Professional Documents
Culture Documents
Construction Project Management
Construction Project Management
1. Skilled or unskilled
2. Technical/ non-technical
3. Manager etc
Should be taken care of.
ii) Machine: the machine plays an important role as a resource as it makes
the work efficient and consumes less time. Also some works which are not
possible by labour force to carry out like heavy object lifting, etc can be
easily be done by the machine.
iii) Material:
the proper quality and adequate quantity (not too less or more) shall be
stocked at a time.
The material according to the requirement should be readily available
as to avoid any delay in the project.
Material shall be ordered well in advance.
Also various materials are required at various stages like- cement,
sand, water, timber, aggregate etc.
iv) Money: one of the basic resources to carry out construction
There should be a record that maintains the expenses being made.
It gives the idea of the current costing of the project and how much
could it cost at the completion.
Money should be released at completion of various stages of a project
to keep up the project momentum going.
Thus not causing any delay in the project.
8. Numerical
9. Numerical
10. Define:
10.1. Critical path: Is it the largest possible and the actual total time required
to complete the full task. It is also called the total calender.
10.2. Optimistic path:
The optimistic time is the fastest possible time needed to
complete the task and usually involves additional cost.
The optimistic time expressed as 'to', represents estimate of
minimum possible time by which an activity can be completed
assuming that everything is in order according to the plan and
there can be only minimum amount of difficulty.
10.3. Pessimistic path: Pessimistic time is expressed as 'tp' , represents
estimate of maximum possible time by which an activity can be
completed assuming that things may not be incidence of difficulties in
carrying out the activity.
11. Prepare a detailed note on mile stone chart. Mention its advantages and
disadvantages.
A milestone chart is used to represent groups of activities or significant events
of a project.
The chart shows a group of milestones in an organised manner
Milestone chart is devised to accommodate on project manager's wall.
Each project manager collected related group of activities in the project
and assigned a milestone to every group.
If there were any changes in the schedule which affected the date if
completion of the milestone, the project manager had to visit superior's
office and move to the milestone.
The list of tasks are displayed adjacent to time scale.
This approach is not without it's limitations, relationships among tasks
are not fully established.
12. Numerical
13. Define project management. Write down various objection and responsibilities
of a project manager.
Project management is a concept that helps in the coordination between the
organization strategies, program management, project management. The
structure of organizational project management is used to aligning the
practises of project management with organisational structure.
Project manager:
Organisation appoints a project manager for looking after or managing the
project and achieving the objectives for which project is authorised.
Objectives of project manager:-
Coordinates the efforts
Encourages the initiatives and keenness
He has to use each person’s ability and efficiency.
He has to develop a dynamic and devote time.
15. Define critical path method. Write uses of critical path method along with it’s
network procedure.
Is it the largest possible and the actual total time required to complete the full
task. It is also called the total calendar.
Uses:-
Deterministic model under which the result is ascertained in a manner
of certainty.
Activities of precise well known time.
Time estimate are of rain degree of occupancy.
Deterministic approach.
Cost is governing factor.
Project duration is fixed.
Cost is minimum
Network procedure:-
1. Earliest time: Earliest event time represents the earliest time
an event can possibly begin, conventionally it is zero for the
first event for others it is completed.
16. Write various activities under project management. Explain in brief points of
any activity in detail.
Answer 6
19. Define:-
19.1. Network diagram:- graphical portrayal of the activities and events of a
project. They show how each activity relates to others in the project.
19.2. Circle diagram:-
20. Numerical
21. True or false:
21.1. Man power and material has nothing to do with management of project.
False
21.2. Construction management has relation with project management.
True
21.3. PERT is “ project edit and research technology”
False
21.4. The length of the arrow in network diagram neither represents the
magnitude of work involved nor the time required for it’s completion.
True
21.5. Critical path is when free float is zero.
23. Repeat 22
24. Define:-
i) Free float:- an amount of time a schedule activity can be delayed without
delaying the early start of an immediately following schedule activity.
ii) Total float:- it is the difference between the finish date of the last task on
the critical path and the project completion date.
iii) Late finish:- the extra amount of time taken for a scheduled activity than
the proposed time.