Professional Documents
Culture Documents
Flare Header Failure: An Investigation: Safety/Loss Prevention
Flare Header Failure: An Investigation: Safety/Loss Prevention
Prevention
J. THARAKAN, Suncor Energy Products,
Calgary, Alberta, Canada
110 ft
Failure-2
Failure-3
Failure-1
60-in. flare
header From coker
To flare unit
knockout pot
P
rocess hazards analyses will be no hazard if the plant is oper- lected top event.
(PHAs) are structured reviews ated within design parameters, and Quantitative risk assessment (QRA).
during the engineering design analyzes deviations of the design vari- QRA is the systematic development
process intended to detect potential ables that might lead to undesirable of numerical estimates of the ex-
hazards that were not addressed by consequences for people, equip- pected frequency and consequence
the design team. This one-page refer- ment, environment, plant operations of potential accidents based on engi-
ence describes commonly employed or company image. If a deviation neering evaluation and mathematical
PHA methods. is plausible, its consequences and techniques. The numerical estimates
probability of occurrence are then can vary from simple values of prob-
PHA methods studied by the HAZOP team. Usually, ability or frequency of an event occur-
PHAs are often conducted or moder- an external company is hired to inter- ring (based on relevant historical data),
ated by a specialist, with participation act with the operator company and to very detailed frequency modeling
by the design team, owner’s employ- the engineering company performs techniques. The events studied are
ees or experienced operators. Sev- this study. Evaluating risk involves the release of hazardous or toxic ma-
eral PHA methodologies exist, each multiplying the consequence level by terials, explosions or boiling liquid ex-
suitable for specific purposes and for the frequency of occurrence. panded vapor explosion (BLEVE). The
certain phases of project develop- Layer-of-protection analysis results of this study are usually shown
ment and plant lifecycle (Figure 1). (LOPA). This method analyzes the on top of the plot plan.
Consequence analysis. This meth- probability of failure of indepen- Failure mode and effects analysis
od quantitatively assesses the con- dent protection layers in the event (FMEA). This method evaluates the
sequences of hazardous material re- of a scenario previously studied in ways in which equipment fails and the
leases. Release rates are calculated a quantitative hazard evaluation like system’s response to the failure. The
for the worst-case and alternative HAZOP. It is used when a plant uses focus of the FMEA is on single equip-
scenarios. Toxic points are defined instrumentation independent from ment failures and system failures.
and release duration is determined. operation (safety instrumented sys-
Hazard identification analysis (HAZ- tems to assure a certain safety integ- Timing
ID). HAZID is a preliminary study per- rity level (SIL)). The study uses a fault Methods have more impact in some
formed in early project stages when tree to study the probability of failure design phases than others. For ex-
hazardous material, process informa- on demand (PFD) and assigns a re- ample, if a consequence analysis
tion, flow diagrams and plant location quired SIL to a specific instrumen- is not performed in a conceptual or
are known. It is generally used later on tation node. For example in petro- pre-FEED (front-end engineering and
to design the preliminary piping and leum refineries, most companies will design) phase, important plot-plan
instrumentation diagrams (P&IDs). maintain a SIL equal to or less than considerations can be missed. Oth-
What-if. This is a brainstorming 2 (average PFD ≥10−3 to <10−2), and ers, like HAZOP, cannot be devel-
method that uses questions starting a nuclear plant will tolerate a SIL 4 oped without a control philosophy or
with “What if . . . ?,” such as “What if (average PFD ≥10−5 to <10−4). P&IDs, and are performed at the end
the pump stops running?” or “What if Fault-tree analysis. Fault-tree anal- of FEED or detailed engineering (or
the operator opens or closes a certain ysis is a deductive technique that both) to define and validate pressure
valve?” Participation by experienced uses Boolean logic symbols (that is, safety valve locations and other pro-
staff is important to foresee possible AND or OR gates) to break down cess controls and instrument safety
failures and identify design alterna- the causes of a top event into basic requirements. QRA or LOPA (or both)
tives to avoid them. equipment failures or human errors. are done after HAZOP to validate sit-
Hazard and operability study The immediate causes of the top ing and define SIL levels and meet
(HAZOP). This technique has been event are called “fault causes.” The the level required by the plant. n
a standard since the 1960s in the resulting fault-tree model displays
Editor’s note: This column was adapted from the following article:
chemical process industries. It is the logical relationship between the Giardinella, S., Baumeister A. and Marchetti, M. Engineering for Plant
based on the assumption that there underlying basic events and the se- Safety, Chem. Eng. August 2015, pp. 50–58.
• Expert judgement • HAZID • HAZOP • HAZOP • Inspections • Preventive and corrective • HAZID
• High level risk • What-if • LOPA • Constructability • Materials and maintenance checks
identification • Consequence analysis • QRA review equipment tests • Periodically check instrument
• FAT & SAT and relief-valve calibration
FIGURE 1. Typical hazards analyses that are used throughout a CPI project lifecycle • Hydrostatic tests • Periodic hazards analysis
Kim, et al. proposed Eqs. 7–9, which are based on Eq. 6.3 A com-
⎡ −2 × ∫ pp v × dp ⎤
(3)
G2 = ⎢ 0
⎥ pressible fluid reaches a condition of maximum flow when the
2
⎣⎢ v t ⎦⎥ velocity at the nozzle reaches the speed of sound. The isentro-
pic maximum mass flux for Eq. 2 is given by Eq. 7. Eqs. 7 and 8
where, are in an identical derivative form.
G = the mass flux through the nozzle, lb/sec-ft2 An identical and simple equation form for both critical mass
P = the pressure of the fluid, psia flux and subcritical mass flux is preferred to simplify the calcula-
v = the specific volume of the fluid, ft3/lb tion method. This allows for an analytical solution for mass flux
t = the throat of the nozzle. calculations to make the numerical integration easier. Eqs. 2 and
The calculation precision associated with the HDI method 3 are in an identical integral form rather than derivative. The
is determined by the size of the pressure intervals, with small- integral form does not allow the analytical solution for mass flux
er pressure intervals providing better results. Some cases may calculations. Eq. 9 is derived from Eqs. 3 and 8, and has been
require many data sets for acceptable sizing results. The HDI upgraded here to handle slightly subcooled liquids. Eq. 9 sim-
method requires intensive computational efforts; however, the plifies the numerical integration and provides rigorous results.
numerical integral result can also be obtained accurately and Both Eqs. 7 and 8 provide the results of P-v equation-based in-
quickly if evaluated analytically with pressure-specific volume tegration. This new method is applicable to compressible fluids
(P-v) models or employed P-v models. (vapors and two-phases, including slightly subcooled liquids):
β +1
Reduced P-v models. The equation of state (EOS) typically ⎛ −∂P ⎞ pec−max
Gc = ⎜ ⎟ = 68.07 ×
involves four variables. Simpson presented a total of six reduced (7) ⎝ ∂v ⎠ s α × β × p0β × v0
P-v models involving only two variables.2 The reduced P-v
model is obtained by a few constant entropy flash calculations,
for which the specific volume reflects changes in the compress- (8) pecβ +1
G = 68.07 ×
ibility factor, pressure and temperature. The reduced P-v model α × β × p0β × v0
based on the homogeneous equilibrium model (HEM) well 1
−2
represents the pressure expansion processes in the PRV. ⎡ ⎡ β ⎤ ⎤ β +1
⎢ −2 × α × β × P × ⎢α ×
β ⎛ p ⎞ ⎥
This article evaluates two out of the six P-v models and a 0
⎜⎝ p ⎟⎠ − α + 1 ⎥ ×
conventional model in a simple vapor equation to select the ⎢ 0
⎢⎣ ⎥⎦ ⎥
⎢ ⎥
best P-v model for isentropic expansion flow. Eq. 4 is good Pec = ⎢⎛ β ⎥
⎞
for ideal vapors, but not suitable for flashing liquids. Eq. 5, the ⎢ ( p0 − psc ) + α × p0 × p1−β − p1−
( β
) + ⎟ ⎥
⎢ ⎜ 1− β
0
⎥
Omega method, is good for flashing liquids, but not so suitable (9)
⎢⎜⎜ ⎟ ⎥
⎣⎢⎝ (1− α ) × ( p − p0 )
for vapors. The two-point Omega method is most widely used ⎟⎠
for sizing two-phases. Eq. 6 is a combination of Eqs. 4 and 5, so ⎦⎥
it should be suitable for both vapors and two-phases. Simpson where,
noted that Eq. 6 is the only reduced P-v model that gave consis- ec–max = the critical pressure (Pc ), maximum
tently outstanding fits of the data. equivalent pressure
ec = the equivalent critical pressure at the calculated mass flux
1
⎛ p ⎞n
sc = the subcooled liquid.
v = v0 × ⎜ 0 ⎟
(4) Eq. 10 has been developed to determine if a subcooled liq-
⎝ p⎠ uid is compressible or incompressible. Eq. 10 is similar to the
API 520 Part 1 Equation (C.32), but easier to follow. If the sub-
v P
− 1 = ω × ⎡⎢ 0 − 1⎤⎥
(5) cooled pressure is greater than the calculated Pec–max , the fluid is
v0 ⎣P ⎦ incompressible; the fluid is not considered a slightly subcooled
β
liquid because there is no change in density during the expan-
v − 1 = α × ⎡⎛ P0 ⎞ −1⎤ (6) sion process. In this case, the fluid should be sized using a liquid
⎢⎝ ⎠ ⎥
v0 ⎣ P ⎦ equation and the fluid chokes at the saturated pressure. If the
subcooled pressure is not greater than the calculated Pec–max , the
where, fluid is compressible. In this case, the fluid should be sized as a
n,ω,α,β = the P-v model constants. two-phase fluid:
For subcooled liquids, the initial pressure (P0 ) shall be at the p0
saturated pressure, ignoring subcooled conditions. Eq. 5, a two- Psc−max = p0 +
(10)
2×α ×β
point method, uses two data sets at initial pressure and typically
90% of the initial pressure. Eq. 6, a three-point method, uses For subcritical mass flux, use Eqs. 8 and 9. The Pec in Eq. 8 is
three data sets at initial pressure, a middle pressure and 50% of calculated using Eq. 9 at P (typically at backpressure) without
the initial pressure (not greater than the critical pressure). iteration. For critical mass flux, use Eqs. 7 and 9. The Pec–max in
Eq. 7 is also calculated using Eq. 9 at P (initially at backpressure)
Upgrading the numerical integration method. A new with iteration until Pec is equal to P. The calculated Pec replaces
approach to make the rigorous HDI method more convenient P in the next trial. The maximum Pec value (Pec–max ) is obtained
is discussed here. To reduce significant computational efforts, when Pec is equal to P.
24 JULY 2022 | HydrocarbonProcessing.com
Valves, Pumps and Turbomachinery
Critical pressure can also be obtained from the following non-ideal vapors at the relief conditions is often used because
approximations (Eqs. 11 and 12) developed based on the it is readily available. A constant isentropic expansion coeffi-
Omega method. cient can be easily back-calculated using Eq. 14 if the C value
is known. Eq. 14 can be expressed in terms of two-parameters
pc = ncβ
(11)
−0.727144
× p0 + 1− ncβ(× p0 ×
−0.727144
) in a P-v model, critical pressure and initial relief pressure, as
shown in Eq. 15. The C value can be calculated by other meth-
⎛ p0 ods if the mass flux result is validated. Eq. 15 is recommended
1− 2 × α × β + × (1 + 2 × α × β ) × ⎞ as the calculation method of choice as a result of the reduced
⎜ psc ⎟
⎜ ⎟ P-v model evaluation.
⎜ ⎡ psc ⎛ 2 × α × β −1 ⎞ ⎤ ⎟ Cp
⎜ ⎢1− 1− × ⎜ ⎟ ⎥ ⎟ v ⎛ ∂p⎞
p0 ⎝ 2×α ×β ⎦ ⎠ n = −
(13) × ⎜ ⎟ ×
⎜ 1− ⎣ ⎟ P ⎝ ∂v ⎠ T C v
⎜ 1− 2 × α × β + (1 + 2 × α × β ) × ⎟
⎜ ⎟ n+1
⎜ ⎡ 1 ⎤ ⎟ 2 ⎞ n−1
⎜ ⎢1−
× α × β ⎥ ⎟ C = 520 × n × ⎛
(14)
⎜ ⎣ 2 ⎦ ⎟ ⎝ n +1 ⎠
⎝ ⎠
β +1
1 ⎛p ⎞
(
⎡1 + 1.0446 − 0.0093431 × α 0.5 × ⎤ ) ( −0.70356 +
0.014685 × ln α ) C = 520 ×
(15) α ×β
× ⎜ c ⎟
⎝ p0 ⎠
nc = ⎢ ⎥
(12)⎢⎣α −0.56261 ⎥⎦ Kim proposed Eqs. 15–17 at the API SCPRC Meeting.4
Eq. 15 is derived from Eqs. 1 and 7.
All values of nozzle pressure and Pec , along with mass flux, The polynomial Eqs. 16 and 17 are used to estimate the
are plotted in FIG. 1 to tangibly illustrate the relations among constant isentropic expansion coefficient for two different C
nozzle pressure, Pec , Pc and mass flux for API 520 Part 1, Ex- ranges. The C value is a result of the most rigorous calculation
ample B.3.3. The green line shows the subcritical mass flux method. This may be an outstanding solution for constant is-
calculations for a known backpressure (at P, greater than the entropic expansion coefficients. This approach allows a sim-
critical pressure). In subcritical flow, there is no iteration. Be- ple vapor equation to be extended to any compressible fluid,
cause Eq.9 provides a result of equivalent critical pressure at including slightly subcooled liquids because Eq. 1 is based on
the integrated mass flux from initial pressure to the backpres- Eq. 4. Therefore, a simple vapor equation can be applied to
sure, the calculated Pec is directly used for the mass flux calcu- any compressible fluid, not only to ideal vapors.
lation. The calculated Pec value shall be less than the known However, n should be a constant isentropic expansion coef-
backpressure (P). ficient obtained from Eq. 14 to be compatible with a simple
The red line shows the critical mass flux calculations for a vapor equation. The constant isentropic expansion coefficient
known backpressure (at initial P, the backpressure is not great- reflects the assumption of ideal vapor relationship in Eq. 14
er than the critical pressure). In critical flow, the calculations since it is simplified for ideal vapors with the ratio of the ideal
are repeated until the calculated Pec is equal to P. The mass gas-specific heats; therefore, the constant isentropic expansion
flux and Pec are maximized at the critical pressure (Pc ). In the coefficient is different from the average isentropic expansion
critical flow region, the maximum mass flux is taken at Pc be- coefficient. For a non-ideal vapor, an average isentropic expan-
cause a further decrease in nozzle pressure does not affect the sion coefficient can result in undersized PRVs. For an ideal va-
mass flux. The calculated Pec also decreases as the P is further por, an ideal gas-specific heat ratio at the relief inlet conditions
decreased below the critical pressure. can be used as a constant isentropic expansion coefficient.
The HDI method uses only one blue graph. The upgrad-
ed integration method uses two graphs (blue graph and gold
graph). The two graphs intersect at Pc . Using the two graphs
significantly improves obtaining the critical pressure point
quickly and accurately. Eq. 9 is used to calculate both the Pec
for subcritical mass flux and the Pec–max (Pc ) for critical mass
flux. The upgraded integration method quickly determines if
the flow is critical or subcritical. However, the HDI method
should complement the Eq. 2 calculations to determine if the
flow is critical or subcritical.
Takeaways. The above proposed method for sizing com- LITERATURE CITED
pressible fluid PRVs using a simple vapor equation is an out- Complete literature cited available online at www.HydrocarbonProcessing.com.
LEADING
Electricity generated can be stored at mass scale by a plant or by many
and transmitted to other facilities to gas-producing facilities that are
TECHNOLOGY
meet their daily operational needs, in close vicinity. Unwanted gas
or it can be sold to other users and produced in all facilities can be
FOR HYDROGEN to generate revenue. The amount
of gas to be flared is reduced, as
stored and cooled at a common
“gas-to-liquid conversion plant”
SOLUTIONS electricity is generated by using
site-produced gas that otherwise
and then transported to other local
and international market for sale.
would have been flared, resulting in
↘ PROCESS GAS GHG emissions reductions. Takeaway. While these strategies will
• Gas-powered e-frac fleets— not completely eliminate gas flaring,
COMPRESSORS This system utilizes modular gas they provide viable paths to reduce the
turbine generators that run on extent of gases to be flared and means to
↘ HEAT EXCHANGERS site-produced gas rather than diesel utilize them more effectively. Compa-
used in a conventional system. nies should utilize flaring strictly for the
↘ MEMBRANE Electricity generated is used to safety of plants in upset or emergency
power pressure pumps and other conditions. Routine flaring should be
TECHNOLOGY electrical items onsite. diminished progressively to zero flaring
• Gas-powered onsite equipment— by applying strict regulations. Govern-
Some companies manufacture ment and companies should collaborate
heavy machines or equipment that and support each other for effective
www.borsig.de utilize gas as fuel. They also offer monetization of such hydrocarbon re-
the service to modify the existing sources and unwanted gases to eliminate
BORSIG GmbH
Phone: + 49 (0)30 4301-01
machineries and heavy vehicles to routine flaring.
Fax: + 49 (0)30 4301-2236 run on gas against conventional fuel
ANUJ RASTOGI is a Mechanical
E-mail: info@borsig.de diesel. Utilizing the site-produced Engineer with Fluor Daniel India
Egellsstrasse 21 gas in these machines can save fuel Private Ltd. New Delhi and has been
13507 Berlin with the company for 11 yr. He has
Germany
costs and reduce gas flaring.
more than 16 yr of experience in
• Small-scale gas-to-liquid packaged equipment and holds a BE
conversion plants—This degree in mechanical engineering.
Avoidance of nuisance alarms. During the FEED stage, following example of a typical low-pressure alarm on a cooling-
the team develops the alarm documentation, considering every water main header in a process unit is used for explanation of
single possibility where process alarms are needed to monitor alarm priority (FIG. 2). Alarm priority for a low-pressure alarm
the behavior of a particular process unit. During the detailed on a cooling-water header should be defined as high priority.
engineering phase, the client’s operations team may recom- In the event this alarm goes off, it is very important for the op-
mend that nuisance alarms be removed from the list of process erator to acknowledge it and to take corrective action immedi-
alarms where they may be redundant or not significant for the ately by identifying the cause of the alarm. Low pressure would
operator to monitor during plant operations. A typical example result in a low flow, leading to starvation on the cooling-water
would be a pressure alarm on the potable water line inside the exchangers and to high temperatures inside the process units,
unit. Operations typically advises that the interconnecting subsequently leading to an upset of the process unit. Therefore,
units should have alarms on their headers to avoid multiple it is defined as a high-priority alarm that can notify the operator
monitoring within the process unit, as well. The rationalization about the severity of the upset.
of alarms should take place under the guidance of the client
operations team and streamlined to keep only those process Time for the operator to act on an alarm. This is an impor-
alarms that are vital for proper plant operation. tant aspect that needs significant attention. The primary objective
of a process alarm is to alert the operator about a possible devia-
Prioritizing process alarms. Prioritizing a process alarm tion from the normal operating range. The alarm provides the op-
means assessing a risk associated with a process alarm and ad- erator a chance to take predefined corrective actions to mitigate a
vising the operator about the magnitude of impact on plant potential trip scenario. The emergency shutdown of a process unit
operations—especially with respect to process safety—if the can lead to production losses and negatively impact the plant life
alarm goes unattended. An emphasis should be placed on de- due to the sudden fluctuation in the operating conditions caused
fining the priority for an alarm. There can be cases where some by an abrupt shutdown. Importance should be given during the
process alarms are initially labeled as high-priority alarms, but, design phase to ensure that sufficient response time is available
after a detailed analysis and discussion, the priority is lessened. for the operator should an alarm go off. Alarms with very little
The same is true for low-priority alarms that can be upgrad- operator response time are seldom useful and contribute to the
ed to high-priority levels. Too much conservatism should be overall alarm count without adding much value. Consideration
avoided in defining the priorities for alarms. The number of should be given to categorize such alarms with a lower priority.
high-priority alarms should be optimized to ensure that the op-
erator is not overburdened in case of an emergency.
Alarms are typically categorized into high, medium and low
priority, although the exact nomenclature may vary as defined
by the specific design practice applicable for that project. The
Battery limit Pressure signal
Pressure signal
To SRU train 1
Pressure signal
PT
Acid gas To SRU train 1
PI
L
PT
Cooling water
SUBSCRIBE NOW!
HydrocarbonProcessing.com/Podcasts
From supply header
TI
H or equipment maintenance. Alarms with a suppression require-
L ment should be identified and documented to make the unit
TT
operator aware of the suppression aspect of a process alarm.
The automation contractor should devise a methodology to
suppress alarms that will go off during a particular mode of op-
eration. For example, in a typical process unit, when the feed is
cut in, the low-level alarms will go off in most of the vessels in
the unit, especially in the feed knockout drum, leading to con-
Feed heater H fusion during the startup. Such alarms are suppressed until a
AI
steady-state operation is achieved. The operator can change the
status of such alarms from a suppressed state to a normal state
AT SS in the distributed control system once the unit is stabilized and
Feed + hydrogen normal liquid levels are achieved.
Hydrotreater Sulfur absorber
Clearly defined operator actions. The corrective actions
FIG. 3. Sulfur slippage from hydrodesulfurization reactors. to be performed by an operator in case of the activation of an
alarm should be clear, specific and realistic in nature. The ac-
Mode-dependent alarms (alarms during normal opera- tions for panel operators and for field operators should be seg-
tion, startup or shutdown). Mode dependency is another regated and documented. If possible, actions may be outlined
vital aspect to be defined during the alarm management study. in a sequential manner in order of importance. The response
The client’s operations team should advise to clearly define the time available for the operators is usually minimal; therefore, it
alarms that are mode dependent (i.e., to categorize based upon is important to avoid assigning any unnecessary and irrelevant
startup, shutdown and normal operation). This provides a deep actions. Clearly defined actions provide a clear path forward
insight to operators to understand the applicability of the alarm for the operators, allowing them to revive the process to avoid
during a particular phase of operation of a process unit. a plant upset or trip. Obtaining a clear understanding and agree-
ment from operators is essential.
Alarm verification. It is not uncommon to have spurious
alarms in a refinery. It is always useful if the alarm can be verified Takeaway. Alarms play an important role in normal plant opera-
with the help of another independent instrument reading. It is tions, as well as during startup and shutdown scenarios. Proper
advisable to consider a realistic alarm verification. For example, configuration and definition of alarms are of prime importance.
a pressure alarm in a process stream should be verified against A prime concept that is often neglected involves considering the
another independent pressure instrument (such as a pressure inputs from the end users of these alarms, i.e., the plant operators.
gauge), and an indirect verification (e.g., flowrate) should be During the design phase for alarm configurations, it is important
avoided. However, there may be certain instances where an indi- to consider the operators’ perspectives and provide the best pa-
rect verification cannot be avoided. The following example from rameters for configuring them as defined in this article. This also
a hydrogen production unit explains the difference between a ensures that the proper priorities and corrective actions are con-
direct and an indirect verification. sidered against each alarm. Therefore, it is important to configure
The hydrodesulfurization section of a hydrogen production alarms by taking into consideration the operators’ perspectives
unit typically consists of a hydrotreater and a sulfur absorber. for a safe, continuous and optimum operation of the facility.
The mixture of the hydrocarbon feed and hydrogen is heated to
the desired inlet temperature before entering the hydrotreater. NOTE
The sulfur compounds present in the hydrocarbon feed are con- The conclusions presented in this article are solely those of the authors and can-
verted to hydrogen sulfide (H2S) in the hydrotreater and are sub- not be ascribed to Fluor Corporation and/or any of its subsidiaries.
sequently absorbed in the sulfur absorber. Inefficient operation DEBOPAM CHAUDHURI is a Senior Process Engineer with Fluor
of the hydrodesulfurization section may cause sulfur slippage, New Delhi. He has more than 20 yr of experience in petroleum
which can damage the steam reformer catalyst located down- refining, petrochemicals and upstream projects. He earned Bch
stream. For this purpose, an online analyzer with a high sulfur degrees in chemistry and chemical engineering from the
University of Calcutta, India.
alarm is usually provided at the outlet of the sulfur absorber to
alert the operator. A manual sampling station provided at the
same location is considered a reliable direct verification for the PRANAY VEER SINGH is a Process Engineer with Fluor New
Delhi. He has more than 12 yr of experience in petroleum
high sulfur alarm; however, lab analysis may take some time be- refining, petrochemicals and fertilizer projects. He earned an MS
fore the results are made available. Since a low hydrotreater inlet degree in chemical engineering from the Indian Institute of
temperature causes sulfur slippage due to poor conversion, the Technology in Kharagpur, India.
low-temperature alarm available at the inlet of the hydrotreater
may be considered a credible indirect verification that can be VENKATA SRAVAN KUMAR is a Process Engineer with Fluor
verified instantly (FIG. 3). New Delhi. He has more than 14 yr of experience in petroleum
refining, petrochemicals and fertilizer projects. He earned a Bch
degree in chemical engineering from Jawaharlal Nehru
Suppression of alarms. Provision for alarm suppression Technological University in India.
may be required for some alarms, such as during unit startup
72 APRIL 2022 | HydrocarbonProcessing.com
Feature Report
Health, Safety and
Environmental Considerations
for Process Synthesis
Following this approach to assessing health, safety and environmental risks can steer engineers
to consider more inherently safe process options earlier in process synthesis
D
Thane Brown uring process synthesis in the ing all major process steps and flow streams
Proctor & Gamble (ret.) chemical process industries (CPI), • Process operating conditions
engineers make decisions that • Material specifications for raw materials,
determine the inherent health, catalysts, solvents, processing aids, pack-
safety and environmental (HSE) risk level of aging materials and so on
IN BRIEF a process. This article proposes a simple • Material and energy balances
WHAT IS PROCESS approach for identifying and assessing the • Required materials of construction
SYNTHESIS? major HSE hazards during synthesis. • Process design data, such as reaction ki-
Understanding the risk level during synthe- netics and physical properties
HOW TO THINK ABOUT
sis enables the engineer to consider inher- • Scale-up criteria
HSE
ently safer designs (ISD) while developing the • Major HSE hazards
METHODOLOGY flow sheet. If risk levels are not considered
EXAMPLE
during synthesis, higher risk processes will How to think about HSE
result, because decisions are hard to change HSE is a broad topic dealing with the safety
UNADDRESSED RISKS once the flow sheet has been finalized. Most of plant employees, of the physical plant, of
AND HAZARDS of the resistance to process design changes the community and of the environment. Each
CONCLUDING REMARKS comes from trying to avoid the need to re- of these constituencies is affected in its own
peat expensive research and development way by a production process.
work, as well as avoiding schedule delays. • Plant employees may be affected by
To understand the value of ISD, consider chemical exposure, fire, explosion, noise and
the Bhopal, India incident where, in 1984, injuries
an accidental release of the chemical methyl • The physical plant may be affected by fire,
isocyanate (MIC) occurred at a facility for explosion and overpressure situations
manufacturing the insecticide Sevin. MIC, an • The community may be affected by acci-
intermediate in the production process for dental releases of substances, fires, explo-
Sevin, is a highly toxic chemical. A National sions, noise, pollution, landfills and the dis-
Research Council (Washington, D.C.; www. posal of hazardous chemicals
nationalacademies.org) study stated that • The surrounding environment may be
more than 40 tons of MIC were released, kill- affected by planned emissions and dis-
ing close to 3,800 people and seriously injur- charges, toxic wastes, accidental releases
ing between 100,000 and 200,000 [1]. Had and fugitive emissions
there been an inherently safer process at the In the previous definition of process syn-
Bhopal plant, the accident might have been thesis, the phrase “appropriate level of HSE
prevented, or its severity greatly reduced. risk” requires further explanation. Generally,
risk is thought of as the following:
What is process synthesis?
Process synthesis is the creation of a pro- Risk = (Severity of Incident) × (Likelihood of
cess for manufacturing a product that meets Occurrance)
customer-based quality specifications, has
an appropriate level of HSE risk, and meets or
business and economic requirements [2].
When complete, process synthesis will have Risk = (Human and/or Economic Loss
defined the following: Potential) × (Probability of an Incident)
• A block flow diagram of the process, show-
34 CHEMICAL ENGINEERING WWW.CHEMENGONLINE.COM JANUARY 2022
The definition of acceptable risk sidered along with TABLE 1*. TYPES OF CHEMICAL PLANT INCIDENTS
varies from company to company. other factors.” Type of Probability Fatality Economic
Each organization must define When thinking incident potential loss potential
what is appropriate for it, which is about risk, engi- Fire High Low Intermediate
a difficult task at best. If the ques- neers should also Explosion Intermediate Intermediate High
tion were simply financial, such as consider the infor- Toxic release Low High Low
weighing the cost of risk reduction mation shown in *Adapted from Table 1-6 in Crowl and Louvar, Chemical Process Safety, 3rd ed. [9]
against the monetary loss of an in- Tables 1 and 2, as
cident, it would be fairly straightfor- well as their own TABLE 2. COMPARATIVE FATALITY DATA
ward to answer. The difficulty arises company’s data Fatality cause Deaths per 100,000
people
when one has to consider the loss and practice.
of life or personal injury. What is a life Smokers who smoke ≥15/d ( 2005–2009)a 1,000
or severe injury worth? What is an Methodology Car travel (2019) b 12
acceptable fatality rate? These are The methodology U.S. Manufacturing (2018) c 2.2
hard questions to answer. presented here will Chemical Manufacturing (2018) c 1.2
In a recent article about COVID-19, help to find and d
Being struck by lightning (2006-2019) 0.07
Alex Berezow discussed the value of assess HSE haz-
Source data:
life [3]. Although he wrote the article ards during pro- ª 2014 Surgeon General’s Report, Table 12.4, p. 660
from a geopolitical perspective, his cess synthesis. For b National Safety Council
remarks apply equally to HSE. He hazards that could cd Bureau of Labor Statistics
National Weather Service
states there are three ways to view result in serious or
the value of life: morally/philosophi- catastrophic incidents, the engi- ents. One needs to consider
cally, economically and a blend of neer should consider changing the health, flammability, instability
the two. basic process to make it inherently and special hazards. An exam-
“Many people say that one cannot safer. Because synthesis is the time ple of a material having a special
put a price tag on human life. This when the process is being created, hazard is MIC, which reacts vio-
is true from a moral or philosophi- it is the ideal time to explore options lently with water. This is believed
cal perspective. … In the eyes of an for hazard elimination or mitigation. to be the initiating cause of the
economist, however, we are neither During synthesis, one need not Bhopal incident mentioned pre-
equal nor invaluable. work on routine safety issues, such viously. Usually, the National Fire
“How does one begin to put a as pressure relief. Later on, detailed Protection Association (NFPA;
price tag on a human life? A simple studies, such as HAZOP (hazard Quincy, Mass.; www.nfpa.org)
thought experiment demonstrates and operability analyses), will iden- or the U.S. Hazardous Materi-
how easy it is. Pretend that you’re tify these issues. als Identification System (HMIS)
the mayor of a small town. There’s The steps in the methodology are ratings are sufficient sources
a dangerous intersection that results the following: of information to determine the
in one car crash fatality every year. • Identify the hazards hazard level of a chemical. Both
A company approaches you with a • Estimate the potential for loss systems have five rating levels.
solution: By redesigning and rebuild- • Estimate the probability of having Table 3 explains the NFPA levels.
ing the intersection, it can guarantee an incident HMIS is similar.
no more car crashes. The only prob- • Identify the major risks • Process-related hazards. Some
lem is that the infrastructure project • Consider inherently safer designs operating features and equip-
costs $100 million. Considering that Step 1: Identify process hazards. ment in a process may be haz-
your small town’s budget is far less Begin by looking for toxic release, ex- ardous. The most common are
than that, the city couldn’t afford it plosion and fire hazards, as follows: runaway reactions, high tem-
without a massive tax increase. You • Hazardous materials. For each peratures, high pressures (or
propose that tax increase to your flow stream in the process, list vacuum) and large inventories of
citizens, who reject it overwhelm- the composition, materials and hazardous materials.
ingly. The citizens have spoken: The amounts of each stream. This ❍ Runaway reactions. Runaway
lives of those who will be killed in ac- should include intermediates reactions are a fairly common
cidents at the intersection are not and impurities. Consider feed problem. High heats of reac-
worth $100 million. streams, products, byproducts, tion and large reactor vol-
“… For what it’s worth, various U.S. recycle streams, purge, cata- umes increase the probability
government agencies value a life be- lysts and solvents, as well as of an incident. If a reaction
tween $9 million and $10 million. planned discharges to sewers, is exothermic, assess the
“The key is to remember that we the atmosphere, landfills, recy- chances that it could get out
are talking about economic value clers and waste disposal firms. of control. This usually occurs
rather than moral value. There is al- For each substance, determine when there is a problem,
ways space for a moral consideration whether it is hazardous; and if
such as a cooling system
in geopolitics, but it too must be con- so, the degree of hazard it pres-
or power failure. An assess-
CHEMICAL ENGINEERING WWW.CHEMENGONLINE.COM JANUARY 2022 35
ment of the system requires could cause TABLE 4. HARDWARE RELATED TO INCIDENTS FOR THE REFINERY
knowing the reactor volume, an incident. AND PETROCHEMICAL INDUSTRIES, 1974–2019
the heat capacity of the reac- ❍ Hazardous Hardware % of Incidents
tion mix, the heat of reaction material
Piping, including valves 33
and the reaction rate. If the inventories.
The issue Towers 14
last three pieces of informa-
tion are unknown, the data here is the Reactors 12
can be obtained via reaction possibility Storage tanks 7
calorimetry experiments. of an ac- Unknown 4
❍ High-pressure or high-tem- cidental Instruments 3
perature operations. These release. The
Heat exchangers 3
are innately more hazardous larger the
Pumps 3
than lower-pressure and low- inventory of
hazardous Compressors 2
er-temperature operations.
High pressures increase the materials, Other 19
odds of having an equipment the higher Source data: Marsh, The 100 Largest Losses in the Hydrocarbon Industry 1974–2019,
or piping leak. When a pro- the chance www.marsh.com/us/insights/research/100-largest-losses-in-the-hydrocarbon-industry.html
cess stream is within or near of having a catastrophic are only useful during synthesis.
its flammability range, or near incident. Inventory was a They do not take the place of the
or above its flash or auto-ig- major contributor to the large exacting safety studies done later
nition temperature, leaks may number of deaths in Bho- during detailed design.
result in a fire or explosion. pal. Inventories include both Referring back to Table 1, note
The same is true of leaks in-storage and in-process that toxic releases and explosions
of flammable heat-transfer material. When considering have the greatest potential for fatali-
fluids. A special category of in-process inventory, keep in ties and economic loss. To estimate
high-temperature operations mind that batch reactors gen- each hazard’s potential for loss,
is furnaces. By their nature, erally have higher volumes place each into one of the following
furnaces are risky. If a furnace than continuous reactors, broad loss categories:
standard distillation columns • Catastrophic — Those resulting
is used to heat a process or a
heat transfer fluid that is flam- arranged in sequence contain in deaths or permanent disabilities,
major community damage, or major
mable, tube leaks could result more liquid than a divided-
plant damage
in a fire or explosion. Also, wall column does, and plate
• Major — Those resulting in hos-
high-temperature operation towers hold more liquid than
pitalizations, significant community
weakens the strength of the packed towers do. damage, or significant plant damage
tube materials increasing the Step 2: Estimate loss potential. • Moderate — Those resulting in
probability of leaks. Once the hazards in the process injuries needing medical treatment,
❍ Vacuum operation. While have been identified, engineers minor community damage, or mod-
vacuum operations are usu- should assess the potential for loss erate plant damage
ally safer than high-pressure for each hazard. Because there • Minor — Those resulting in minor
operations, air leaks into are few design details at this point, injuries, no community damage, or
a process stream that will these assessments will be “order- minor plant damage
oxidize or that is combustible of-magnitude” quality. As such, they When assessing the loss poten-
tial of materials, one can use NFPA
TABLE 3. THE NFPA RATING SYSTEM or HMIS ratings to define the sever-
Adapted from Figure 3-8 in Crowl and Louvar, Chemical Process Safety, 4th Ed. [5]
ity of health, flammability or instabil-
ity hazards. If these are not avail-
4 3 2 1 0
able, use the Materials Safety Data
Health rating Can be lethal Can cause Can cause Can cause Not Sheets (MSDS) for each substance
permanent or temporary in- significant hazardous
serious injury capacitation or irritation
or PubChem’s Compound Summary
residual injury database [4]. If a material has an
Flammability Rapidly Ignites easily at Ignites when Must be Will not NFPA or HMIS rating of 4, assign its
rating vaporizes and ambient moderately heated preheated to burn potential for loss as Catastrophic. A
burns at room temperatures ignite 3-rating should be assigned the loss
temperature category of Major, and so on. To il-
Instability May detonate Shock and heat Violent Unstable if Stable lustrate, MIC, the toxic intermediate
rating may detonate chemical change heated
at elevated
in the Bhopal Sevin process, has an
temperatures NFPA health rating of 4. Thus, its loss
Special hazards W: Violent reaction with water
potential would be Catastrophic. Its
OX: Oxidizer SA: Simple asphyxiant release was clearly that.
36 CHEMICAL ENGINEERING WWW.CHEMENGONLINE.COM JANUARY 2022
For process hazards, TABLE 5. RISK RATING MATRIX FOR PROCESS SYNTHESIS
the guidelines are not as Event probability Very likely, Probable, Every Possible, Every Unlikely,
clear cut. The Marsh 100 Loss potential Every 0– 10 years 10– 30 years 30 – 100 years >100 years
Largest Losses Report Catastrophic:
provides perspective. • Deaths or permanent disabilities
Marsh, an insurance- •• Major community damage
Major plant damage
brokerage and risk-man-
Major:
agement firm, regularly • Hospitalizations
publishes global incident • Significant community damage
data. As this report only • Significant plant damage
reports the largest global Moderate:
losses, it represents only • Injuries needing medical treatment
the tip of the loss ice- • Minor community damage
• Moderate plant damage
berg. Property losses
follow a similar pattern Minor:
• Minor injuries
to deaths and injuries. • No community damage
Crowl and Louvar sug- • Minor plant damage
gest that for every 1 to
2 fatalities resulting from Fifty eight of those came from the toxic releases
an incident, there are 10 to 20 seri- petrochemical and petroleum re- • 39 (67%) began with an explosion
ous injuries, 100 to 200 minor inju- finery segments. These resulted in • 19 (33%) began with a fire
ries, and 1,000 to 2,000 near misses losses totaling $23 billion, as well as Table 4 summarizes the hardware
[5]. the following: and equipment associated with the
The March 2020 Marsh report • Losses averaged $500 million/yr 58 incidents from the petrochemical
covers the 46-year period from 1974 • The average cost of an incident and refining sectors.
to 2019. It describes the 100 largest was $397 million Step 3: Estimate the probability
global hydrocarbon industry losses. • Three incidents (5%) resulted in of an incident. As was the case
Unaddressed risks/hazards
If significant hazards/risks exist that are not dealt with,
they should be flagged so they will not be forgotten
in the future. This helps ensure someone will design
safeguards into the process to manage those risks
and mitigate outcomes. For example, one of the senior
chemical engineering design projects at the University
of Cincinnati involved designing a greener process for
making dimethyl carbonate [11]. The process uses a
catalyst (methyl iodide) with an NFPA health rating of
3. The Safety and Hazard Section of PubChem’s Com-
pound Summary for methyl iodide states that storing
amounts greater than or equal to 7,500 lb “presents a
potential for a catastrophic event …” [12]. This is the
type of item one would flag, because storage systems
are not dealt with during process synthesis.
Concluding remarks
The decisions made during synthesis set the HSE
features of a process. Thus, it is imperative HSE be
integrated into the process design. Especially with
chemical processes, it is the only way HSE risk can
be adequately dealt with. The approach in this article
enables the synthesis engineer to identify and man-
age the major HSE hazards and risks in a process. n
Edited by Scott Jenkins
References
1. National Research Council, The Use and Storage of Methyl Isocyanate (MIC) at Bayer Crop-
Science, Washington DC, 2012, p. 32.
2. Brown, T.R., Cost Engineering: Integrating Technology and Economics, Chem. Eng., December
1, 2017, pp. 35–36.
3. Berezow, Alex, Four Coronavirus Lessons That We Will (or Won’t) Learn, Geopolitical Futures,
May 1, 2020.
4. Cameo Chemicals MSDS, available at: https://cameochemicals.noaa.gov/chemical/1112.
5. Crowl, D.A. and Louvar, J.F., “Chemical Process Safety,” 4th Edition, Prentice Hall, 2019.
6. Kletz, T.A, and Amyotte, P., “Process Plants: A Handbook for Inherently Safer Design,” 2nd Edition,
CRC Press, 2010.
7. Crowl, D.A. and Louvar, J.F., “Chemical Process Safety,” 2nd Edition, Prentice Hall, 2002, p. 26.
8. Cameo Chemicals MSDS, https://cameochemicals.noaa.gov/chemical/4228.
9. Crowl, D.A. and Louvar, J.F., “Chemical Process Safety,” 3rd Edition, Prentice Hall, 2011.
10. National Research Council, The Use and Storage of Methyl Isocyanate (MIC) at Bayer Crop-
Science, Washington, D.C., 2012, p. 114.
11. An unpublished report by: Ballachino, K., Barr, C., Brown, N., Gunther, A., and Vennefron, Evalua-
tion of the Production of Dimethyl Carbonate (DMC) through a Catalytic Reaction, March 2020.
12. PubChem Compound Summary, available at: https://pubchem.ncbi.nlm.nih.gov/
compound/6328#section=NFPA-Hazard-Classification.
Author
Thane Brown (Email: trbnjb@earthlink.net) worked for more
than 36 years for Procter & Gamble in a variety of engineering
and manufacturing roles, primarily in the food-and-beverage
business and in health, safety and environmental engineering.
In his last position there, Brown was director of North Ameri-
can engineering. After retiring, he taught engineering eco-
nomics at the University of Cincinnati, and plant design at the
University of Dayton. Brown is presently a member of the
Chemical Engineering Advisory Committees at the University
of Dayton, at Miami University (Oxford, Ohio), at the University
of Louisville and at the University of Cincinnati. He also works as a SCORE coun-
selor, providing free assistance to small businesses in the Cincinnati area. Brown
authored the book “Engineering Economics and Economic Design for Process En-
gineers” [1], as well as a number of articles on engineering economics, batch pres-
sure filtration and heat transfer. He is a registered professional engineer in Ohio
(inactive), and holds a B.S.Ch.E. from Oregon State University.
Pressure-relief devices (PRDs) play a critical role in the hy- installing a dedicated spare PRD. The following will review
drocarbon processing industry. They act as the last line of de- the three options in further detail.
fense in protecting plant equipment from overpressure and are
mandated by the American Society of Mechanical Engineers Option 1. Providing an installed spare PRD is generally the
(ASME). This article provides some key factors that process preferred way to provide adequate overpressure protection
engineers and plant operators must consider to determine if an to the process equipment. While this option involves initial
installed spare PRD is necessary. capital expenditure for the PRD and associated piping, it also
Like many other plant components, relief devices require provides the safest way to keep the protected equipment in
routine maintenance to ensure safe and reliable plant operation. continuous operation for the duration of the maintenance.
While most of the PRDs in hydrocarbon processing plants can Plant operators are required to follow stringent administrative
be taken out for maintenance during plant turnarounds, cer- procedures for isolating the PRD requiring maintenance.
tain PRDs may require more frequent maintenance while the In the absence of an installed spare PRD, other creative
plant is in operation (onstream). The term “onstream” refers to ways are available to achieve the same purpose. This includes
the overall plant operation. Reasons for more frequent main- utilizing PRDs on nearby equipment to provide the necessary
tenance could include safety requirements or possibly because protection by means of utilizing an existing pipe routing for
the PRD is installed in a fluid service where fouling, corrosion a temporary relief path. However, process engineers should
or plugging could potentially impact PRD operation. perform a thorough analysis to ensure that such a temporary
Onstream maintenance of a specific PRD in the plant can and alternate relief path is adequate in terms of hydraulic re-
be achieved by one of the following options: quirements (inlet pipe pressure loss), PRD flow area and fluid
1. Providing an alternate and adequate relief service compatibility.
protection to the protected equipment
(e.g., a spare PRD, or an alternate and adequate Option 2. This option is best suited for equipment that can be
flow path to another PRD) taken out of service while onstream plant production is main-
2. Isolating, draining and depressurizing the protected tained. A spare PRD may not be required if the entire pro-
equipment from all possible overpressure sources tected system can be isolated during normal plant operation.
(taking the equipment out of service) Equipment operating in intermittent service also may not re-
3. Eliminating as many overpressure sources as feasible, quire a spare PRD. For example, consider a hydrocarbon sys-
and implementing administrative controls tem containing multiple catalyst bed vessels in parallel, where
for monitoring the protected equipment at least one vessel is always isolated for catalyst regeneration
for the duration of the PRD maintenance. and is in standby mode for a prolonged duration. A spare PRD
Process engineers are required to review these options may not be provided for protecting such vessels, as mainte-
during the front-end design development step, with input nance can be performed when the vessel is in standby mode.
from the plant operations team, to make an appropriate deci- In such cases, the duration of the maintenance should be given
sion. PRDs requiring onstream maintenance are, in general, careful consideration, as the vessel cannot be returned to ser-
provided with isolation valves on inlet and outlet (if appli- vice without code-compliant relief protection. Plant operators
cable) pipelines. ASME code requires administrative controls generally rely on administrative procedures to open and close
to be in place for proper operation of the isolation valves in several valves for placing equipment back in service. Failure
the relief path so the equipment’s overpressure protection to properly follow these administrative procedures can com-
is not compromised. These requirements include provid- promise the overpressure protection mandated by the ASME
ing locks or car seals in addition to administrative controls code. One such safety incident was the ruptured heat exchang-
to prevent accidental closure (for more information, refer to er in June 2008 that killed one worker and injured six others at
ASME BPVC Section XIII Non-Mandatory Appendix B). the Goodyear Tire and Rubber Co. in Houston, Texas.1 One of
Process engineers and plant operators must be familiar with the root causes of this accident was failure to properly follow
the ASME code requirements, and Appendix B provides valu- the procedure of opening the PRD inlet piping isolation valve
able guidance and requirements for determining a need for before placing the heat exchanger into service.
Gas Processing & LNG | MAY/JUNE 2022 19
INFRASTRUCTURE & EQUIPMENT
PRDs requiring onstream pressure due to an external pool fire is a well-known scenario
that is applicable for process equipment at grade level. Ad-
maintenance are, in general, ditional overpressure scenarios include blocked outlets and
auto-control failures, among others (see API 521 for more
provided with isolation valves information). The process engineer should review all appli-
on inlet and outlet (if applicable) cable overpressure scenarios when determining the need for
a spare PRD.
pipelines. ASME code requires It is a generally accepted industry practice not to provide
administrative controls to be in spare PRDs in the following applications, as the PRD main-
tenance interval typically aligns with the protected system
place for proper operation of the maintenance interval:
isolation valves in the relief path • PRDs installed exclusively for protecting equipment from
external fire (fire-only PRD)
so the equipment’s overpressure • PRDs installed in cooling water service exclusively
for protecting the equipment from thermal expansion
protection is not compromised. (cooling water thermal).
Option 3. This is the least preferred option, as it involves Multiple PRDs. Multiple PRDs are often provided when a
operating the process equipment without overpressure pro- single PRD is inadequate to handle the required relief flowrate.
tection under administrative controls. One of the first things The ASME code allows staggering the PRD set pressures in
that the plant operator is required to do in this option is to this case. For multiple PRDs:
identify all potential overpressure sources beforehand and at- • A single spare PRD may be installed with the basis
tempt to eliminate or minimize the likelihood of overpressure that administrative controls are in place to perform
from such sources for the duration of the PRD maintenance. maintenance on one PRD at a time. When a single spare
In this option, assuming that isolation valves are in place, the PRD is installed, performing maintenance on multiple
PRD must first be isolated by closing the inlet and outlet iso- PRDs would result in inadequate relief protection,
lation valves before the maintenance can begin. Closure of the which is a possible code violation.
isolation valves would lead to blocking the relief path and to • The spare PRD should have an orifice flow area
operating the protected equipment with a risk of overpres- identical to the operating PRD with the largest area.
sure. Plant operators are required to stay in compliance with • When the spare PRD is put into operation, at least
the ASME code for proper implementation of administrative one PRD should have a set pressure at 100% of the
controls. ASME BPVC-XIII Appendix B-7(d) states: maximum allowable working pressure.
“Procedures are in place to provide pressure relief Takeaway. The ASME code does not mandate installing a
protection during the time when the system is spare PRD. However, in the absence of an alternate and ad-
isolated from its pressure relief path. These procedures equate relief path, the ASME code mandates the implemen-
should ensure that, when the system is isolated from tation of proper administrative controls for safe isolation and
its pressure relief path, an authorized person should subsequent monitoring of the protected system for the du-
continuously monitor the pressure conditions of the ration of PRD maintenance. Administrative controls play a
vessel and should be capable of responding promptly critical role in the safe operation of any plant, and many plant
with documented, pre‐defined actions, either stopping operators prefer to install a spare PRD to provide an adequate
the source of overpressure or opening alternative and equivalent overpressure protection. Process engineers
means of pressure relief. This authorized person and plant operators must be conversant with the applicable
should be dedicated to this task and should have regulatory requirements and must review all PRDs on a case-
no other duties when performing this task.” by-case basis to determine whether an installed spare PRD is,
or is not, necessary.
Plant operators should consider several factors to safely
rely on administrative controls for monitoring unprotected LITERATURE CITED
equipment. One such factor is the duration of maintenance. 1
U.S. Chemical Safety and Hazard Investigation Board, “Goodyear heat
Can the relief device be returned to service in a reasonable exchanger rupture,” January 2011 (report released), online: https://www.csb.
gov/goodyear-heat-exchanger-rupture/
amount of time? Another factor is training. What kind of 2
ASME Boiler and Pressure Vessel Code, Section XIII-2021, “Rules for over-
training would be required for authorized persons to respond pressure protection.”
promptly in an event of pressure excursion in the process ser-
vice? If possible, process engineers and plant operators should PRANAY K. NAMILAKONDA is a Process Engineer with Samsung Engineering
steer away from this option, as this involves several factors America, a global EPC firm based in Houston, Texas. He is a licensed Professional
Engineer and has more than 15 yr of experience in front-end engineering
that cannot be fully accounted for during the plant design. execution of various hydrocarbon projects. He also leads the process engineering
group, with an emphasis on engineering automation. Mr. Namilakonda earned
Multiple overpressure scenarios. There can be more than an MS degree in chemical engineering from Oklahoma State University, and a
one overpressure scenario that is applicable for a PRD. Over- BTech degree in chemical engineering from Osmania University, India.
There are more than 100 flares spread sive engineering standard for real-time situation has changed. In the current in-
across many operating facilities in the measuring, monitoring, reporting and dustry environment, the primary drivers
upstream and downstream oil and gas minimizing flaring was developed. Part favoring FGRS projects include:
processing plants of Saudi Aramco. Flare of this minimization plan was to study • Stricter global environmental
systems are designed to provide the safe the leakage rate to the flare system and regulations governing the emissions
disposal of hydrocarbons that are either to determine purge optimization. These of GHGs, such as CO2
automatically vented or manually vented two analyses play major roles in reduc- • Environmental impacts and health
from process units. Flare systems gather ing facility emissions. Furthermore, the effects of harmful emissions,
vented gases and combust them to pre- company’s Process and Control Systems such as nitric oxide (NOx ), sulfur
vent release directly to the atmosphere. department issued design guidelines for oxide (SOx ) and volatile organic
Since Saudi Arabia started produc- FGRSs to give clear direction for select- compounds (VOCs)
ing oil, associated gas has been flared. In ing and applying new FGRS projects in • Improved economic returns in
the 1970s, the Kingdom recognized the all Saudi Aramco operating facilities. This recovered flared gas to the value
value of the associated gas produced with guideline is in line with the Saudi Aramco chain, thus saving on plant fuel gas
crude oil. Major investments in building corporate decarbonization strategy to re- and steam consumption
a sizable master gas system resulted in duce greenhouse gas (GHG) emissions. • World Bank carbon credits for
capturing and utilizing all the associated The company has had several tech- uneconomic FGRS projects,
gas instead of burning it in gas flares. As nologies in operation for a few years. specifically for the elimination of
a result, the Kingdom’s annual flaring has Therefore, Saudi Aramco has updated CO2 emissions, which can be traded
been considerably reduced to facilities’ its best practices with lessons learned for monetary gains—thus helping
routine and emergency flaring only. The from the startup and commissioning of to improve returns on investment
environmental regulations from Saudi compressor and ejector technologies at (ROIs) for projects
Arabia’s Presidency of Meteorology and its facilities. This compilation of informa- • Increased raw gas production
Environment require controls for smoke- tion provides additional insights that will costs, which makes FGRSs more
less flaring only from industrial activities, enhance designs and proactively address attractive, since these systems
and there are no penalties for carbon di- common issues that can arise during the recover flared gas and recycle it
oxide (CO2 ) emissions. startup and operation of FGRSs at Saudi back to the process
These standards apply just to routine Aramco facilities. • Rising sales gas costs, making FGRS
emissions, and not to emergency, startup recovery projects more viable
or shutdown events. Most Saudi Aramco FGRSs. Corporate management has rec- • Shortage of natural gas
facilities meet the environmental standard ognized the need to approve a flaring in the country
for smokeless flaring. The corporate road- roadmap, which calls for considering an • FGRSs improve the reliability
map on flaring was initiated as a response FGRS if any facility is flaring more than of main flare tips (important for
to the escalating cost of the new project 1 MMsft3d of gas after implementing all larger-diameter flares that are prone
proposals to make flares smokeless for flaring reduction measures. An FGRS will to damage from operation at low
routine operations in all of the company’s eliminate flaring as required for plant safe- daily flaring rates), enabling the
facilities. The key element of this roadmap ty, provide routine process reliefs and re- main flare to stay in standby mode,
is to minimize flaring by implementing turn gases back to the process to prevent which improves its reliability and
site-specific flaring minimization plans any leakages. Although FGRS technology life, and minimizes the recurring
(FMPs) and installing a flare gas recovery is proven in industry, it was not adopted cost of flare tip replacement.
system (FGRS) wherever feasible. by the authors’ organization in the past Additionally, one of Saudi Aramco’s
An FMP was initiated to reduce flaring because, during that time, there were no key values is citizenship, where the orga-
from all Saudi Aramco facilities over a de- compliance requirements for CO2 emis- nization has a positive influence in com-
fined period by minimizing the frequency sions and there was a very low price to pay munities and requires a demonstration
and magnitude of flaring. A comprehen- for sales gas. In recent years, however, the of social responsibility. An FRGS pro-
Gas Processing & LNG | MARCH/APRIL 2022 13
SPECIAL FOCUS: GREEN TECHNOLOGIES
vides an excellent platform to reflect this tween the knockout drum and the staging to move toward it and mix with motive
company image. device and pulls flare gas from the header fluid in the mixing chamber. The mixed
whenever flow is detected. Basically, the fluid will enter the diverging portion of
FGRS components. A flare gas recovery staging devices enable safe operation of the ejector, where its velocity energy is
installation at an existing plant will con- the entire system through sealing the el- converted into pressure energy (FIG. 2).
sist of four main components. Brief de- evated flares and providing backpressure The authors’ company has patented
scriptions of these component are below: in the flare header, allowing the flare gases this technology to be utilized in a flare
1. Compression technology is to be routed to the FGRS. system to recover the wasted gas for
designed to recover flare gases further treatment or to generate energy.
for reuse in the existing Types of compression equipment. The team conducted several feasibility
processing facilities. The choice of compression equipment studies that approved the applicability of
2. Staging devices safely divert will greatly influence the configuration this technology to recover flare gas either
routine flared gases to the of an FGRS. A detailed survey of existing by using a gas/gas or liquid/gas ejector.
FGRS, but not the emergency technologies revealed that the compres- This technology was applied in oil-pro-
or abnormal relief loads. FIG. 1 sor types widely used for FGRS applica- ducing facilities and refineries, and it has
illustrates the integration of an tions include: successfully been used in gas-operation
FGRS into the flare system. • Liquid-ring compressors with a facilities by using amine solution as a
3. A nitrogen-generation package is variety of service fluids (such as motive liquid. When gas at sufficient
included to supplement existing water or diesel) pressures is available onsite, gas-motive
nitrogen-generation capacity. • Multi-staged screw compressors. ejectors could be an economical com-
Nitrogen will be used as a purge gas The major advantages of these compres- pression solution. Eductors or liquid-
downstream of the staging device. sor types include: motive ejectors can also be considered
4. A control system within the • They can handle a wide range and may use a closed-loop liquid circula-
package interfaces with the plant’s of gases with varying molecular tion to provide the needed liquid-motive
distributed control system. weights, with no effect on their pressure. Eductors can also be used for
As shown in FIG. 1, the flare gas recov- performance. gas sweetening purposes.
ery unit ties into the flare gas header be- • They can handle flow from zero Recovering flare gas was not stopped
to full capacity with a robust by these compression types. The feasibil-
Flare gas Recovered gas to process recycling system. ity of flare gas recovery is considered the
• They can tolerate liquid in the feed process philosophy for each facility. For
Knockout drum
FGRS 6
vs. any other type of compressors. example, each facility can recover flare gas
MMscfd by using an atmospheric compressor. As
Ejectors. An ejector is a well-known a result, hydraulic analysis was required
technology for pressurizing gas by using to install a jump-over line from the flare
a high motive source. The operating prin- header to the compressor suction pipe.
N2 purge
ciple of the ejector is the pressure energy
in the motive fluid, which is converted to Challenges. Since Saudi Aramco started
Staging
device velocity energy by an adiabatic expansion recovering flare gas, there have been major
Existing flares in the converging/diverging nozzle. Due challenges. However, without these experi-
HP/ACID or
INLET to the pressure drop of the motive fluid, ences, the authors would not be able to list
it will create a low-pressure zone before all the lessons learned to overcome them.
FIG. 1. The integration of an FGRS into the the mixing chamber. Due to this low- One of the major challenges experi-
flare system. pressure zone, the suction fluid will start enced in FGRSs is the oxygen ingress
that resulted in the formation of solid
Nozzle Mixing chamber particulates. As a result, these solid par-
Diffuser Mixing fluid
ticulates blocked the suction strainers of
outlet the compressors. A sample was collected
and sent to the research and development
center for detailed analysis. It was discov-
ered that elemental sulfur composition
exceeded 99%.
Normally, elemental sulfur can be
found in natural gas processing plants
for two reasons: as part of the natural gas
Motive fluid mixture coming from the source reser-
voir, or because of sulfur compounds re-
Suction fluid acting with oxygen, resulting in sulfur in
its elemental form.
FIG. 2. An ejector schematic.
In natural gas, elemental sulfur is usu-
14MARCH/APRIL 2022 | GasProcessingNews.com
SPECIAL FOCUS: GREEN TECHNOLOGIES
ally found in the vapor phase. Due to the headers, which would affect the limit on
increased carrying capacity that hydro- PZVs allowable backpressures. Having
gen sulfide (H2S) provides to natural gas, the FGRS could also develop new criti-
its presence in the transported gas mix- cal overpressure scenarios that would
ture helps with transporting elemental need to be addressed. Further, in many
sulfur. Compared to methane, H2S can applications, processes are equipped
carry more sulfur by three or four more with continuous vent-to-flare systems,
orders of magnitude. Consequently, the either in the process equipment or in
probability of sulfur deposition in oil and the seal gas of the compression systems.
gas processing facilities is increased. Even small changes in operating pres-
The desublimation of elemental sulfur sures of the flare headers could lead to
at certain pressure and temperature con- process interruptions from these ser-
ditions is a major cause for deposition. vices. Overall, any proposed changes in
Usually, the low concentration of elemen- flare and relief system operations should
tal sulfur—within the parts-per-billion be first assessed with appropriate studies
range—makes it more challenging to de- on these systems. GP
tect. In some cases, elemental sulfur de-
sublimates intermittently at certain loca- ABDULAZIZ H. AL-TIJANI is an
tions within the plant, causing difficulties
in tracking the root causes of the problem.
Engineering Specialist at Saudi
Aramco’s Process and Control
INSIDE
In addition to elemental sulfur solu-
Systems Department in Dhahran,
Saudi Arabia. He supports company INTELLIGENCE
bility, the oxidation of sulfur compounds
could also be a major cause for elemental
operations and project design,
mainly in flare and relief systems for the Downstream
sulfur deposition. Testing of the demin-
and in flare gas recovery applications. Mr. Al-Tijani
also supports Saudi Aramco and JV oil and gas Industry
eralized water (in a liquid-ring compres- operational facilities, pipelines and process
sor) indicates that the dissolved oxygen simulations, as well as various phases of projects. He
is within the acceptable parts-per-million earned a BS degree in chemical engineering from
King Fahd University of Petroleum and Minerals
SUBSCRIBE
range. Normally, oxidation of sulfur com-
pounds like H2S leads to the production
(KFUPM), and an MS degree in oil and gas surface
facilities from KFUPM (in partnership with IFP).
TODAY
HydrocarbonProcessing.com
of sulfur in the elemental form at certain /Subscribe
MAHDI ALDAJANI is a Flare and
pressure and temperature conditions. Relief Systems Engineer at Saudi
However, the source of oxygen is not Aramco. He has 10 yr of experience
limited to that in the demineralized wa- with Saudi Aramco, working in
several Saudi Aramco facilities in
ter, as it could be air entering the system support of operations and on
through leaks, or it could involve the detailed design and construction
availability of oxygen within the gas mix- activities on several projects. Mr. Aldajani earned a BS
degree in chemical engineering from KFUPM.
ture transported to the FGRS. Operating
the purge gas below the minimum safety ABDULLMAJEED AL-SANAD is a
requirements can be a major contributor Process Engineer at Saudi Aramco’s
of exposing oxygen in the system. Process and Control Systems
Department, within the Flare and
Also, part of enhancing FGRS reliabil- Relief Systems Group. He has 6 yr
ity is to segregate flare headers with pow- of experience, which includes
HPI
er operated emergency isolation valves company operations and project T
MARKE
DATA
support. Mr. Al-Sanad has also participated in a flaring
(ZVs) should any upset occur in the fa-
cility. The FGRS is designed to recover
minimization program that included several aspects
2022
such as purge gas optimization studies and FGRS
the normal continued flaring; during an evaluations. He earned a BS degree in chemical
engineering from KFUPM.
upset, the FGRS will be interrupted, re-
sulting in a trip. Therefore, as part of reli- MOHAMMED AL-MAHMOOD
ability enhancement, the team proposed is a Process Engineer at Saudi
segregating feed ZV to the FGRS, along Aramco’s Process and Control
Systems Department, within the
with sending a signal to close it in case Energy Transition Engineering
the pressure in one of the flare headers Group. He has 6 yr of experience
increases near to the tipping point. with Saudi Aramco, which includes Hydrocar
bonP roce
ssing .com
in FIG. 2. Considering that the flare stack is the last pollution- flare gas recovery and compression equipment on the market. It
controlling equipment in the refinery, the water-sealing height has been used for more than 10 yr without maintenance. The
of the flare gas system seal drum needed to be modified. equipment also has the advantages of high stability, high durabil-
The engineering techniques adopted and the optimization ity, simple construction and lower maintenance costs. It can also
achieved with the project are discussed in the following sections. handle aerosol-containing gases without affecting performance,
shortens the time from start to full load and has no lubricant
Ejector as compressor. Advanced and highly durable flare gas contamination problems.
recovery and compression equipment (high-performance ejec- Unlike other compressors, high-performance ejectors have
tor) was used for the FGRS. The concept is to use high-pressure the following characteristics:
water to drive the flare gas into the recovery system and process it. • Not sensitive to changes in the suction gas load
In the past, most flare gas recovery systems used liquid ring • Not sensitive to changes in the molecular weight
compressors. These compressors have disadvantages, such as of the incoming gas
complicated maintenance procedures and high maintenance • Works with a closed suction gas valve, with a load ratio
costs, large equipment and relatively long delivery times. For of 0%–100%
these reasons, a high-performance ejector was selected as the • Controls the upstream side pressure with a suction
flare gas recovery compression equipment instead of the con- pressure control valve
ventional method using complicated, large compressors (FIG. 3). • Easy to start and stop
Rapid injection of high-pressure water is used in this equip- • Only moving parts consist of the shaft and the impeller
ment to drive the flare gas through the ejector, after which it is of the centrifugal pump
mixed with water and then enters the FGRS. The high-perfor- • Only parts that require maintenance are the bearings
mance ejector flare gas compression system is the most advanced and seals of the centrifugal pump
• Zero-maintenance solution
Hydrocarbon flare header • As an absorption tower, any particle in the feed gas
can be cleaned by a motive fluid
KOD • Ability to handle feed gases containing solids, particles
Sour flare header FI or mists/liquids without compromising performance
• At low molecular weight, there is no loss of incoming
KOD Ground flare Ground gas capacity, unlike liquid ring compressors
seal drum flare • At high molecular weights, there is no cavitation
Hydrocarbon
flare problem, unlike liquid ring compressors that can cause
Waste gas
heavy loads and vibrations on the shaft and coupler
Ejector • Faster startup time to full load, unlike liquid ring
Three-phase
Fuel gas compressors
separator • Faster gas supply than all other compressors
Lean amine • No lubrication problems, unlike screw compressors
Cooler Rich amine • No moving parts inside the compression chamber
• No metal-to-metal contact.
Scrubber
Waste oil
Design of three-phase separation tank. The three-phase
separator tank functions as a separator of water, oil and gas, with
FIG. 2. Process flow diagram for the FGRS in the refinery. an internal diverter to disperse the gas-liquid and minimize the
impact on the gas-liquid separation tank. The calming baffle is
set to reduce level fluctuations. The double baffle is used for liq-
uid and gas three-phase separation, as shown in FIG. 4.
Waste oil
FIG. 3. High-performance ejector for flare gas compression. FIG. 4. Process sketch for high-performance three-phase separation tank.
A gas demister is installed at the outlet to reduce the drop- water circulation loop.
lets brought out, and another tank is built with oil-water two- Sour water self-purification circulation has the following
phase liquid-level control functions. Oil-water separation uses advantages:
an oil-water-gas three-phase gas separation tank and an oil-water 1. Decreases the amount of blowdown/makeup
separation tank to accomplish a two-step separation procedure; water required. TABLE 1 shows that sour water
it separates oil and water effectively and reduces waste oil and self-purification circulation can remove approximately
wastewater at the outlet. 80%–90% of hydrocarbons, which significantly
enhances oil-water separation efficiency, improves
Self-purification sour water loop. A self-purification loop for the quality of process water and reduces the amount
sour water is incorporated to improve the circulating water qual- of blowdown/makeup water.
ity, thereby reducing wastewater discharge, as shown in FIG. 5. 2. Decreases H2S concentration, which reduces
The benefits of establishing a sour water self-purification loop corrosiveness and extends equipment service life
include reductions in emissions, supplemented water consump- 3. Increases the amount of recovered fuel gas
tion, H2S concentration and corrosion, as well as extending the 4. Reduces the impact of emulsion.
equipment life. It also increases fuel gas recovery and reduces Although the cost savings from water reduction (18 m3/hr)
the impact of emulsification caused by the recovery system. and fuel gas recovery are not significant, the benefits of decreas-
To maintain the quality of process water in a three-phase ing wastewater are great.
separator for the FGRS, the typical design includes discharging
part of the process water and adding the equivalent amount of Optimization of amine liquid dosage design. Proprietary
supplemented water, which maintains the overall quality of the software is used to simulate and control the temperature of the
process water. However, using sour water self-purification circu- exhaust gas into the amine washing tower, so that the volume
lation brings many advantages, such as a reduction in the amount concentration of H2S in the exhaust gas is less than 80 ppm. Ad-
of sour water blowdown/supplemented water, less corrosion, an ditionally, about 20% of the amount of amine liquid is saved, as
extension of equipment service life, an increase in fuel gas recov- shown in FIG. 7.
ery and a reduction in the impact of emulsion phenomenon. Amine liquid absorption tower design. The refinery re-
In the flare gas recovery system, the refinery’s requirement quires the installation of two sets of FGRSs. According to this
of recovered fuel gas pressure is a minimum of 4.5 kg/cm2g, requirement, the processing capacity of each set of recovery
and the separator’s operating pressure must be at least 6 kg/
cm2g in the front process. These operating conditions would
increase the water solubility of the hydrocarbon and reduce the
separation efficiency.
To maintain the quality of the process water, the typical de-
sign is to blow down part of the process water (approximately
1%–2%) and add the equivalent makeup water. Sour water self-
purification circulation (FIG. 6) would route a portion of the
sour water into a low-pressure flash drum. The water solubil-
ity of hydrocarbon decreases immediately due to a reduction in
pressure, and a portion of the sour water flashes into vapor. The
flash gas is then sent to the flare header, and the residual liquid
is sent to the separator by a circulation pump, creating a sour
FIG. 5. Process sketch for circulation of water self-purification loop.
TABLE 1. Sour water self-purification circulation benefits
Mass flow Stream 1, kg/hr Stream 2, kg/hr Removal % Flash gas
H2 0.00612 0.00075 87.8
Sour water flash drum
C1 0.19248 0.0313 83.74 OPI 0.2 kg/cm2g
C2 0.46093 0.08297 82 Flare gas header Flare gas
Three-phase separator
OPI 6 kg/cm2g
C3 0.4071 0.05901 85.51
iC4 0.10173 0.00974 90.42
Oil level
nC4 0.1655 0.02275 86.26 Sour water level
iC5 0.06229 0.00471 92.44 Makeup water Oil
nC5 0.05995 0.00547 90.87 1 2
Sour water
C6 0.05017 0.00275 94.51
Sour water
CO 0.04737 0.00588 87.58 circulation pump
CO2 1.3133 1.04683 20.29
H2S 1.8489 1.71026 7.5
Water 8,827.29 8,827.21 0 FIG. 6. Sour water self-purification circulation flow scheme.
equipment is 9,600 Nm3/hr. The treated exhaust gas must have Design considerations. The following items are considered as
an H2S volume concentration below 80 ppm. parameters for the design of the amine liquid absorption tower:
Each FGRS comprises two sets of amine liquid absorption • Amine liquid circulation flowrate
towers, and the H2S in the exhaust gas is removed by a 27 wt% • Lean amine inlet temperature
solution of diisopropanolamine (DIPA). • Absorption tower retention time
Thermodynamic mode and simulation tools. The soft- • Amine liquid circulation flow.
warea used for simulating the amine liquid absorption tower has Using the software to simulate amine absorption, the lean
a rigorous electrolyte mode and an accurate liquid phase-activ- and rich approaches can be adopted to determine the closeness
ity coefficient mode, which is suitable for amine liquid absorp- of the operating state and the equilibrium state of the system.
tion systems. Other commercial process simulation software Conceptually, the lean approach indicates the ratio of equilib-
programs, which use the amine thermodynamic model, consid- rium H2S content to operation H2S content at the absorber
er the electrolytic properties of the amine absorption system; overhead, and the rich approach indicates the ratio of operation
however, the basis is regression, not electrolyte calculation. amine loading to equilibrium amine loading at the bottom of
The amine liquid-absorption system contains a chemical re- the absorption tower for the rich amine solution.
action of H2S and CO2 with amine. The reaction rate of H2S In an example of the lean approach, FIG. 8 shows the ratio
with amines is very fast and can be considered as equilibrium, of H2S content of the sour gas when the amine/sour gas feed
while CO2 is not. If CO2 is present in the system, it will signifi- reaches equilibrium (point B, Ye) to the H2S content of the
cantly affect the absorption of H2S. overhead gas under operation (Point A, Y1 ).
The software has a reaction kinetics model for CO2 to simu- In an example of the rich approach, FIG. 9 shows the ratio of
late selective absorption of H2S by amines in the presence of H2S content of the bottom rich amine solution (Point A, X2 ) to
CO2 and H2S. It calculates the lean and rich approaches for the the H2S content of the rich amine/acid gas feed at equilibrium
amine absorption tower, which engineers use to determine the (Point B, Xe ).
efficiency and space of the absorption tower. These approaches FIGS. 8 and 9 show that the slope of the operating curve is the
are the two most important indicators for the absorption tower. ratio of the circulating amount of amine liquid to the flowrate of
the acid gas. If the ratio of the circulation flowrate of amine liquid
to acid gas flowrate (L/V) decreases, then the appeal of the rich
approach increases. The value of the rich approach helps quickly
determine the appropriate amine circulation flow. As a rule of
thumb, the rich approach should be between 70% and 80%.
A rich approach above 80% indicates low volume circula-
tion; for a typical 15–20-tray absorption tower, the amine liquid
generally does not absorb a higher proportion of H2S. Under
abnormal conditions, such as an increase in the concentration
of H2S in the imported acid gas or a sudden increase in the
amount of imported acid gas, the concentration of H2S in the
outlet gas may be out of specification.
If the rich approach is less than 70%, it suggests excess circula-
tion; at this stage, even if the quantity of amine liquid is increased,
the concentration of H2S at the overhead gas outlet is low.
FIG. 7. Process sketch of amine scrubber. Dynamic simulation of flare gas discharge. A dynamic
simulation softwareb calculates the levels of exhaust gas emis-
Ye
Point B
Liquid phase H2S composition Liquid phase H2S composition
X1 X2 X1 X2 Xe
Lean approach = Ye/Y1 Rich approach = X2 / Xe
sions (FIG. 10) and helps determine the circulation pump start/ lines, pipe racks, concrete and others. A three-in-one design
stop settings and the water seal isolation tank’s water sealing is used to integrate two liquid separation tanks and one amine
height. The goal is to obtain the best control parameters and scrubber into one vessel to save space.
reach the target of zero emissions. Equipment backup system. The two train systems are de-
Sour flare gas backflow prevention. Anti-backflow facili- signed for both Sections C and F. When the first train equip-
ties were added to prevent sour flare gas from flowing back into ment is under inspection or maintenance, the other train can
the hydrocarbon flare header facility. continue the flare gas recovery operation.
An exhaust gas recovery backflow prevention facility prevents Multistage automatic start/stop. The process system safety
sour flare gas from flowing back into the hydrocarbon flare head- control design included multistage control start/stop for the flare
er and discharging from the ground flare, causing air pollution. gas recovery unit to save power and improve efficiency. Comput-
This design also allows the exhaust gas recovery system to pri- er simulation software was used to calculate the best setpoint to
oritize the recovery of acid waste gas to clean the air near the re- achieve the highest system efficiency, safety and reliability.
finery, thereby improving the value of investment in this system. Finally, the dual-feeder power supply system is designed to
Low consumption for utility system. The temperature dif- improve system stability and reliability.
ference between the cooling water inlet and outlet is 13°C, and
the cooling water consumption is the most economical. As the Takeaway. After the completion of the project, the improve-
amount of exhaust gas recovery is ever-changing, the amount of ment in overall environmental quality in the city is quantifiable.
water supplement for the oil-water-gas three-phase separation Calculations show that each train in Sections C and F can re-
tank can be proportionally adjusted according to the quantity cover up to 9,600 m3/hr of flare gas. The flare gas recovered in
of exhaust gas recovery needed to save water. one day is equivalent to the amount of CO2 absorbed by Daan
Since the energy consumption of the ejector circulation Forest Park in Taiwan in an entire year.
water pumps is high, energy-saving designs have been incorpo- The project was highly praised by the jury members in the
rated. Four circulation water pumps—two BB3 high-efficiency Golden Quality Award of the National Public Construction
(80.2%) pumps and two BB2 pumps (efficiency 69.5%)—were Commission of Taiwan for technology innovation and opti-
added in two trains in Section C of the refinery. mized design. This recycling technology should be promoted
The two BB3 high-efficiency pumps are prioritized for ac- to increase environmental protection.
tivation during operation, and when the demand is high, the
NOTES
other two BB2 pumps are also activated to improve energy ef- a
ProMax
ficiency and reduce operating costs. b
DySime
Optimization of plant plot arrangement. Due to the limit-
ed space in the existing plant, in addition to optimizing process SHIN-GEE LU is Assistant Chief Engineer for CTCI Corp. in Taipei, Taiwan, specializing
in process and system design. He has 31 yr of experience in petroleum refining,
technology, the project optimized plant layout by symmetrical petrochemical production and utilities/offsites, as well as basic and detailed design.
arrangement to reduce the materials required, including pipe- He holds a BS degree in chemical engineering from Chung Yuan University in Taiwan.
FIG. 10. Dynamic simulation for exhaust gas emissions from flare main header.
brings us to the last key concept: When the as in the example case, it will allow use of the minimum design conditions
ASME data is used for a specific valve, it is a valve with an API letter designation that for its API letter designation.
not just the Kd sizing factor that changes; did not appear large enough based on its 2. A required orifice area that is
the actual orifice area and, therefore, the API effective area. This can save time greater than the one calculated
capacity of the valve also adjusts to em- and money by preventing over-sizing of by API. This is usually due to
pirical, certified values. Both values can be valves, leading to smaller piping systems the 10% de-rating on Kd that
generally expected to increase over the API to support them. Remember: The ASME ASME requires.
values. The simple reason is that any given values are empirical and have a 10% safe- PSV sizing and selection is a wide
real-world valve is usually over-designed ty factor built in, so we do not need to topic, and this article addresses only one
so that it will meet and exceed the required worry about cutting the design too close; issue. Specific code references and quota-
minimum capacity of its corresponding the conservatism is already built in to the tions have been omitted to create a gen-
API size. This is a simple concept, but one method. We can choose the Brand X N- eral guideline that is useful for most engi-
that is often overlooked by engineers. orifice valve and sleep well at night. neers, rather than an interpretation of the
Back to our example scenario: Even codes. Anytime you are selecting a PSV
though the ASME Kd (and, therefore, the Recommendations. Avoid simply de- that is near its API capacity limits, a flag
required area) adjustment had a negligi- faulting to the API dataset for the final should go off in your head: Remember to
ble effect, the actual ASME orifice area “rating” or datasheet when selecting a check the ASME capacity!
(and, therefore, capacity) is significantly PSV. Use API sizing calculations as they
NOTES
higher than the listed API area and capac- are intended—for preliminary valve se- a
This article is written for an audience that is familiar
ity for an N-orifice. TABLE 1 shows a sum- lection. Then, switch to the ASME datas- with PSVs, PSV sizing, and API and ASME standards
mary of these calculations. et. This will often (but not always) result at a basic level.
With this adjusted orifice area, we in two differences:
can compare to the ASME certified area 1. An actual orifice area greater than BENJAMIN TAYLOR is Project Manager at Anvil
(which will always be larger than the API the standard API letter-designated Corporation in Bellingham, Washington. His
background is in control systems and instrumentation.
area), and we have our final answer for the orifice area. This means that the He holds a BS degree in chemical engineering from
valve size. Often, this will not result in a PSV selected performs slightly Montana State University in Bozeman, Montana, and a
different choice of valve, but sometimes, better, or is slightly larger, than PE in control systems engineering in Washington state.
• The pipe was not touching one of the bottom supports (1- Design observations. Several design features were observed
in. gap), due to a permanent deformation in the vertical plane during the investigation. The saddle support for the 60-in. flare
• The lone Y- stop that prevented upward movement of the header had an angle of contact of 72°. This is less than the mini-
line was forced open (see FIG. 3) mum angle of contact of 120° for saddles for horizontal pressure
• There was no ovalization at the long radius bends vessels. The flare header was not designed for hydro-fill condi-
• There was no sign of excessive axial or lateral movement tions. Some pipe spans that exceeded 40 ft, coupled with defi-
• There were no fretting marks on supports, that could be ciency in saddle design, caused high local stress and ovalization
associated with vibration. of the pipe near supports, as confirmed with stress analysis.
The first three observations led to the conclusion that the The pipe thickness (t) was too thin for its outside diameter
flare header must have undergone thermal movement in the (D), i.e., it had a large D/t ratio of 160, as against the industry
vertical plane. norm of ≤120. In FIG. 4, it can be seen that when the D/t ratio
0.07000
increases, the allowable strain limit decreases.
FIND OUT HOW YOU COULD IMPROVE THE LEARN MORE ABOUT THE REVOLUTION
EFFICIENCY OF ETHYLENE PRODUCTION IN HYDROCARBON GAS ANALYSIS
DOWNLOAD THE WHITE PAPER FROM: DOWNLOAD THE WHITE PAPER FROM:
SERVOMEX.COM/LASERSP SERVOMEX.COM/SPECTRASCAN
OR TO REQUEST ONE, EMAIL: LASERSP@SERVOMEX.COM OR TO REQUEST ONE, EMAIL: SPECTRASCAN@SERVOMEX.COM
D/t is not the lone parameter limiting the bending capacity The cracking occurred after the buckling damage. For crack-
of pipe. The other factors are: ing, tensile stress is required, and this must have resulted dur-
• Nonhomogeneity or the presence of imperfections in the ing straightening of the pipe when thermal gradients receded
material or when reversed.
• Initial out-of-roundness About 150 ft on either side of the sulfur lateral was deemed
• Loading conditions as the only area where all the following conditions required for
• Residual stress local buckling co-existed:
• Strength of the material in the longitudinal and circum- • High temperature due to downstream coker unit relief
ferential directions • Restraints that opposed thermal bowing
• Shape of the stress–strain diagram. • Large D/t ratio
• Pre-existing ovality due to large local stresses near saddle
Thermal bowing. The flare header is designed for flexibil- supports.
ity at 815°F. As per the design, it is expected to move only in
the horizontal plane while undergoing thermal expansion. A Repairs carried out. After thorough evaluation, repair strat-
movement in the vertical plane has to counter the gravity loads; egy improvement began. Key improvements included:
however, the several conditions have led to thermal bowing of
the flare header in the vertical plane:
restraint
Vertical
• Occasional temperature difference between the top and
bottom half of the horizontal flare header
Cold side–tensile stress
• Ovalization of the pipe, which reduced the stiffness of the
pipe in the vertical direction, compared to the horizontal direction
• To accommodate growth, the pipe tends to bend in the di-
rection of least stiffness.
Hot side–compressive stress
The reason for the circumferential thermal gradient is not
well understood. Within the horizontal flare header, there could Sliding support
be a two-phase flow of hot fluid, with the film-heat transfer co-
efficient being different for the liquid flow and the vapor flow. FIG. 5. Thermal bowing of pipe due to circumferential thermal gradient.
This difference can cause a temperature gradient between the
bottom and top of the pipe. Another possibility is the intermit-
tent and partial flow of liquid, hotter or colder than the mean line
temperature; it could create a circumferential thermal gradient.
FIG. 5 shows thermal bowing of a pipe due to circumferential
thermal gradient. The pipe will bend with outer curvature at
the hotter region. The nature and extent of stresses generated
is dependent on the boundary condition. In this example, the
vertical restraint opposes free thermal bowing. The region of
the pipe where actual displacement is less than needed for free
thermal expansion would be in compression and if reversed,
in tension. Therefore, the hotter half of the pipe will be under
compression and the colder half in tension.
GAS DESULPHURISATION
WITH THIOPAQ O&G:
STABLE & COST EFFECTIVE
Award winning technology for sulphur removal
and sulphur recovery from gas streams. Take the
quick scan at www.paqell.com/scan and receive
instant feedback about how THIOPAQ O&G technology
matches with your desulphurisation requirements!
www.paqell.com
mal gradient of 150°F. In general, the pipe is hotter at the bot- treat pipe as a beam and cannot predict local buckling of the
tom; however, in some instances, the temperature gradient is shell elements.
reversed, with the top of the pipe being hotter. Large D/t ratio also increases susceptibility to failures due
to acoustic induced vibration (AIV). AIV is caused by high
Discussions. Vertical movement of the pipe causing lift-off sound pressure levels inside flare headers during significant
from support will add gravity loads to the pipe. Thermal bow- relief scenarios. AIV failures typically develop at small bore tie-
ing will negate the free draining capability of the line, leading to ins to the flare header.
localized liquid pooling and associated issues. Thermal bowing
is not common with process plant piping, and when it occurs, Findings. If the D/t ratio of the pipe exceeds 100, these pre-
it is a difficult problem to correct. Most failures due to thermal cautions apply:
bowing are fatigue cracking at the circumferential welds. Buck- • When the pipeline is subjected to large bending mo-
ling due to thermal bowing is extremely rare due to installing ments, external pressure or axial compression, strain-based de-
pipes with favorable D/t ratio. The 60-in. flare header had both sign/buckling assessment using finite element analysis (FEA)
a very large D/t ratio and a loading/displacement condition should be performed
that increased vulnerability to buckling. • Equations for stress intensity factors given in ASME
When large lateral displacements are imposed on piping, B31.3 are valid only for D/t ≤ 100
failure generally manifests as localized buckling. Buckling is • During flexibility analysis, corrected stress intensity fac-
a failure due to instability and it causes process of achieving tors estimated through FEA should be used
equilibrium between external loads, internal resistance and • Flare headers should be designed with a dead load that
boundary restraint. Strain-based design is typically adopted for includes one quarter full of liquid
displacement controlled designs. Examples are subsea piping • Saddle supports for piping with a large D/t ratio require
or buried lines with large ground movements. design considerations like pressure vessel saddles (Zick analysis)
In a piping flexibility analysis, the displacement stress range • The D/t ratio for flare headers should be less than 120.
is compared with the allowable stress range. This is essentially
LITERATURE CITED
a check against potential fatigue failure due to cyclic tensile 1
Gresnigt, A. M. and R. J. Van Foeken, “Local buckling of UOE and seamless steel
stress. Compressive stress or strain limit checks are not part pipes,” 11th International Offshore and Polar Engineering Conference, Stavanger,
of a piping flexibility analysis. Piping stress analysis softwares Norway, June 2011.
GulfPub.com/GTL