Professional Documents
Culture Documents
Drainnage Piping After Installation
Drainnage Piping After Installation
Drainnage Piping After Installation
Inspection and Testing Procedure of Drainage Piping after Installation | Welding Techniques
1. Piping Inspections:
2. Piping Tests:
1. Piping Inspections:
The pipes shall not be enclosed, covered or put into operation until it has been inspected and
approved by authorities having jurisdiction.
Before testing all pipes should be cleaned and prepared thoroughly, obstructions removed by rodding
the stack with drain rods of suitable diameter.
After the installation is completed the site engineer shall prepare a Request for Inspection and submit
to the Engineer.
Below specified tests shall be performed in the presence of the authorities having jurisdiction:
Roughing-in Inspection: Inspection of piping before concealing or closing-in after roughing-in
and before setting fixtures.
Piping tests: Final inspection to observe tests specified below and to ensure compliance with
requirements.
Re inspection: If the authorities having jurisdiction find that piping will not pass tests or
inspections, required corrections shall be made and arranged for reinspection.
Reports: Inspection reports shall be prepared and have them signed by authorities having
jurisdiction.
After Installation inspection shell be raised as per an approved ITP.
2. Piping Tests:
The piping system to be tested shall be closed by plugging and blanking all openings in the system
in an approved manner. Suitable plugs are inserted at thelower end of the drain or sewer and at the head of
any connections.
A suitable bend together with a vertical length of pipe is fitted at the head of the sewer or drain to
provide the necessary test head. The system then filled with water.
747545865.docx Page - 1
MEP
So ensure that all piping and joints are no leak. During the water test, precautions should be taken to
prevent any movement of the drain or sewer.
All ends shall be plugged after completion of test to protect from debris.
After successful testing & Inspection of pipe work, covering of pipe work can proceed as per
approved drawing details.
Ensure LOTO procedure to be followed and implement comprehensive logout & tagout during
execution of work.
747545865.docx Page - 2
MEP
1.First of all estimate all material related to the repair segment. And arrange the same approved material as
per approved project spec and drawing.
7.After installation make test if required and coordinate with QC for inspection and approval from consultant.
747545865.docx Page - 3
MEP
Conduct site inspection to ensure access/egress is adequate for the task activities. Maintain good
housekeeping of the work area.
Lone working is not allowed.
Ensure work area housekeeping is properly maintained. equipment.
Use correct tools for the job. Do not use a tool or attachment for something it was not designed to.
Ensure tools undergone inspection by a competent person and record must keep. Colour coded as
required.
Follow LOTO procedure strictly when needed – when required.
Only competent/authorized person shall be assigned for the task.
Emergency evacuation routes and procedure shall be reminded regularly to the site staff by
construction and SHE team.
Be familiar with emergency response procedure
Any obstructions from pathways must be removed.
Emergency contact lists shall be posted at site.
747545865.docx Page - 4