1000
143 8 * 0.574 * 1kW 4.592 kW
Electric Kettle 1 1400 1400 1 * 0.560 * 1kW
144 (reference house) 3.315 kW
Table Fan 5 50 2250
LED Light Bulb 6 12 72 Ptotal 79.922 kW
Flat Iron 1 800 800
Handheld iii. KVA load considering 95% p.f.
1 1000 1000 S = P / p.f.
Steam Iron
Total 5922 S = 79.922 kW / 0.95 = 84.128 kVA

Total Power of the Reference House 5.92 kW iv. Transformer Loading %


% = kVA load / kVA rating
% = (84.128 kVA / 50 kVA) * 100%
% = 168.256 % (Overloading)

PROJECT NAME: DRAWN BY: DRAWN DATE: DWG NO.:


CAPARA, ANTONETTE B. 04-07-24
DISTRIBUTION TRANSFORMER MAPPING 202102740 SUBMISSION DATE: 01
BSEE 3-1 04-15-24
SINGLE PHASE RESIDENTIAL LAYOUT APPROVED BY: DRAWING SCORE: 03
SUBJECT: EENG 80 - ELECTRICAL SCALE: ACTIVITY ENGR. ABEGAIL R. RAREZA Final Grade
GROUP NO.
APPARATUS AND DEVICES
NTS NO.01 INSTRUCTOR as per Rubrics