Fast guideof installation
Index
Introduction................................................. ..................... 05
01.Scope of this guide................................................ .......................................05
Page 02
Fast guideof installation
Index
A. UNI-Rivet exposed fixation..................................................................................23
B. UNI-Rivet visible fixation – EQUITONE[line].................................................. ....25
C. NV3 hidden fixation.................................................. ....................................26
Cleaning................................................. ........................... 48
24.Dust removal, general considerations................................................48
25.Dirt from perforation of panels on the façade ...........................................48
26.Cleaning of the finished facade................................................... ....................48
27.Using different cleaning cloths................................................ ......49
28.Cleaning other types of stains on EQUITONE[tectiva], [line] ..............49
29.Cleaning other types of stains in EQUITONE[natura], [natura pro], [pictura],
[textura].......................... .................................................. ............49
30.Cleaning other types of stains on EQUITONE[materia], [lunara]...........50
31.Cleaning efflorescence stains ........................................................... ...........fifty
Disclaimer................................................. ..................................51
Guarantee – Acceptance of materials ........................................................... .....................51
Resignation................................................. .................................................. ...........51
Page 03
Fast guideof installation
Introduction
Before starting
02. Security and health
This guide does not address health and safety requirements, all national and local health
and safety regulations must be complied with.
When more than one pallet of material is needed to carry out the work, it is necessary that the
panels from different pallets be mixed; mixing will guarantee heterogeneity.
Page 05
Fast guideof installation
EQUITONE (picture)
EQUITONE (texture)
EQUITONE (matter)
2,500 2,500
1,250
1,250
3,050 3,100
1,220
1,250
Panel thickness[mm] 8 10 12 8 10 12
Page 06
Fast guideof installation
Page 07
Fast guideof installation
Page 08
Fast guideof installation
Page 09
Fast guideof installation
Leveling clamp They level and fix the panels, they are
and NV3 fixation placed at the upper ends of each
panel. Only two are used per panel,
fixing only one of them.
Page 010
Fast guideof installation
Page 011
Fast guideof installation
Page 012
Fast guideof installation
Page 013
Fast guideof installation
þ EQUITONE [nature]
þ EQUITONE [natura]pro
þ EQUITONE [picture]
þ EQUITONE [matter]
þ EQUITONE [texture]
Face side
Face side
Protection sheet
When handling or cutting panels, place them on the pallet in the same way they were
delivered. Stack the face side against the face side with the protective sheet between
them, and so on. This will prevent scratches and damage to the surface of the panels.
Page 014
Fast guideof installation
It is important that the insulation is well fixed to avoid the risk of the chamber becoming
blocked in the event of detachment.
In addition to the openings that allow ventilation of the chamber at the top and
bottom of the façade, it is also important that air can enter and exit below and
over window openings, doors...
It is recommended to protect the joints between panels of more than 12 mm from the entry
of birds, animals and dirt.
* The dimensions and dimensions of the sketch are the minimum recommended for the correct functioning of
the ventilation and optimal performance of the panels.
Page 016
Fast guideof installation
Page 017
Fast guideof installation
In situations where this is not possible, cutting can be done on site following
the following recommendations regarding tool and procedure.
A. Tool requirements
TO.
c.
b.
Page 018
Fast guideof installation
The workbench must be stable and covered with a clean, soft material to avoid
scratches and marks on the panels.
Page 019
Fast guideof installation
Never cut multiple panels together at the same time. Only one panel should be
cut at a time.
When curved cuts are made the panelsEQUITONEThey are usually placedface
down and the cut is from the back.
Follow the subsequent sanding and cleaning procedures described in the previous section.
Never cut multiple panels together at the same time. Only one panel should be
cut at a time.
Page 020
Fast guideof installation
This effect will disappear over time, when carbonation of the fiber cement
pores occurs naturally. The time period depends on weather conditions.
To help prevent this phenomenon from occurring, the edges ofEQUITONE [nature]and
EQUITONE [natura]promust be impregnated with Luko edge sealantafter cutting, sanding and
cleaning.
Do not apply Luko in wet conditions, or without sanding and cleaning the panel
before application.
Page 021
Fast guideof installation
F. Application procedure
1 2 3
Apply Luko between +5C and After sanding the edges of Pour Luko into the clean
25C.Treat one panel at a the panel remove all the tray. Only the one that
time. dust from the edges by can be used within 30
cleaning them. minutes. Do not pour
leftover Luko back into
the container.
4 5 6
Page 022
Fast guideof installation
For installation using UNI-Rivet riveted visible fixing, the panels must be drilled with the
fiber cement drill bit.EQUITONEø11mm on the visible side of the panel.
DRILL DRILL
MASONPOSTER EQUITONE
It is recommended not to drill the panel placed on the façade as the dust will
spread over large areas and will be difficult to clean.
The panel must be kept firmly attached to avoid vibrations. Turn off the hammer
function on the drill as this can cause it to move and slip.
Drill only one panel at a time. Do not drill multiple panels at the same
time, the slightest movement can cause the holes to end up in the
wrong position.
Page 023
Fast guideof installation
Mark the drill positions precisely. Use a white or red pencil to highlight the
position of the hole, especially on gray or dark gray panels. Use small
crosses, this will reduce time and cleanup.
Consult the Architect's drawings for the position of each UNI-Rivet. The centers for
the rivets are determined based on calculations.
The position of corner drill for vertical substructure should be within the
following range:
Dimensions [mm]
30 30
80
80
8-12
80
80
30 30
8-12
Page 024
Fast guideof installation
The most suitable corner rivets location is V = 80 mm from the horizontal edge and H
= 30 mm from the vertical edges.
For the installation of EQUITONE [linea] the use of the EQUITONE Linea drill bit is
mandatory.
Page 025
Fast guideof installation
For the installation of EQUITONE with the NV3 hidden fixing system, the use
of the specific NV3 drill bit is mandatory.
Page 026
Fast guideof installation
Dimensions [mm]
8-12
75
75
75 75
8-12
Detail
30
75 75
The anchor closest to the corner has the following edge distances.
The hole closest to the corner should be within the area shown below.
The centers for the rest of the panel supports are determined based on the wind load
calculations.
> 30
Page 027
Fast guideof installation
Ensure that anchors specified by the engineer are used and placed correctly, in
form, quantity and position.
Material Aluminum
Page 028
Fast guideof installation
If black profiles are specified, it is recommended that they be anodized for their
durability.
In the case of using galvanized steel profiles, Omegas and U profiles will
be used instead of T and L, minimum thickness 1.5mm and minimum
protective coating Z275.
The T and L profiles will be placed securing them to the wall using brackets supported
on thermostops.
Each T and L profile will have a weight square, which supports all the weight and must be
fixed in all the holes.
The rest of the escutcheons are mobile, they will be fixed in all the slots, in the center of them.
Page 029
Fast guideof installation
Facing
Thermostop
Squad
Profile
The number of squares per section of profile is determined by the wind and deformation
calculation, according to current regulations.
It is recommended that the profiles have the maximum length of the height between
slabs. A minimum space of 20 mm must be left between adjacent profiles.
Page 030
Fast guideof installation
Page 031
Fast guideof installation
Page 032
Fast guideof installation
The horizontal profiles cannot protrude from the last vertical profile more
than 75 mm.
The horizontal profile is riveted or screwed to the vertical L-profiles. This should be
done with fixed and sliding points. Each horizontal profile is normally 3 m long.
Leave an expansion space of 20mm - 30mm between adjacent profiles.
Facing
Thermostop
Squad
Profile Staple
Screw
Horizontal profile
Page 033
Fast guideof installation
75 75
Check that the profiles are level and in correct position. It is easier to level vertical
profiles than horizontal ones. Any uneven profiles will cause stresses in the panels
and may be visible once the façade is completed.
Page 034
Fast guideof installation
Aluminum
Galvanised steel
Stainless steel
Page 035
Fast guideof installation
Page 036
Fast guideof installation
1
Only 2 RED-STOP pointsper panel and placed in different profiles.
2
RED-STOP points will be placed as close as possible to the central area of the panel, the
panel cdg, or above it.
3
The RED-STOP points of a panel should never be placed on the same profile.
Page 037
Fast guideof installation
4
The RED-STOP points of two adjacent panels must never coincide on the same profile.
5
It is very important that whatever option is chosen, the location of the RED-STOP
pointsin all panels is the same.Always to the left, or always to the right.
Page 038
Fast guideof installation
Page 039
Fast guideof installation
fixed point
mobile point
Page 040
Fast guideof installation
Insert the centererEQUITONEø4.1 mm into the ø11 mm holes and drill the metal profile.
Remove the r
3.2Rivet
fixed point
Page 041
Fast guideof installation
Set this panel as the first panel. Continue across the façade moving the support
profile as work progresses. When the top row panels are in place, remove the
support profile.
Measure down from the bottom edge of the top Panel height plus joint
fixed panel and mark the position of the bottom
edge of the next row of panels. This measurement 1
is equivalent to the height of the panel plus the
horizontal joint (8 - 12 mm).
Page 042
Fast guideof installation
The panel must rest on a hard, firm surface and be fully supported.
It is advisable to start with the leveling and fixing staples in the upper corners, remember
that there are only two per panel. Later, the rest of the panel staples will be fixed.
Before placement there may be a small gap between the head of the TUF-S and the staple.
Page 043
Fast guideof installation
Pull the rivet gun away from the panel during mandrel removal.
Only one of the two leveling clips is fixed per panel, always the one on the
same side of the panel.
Page 044
Fast guideof installation
TO b c
TO c c b
c c c c
c c c c
Page 045
Fast guideof installation
The clips used in the top corners of the panel have threaded screws that
allow the panel to move up and down to achieve correct alignment. These
staples also support the weight of the panel.
To prevent lateral movement of the panel, a leveling claw is fixed using locking
screws or clips. Make sure this occurs on the same side of the panel, either the
entire right side or all the leveling brackets on the left side.
The rest of the clips do not have any means of adjustment, they are used to resist wind
loads.
Leveling screw
Fixing screw
Horizontal profile
Leveling clamp
Page 046
Fast guideof installation
Lift the panel onto the horizontal profiles making sure the interlock on the
hanging brackets is aligned with the horizontal profile.
Insert a suspension lock as described by the supplier to prevent the panel from
moving laterally.
5 6
3 4
1 2
Page 047
Fast guideof installation
Cleaning
24. Dust removal, general
considerations
· Use tools with a dust extraction system.
Page 048
Fast guideof installation
Page 049
Fast guideof installation
Page 050
Fast guideof installation
Disclaimer
The information in this document is correct at the time of issue. Keep in contact
withEQUITONEto make sure you have the most recent version.
All information contained in this Guidance Note is protected by copyright
©.
All figures contained in this document are illustrations and should not be used as
construction drawings.
Equitone will provide a guarantee on materials that have been installed in accordance with the
current “Equitone Installation Guide” and on ventilated façades. The use of unrectified panels
voids the warranty.
It is the installer's responsibility to ensure that the materials, at the time of delivery,
are correct and suitable for use. If it is considered that the material is not suitable, it
should not be installed, you should immediately contact the Technical Office of
EQUITONE.
Resignation
The information in this document is correct at the time of issue. Due to our
continuous development program of products and systems, we reserve the right to
modify or alter the information contained therein without prior notice. Keep in
contact withEQUITONEto make sure you have the most recent version. All
information contained in this Guidance Note is protected by copyright ©.
All figures contained in this document are illustrations and should not be used as
construction drawings.
This information is provided in good faith.
Page 051