PART 1-2-DACOHILL Project Execution Plan
PART 1-2-DACOHILL Project Execution Plan
TENDER NUMBER:
DOCUMENT TITTLE:
PROJECT EXECUTION PLAN
Numeric
Country Originator Document
Project Code Client Code Sequence
Code Code Code
Number
A 18/10/2023 IFT C. O E. E D. E
Client
Rev Rev. Date Description Prepared By Checked By Approved By
Rev./App
REPAIR OF INSULATION FOR
HOT/COLD LINES IN EGPP REFRIGERATION &
FRACTIONATION
PROJECT NUMBER:
PROJECT EXECUTION PLAN
Document No: NG-EGPP-DGSL-PNG-PEP-0001
AUTHORIZATION PAGE
REVISION HISTORY
TABLE OF CONTENT
1.0 INTRODUCTION 5
2.0 PROJECT OVERVIEW 5
2.1 Scope of work 5
2.1.1 Location 5
2.1.2 Timeline 5
2.1.3 Safety 5
2.2 PROJECT DESCRIPTION 5
2.2.1 Highlights of Work Elements 5
2.3 REFERENCES PROJECT DRAWINGS 5
2.4 PROJECT SPECIFICATION 5
3.0 PREPARATORY PHASE 6
3.1. Project Kickoff 6
3.2. Risk Assessment 6
3.3. Material Procurement 6
4.0 WORK EXECUTION PHASE 6
4.1. Insulation Removal 6
4.2. Surface Preparation 6
4.3. Installation of New Insulation 6
4.4. Quality Control 7
4.5. Final Safety Inspection 7
5.0 ENVIRONMENTAL RESPONSIBILITY 7
6.0 PROJECT COMPLETION PHASE 7
6.1. Final Inspection 7
6.2. Documentation 7
6.3. Handover 7
7.0 CONCLUSION 7
APPENDICES
REPAIR OF INSULATION FOR
HOT/COLD LINES IN EGPP REFRIGERATION &
FRACTIONATION
PROJECT NUMBER:
PROJECT EXECUTION PLAN
Document No: NG-EGPP-DGSL-PNG-PEP-0001
1.0 INTRODUCTION
This work execution plan outlines the steps and processes to be followed by Dacohill Global
Services Limited (DACOHILL) in the repair of insulation for hot and cold lines within the EGPP
(Electricity Generation and Power Plants) Refrigeration & Fractionation Units for PNG Gas
Limited (CLIENT). The objective is to ensure the efficient and safe restoration of the insulation
system.
2.1.3 Safety: The repair of insulation for hot and cold lines in EGPP Refrigeration &
Fractionation Units is a project of significant importance, and safety is a
cornerstone of its success. Continuous monitoring and unwavering
adherence to safety protocols are essential to protect personnel, the
environment, and DACOHILL's reputation while ensuring that the project is
executed efficiently and responsibly. In DACOHILL Safety is not an option; it is
an absolute necessity
2.3 REFERENCES
PROJECT DRAWINGS
• Applicable Project Drawings
• P&IDs
• Others.
2.4 PROJECT SPECIFICATION
• Section 31 of the Oil pipeline Act CAP 338 of the Law of the Federation of Nigeria
1990.
• Piping Works Specification
REPAIR OF INSULATION FOR
HOT/COLD LINES IN EGPP REFRIGERATION &
FRACTIONATION
PROJECT NUMBER:
PROJECT EXECUTION PLAN
Document No: NG-EGPP-DGSL-PNG-PEP-0001
6.2. Documentation
DACOHILL shall ensure compilation of detailed records, including photographs, inspection
reports, and material certificates and Material datasheets.
6.3. Handover
• DACOHILL shall ensure handover of the completed project to PNG representatives.
7.0 CONCLUSION
The repair of insulation for hot and cold lines in EGPP Refrigeration & Fractionation Units is a
critical endeavor to enhance operational efficiency and safety. This work execution plan will
guide DACOHILL project team in executing the repair, ensuring quality, safety, and
environmental responsibility are maintained throughout the project.
REPAIR OF INSULATION FOR
HOT/COLD LINES IN EGPP REFRIGERATION &
FRACTIONATION
PROJECT NUMBER:
PROJECT EXECUTION PLAN
Document No: NG-EGPP-DGSL-PNG-PEP-0001
APPENDICES
REPAIR OF INSULATION FOR
HOT/COLD LINES IN EGPP REFRIGERATION &
FRACTIONATION
PROJECT NUMBER:
PROJECT EXECUTION PLAN
Document No: NG-EGPP-DGSL-PNG-PEP-0001
Work Breakdown Structure (WBS) for Repair of Insulation in EGPP Refrigeration &
Fractionation
1. Project Initiation
• 1.1 Define project scope and objectives
• 1.2 Identify stakeholders
• 1.3 Appoint project manager and team
• 1.4 Allocate initial budget and resources
2. Feasibility Assessment
• 2.1 Insulation condition assessment
• 2.2 Determine repair scope
• 2.3 Impact analysis on EGPP operations
3. Planning
• 3.1 Develop repair plan
• 3.2 Create a detailed budget
• 3.3 Procure necessary permits and approvals
• 3.4 Establish safety guidelines and risk assessment
4. Procurement
• 4.1 Procure insulation materials
• 4.2 Procure necessary equipment
• 4.3 Ensure timely delivery
5. Preparatory Work
• 5.1 Mobilize workforce and equipment
• 5.2 Conduct safety training
• 5.3 Verify availability of tools and equipment
6. Insulation Removal
• 6.1 Remove damaged insulation
• 6.2 Disposal of waste materials
• 6.3 Inspect hot/cold lines for underlying issues
7. Surface Preparation
• 7.1 Clean exposed surfaces
• 7.2 Make necessary pipeline repairs
• 7.3 Apply primers or corrosion protection coatings
8. Insulation Replacement
• 8.1 Install new insulation materials
• 8.2 Ensure proper fitting and sealing
REPAIR OF INSULATION FOR
HOT/COLD LINES IN EGPP REFRIGERATION &
FRACTIONATION
PROJECT NUMBER:
PROJECT EXECUTION PLAN
Document No: NG-EGPP-DGSL-PNG-PEP-0001
This proposed Work Breakdown Structure breaks the project into manageable tasks, making
it easier to plan, manage, and execute. Each task shall have its own detailed plan, timeline,
and responsible team members. This WBS can be adjusted as needed to match the specific
requirements and complexities of the EGPP insulation repair project.
REPAIR OF INSULATION FOR
HOT/COLD LINES IN EGPP REFRIGERATION &
FRACTIONATION
PROJECT NUMBER:
PROJECT EXECUTION PLAN
Document No: NG-EGPP-DGSL-PNG-PEP-0001
foamboard-2000-d---2500-d---3000-d---3500-d846.pdf Band-It-Industrial_Solutions_Guide.pdf
REPAIR OF INSULATION FOR
HOT/COLD LINES IN EGPP REFRIGERATION &
FRACTIONATION
PROJECT NUMBER:
PROJECT EXECUTION PLAN
Document No: NG-EGPP-DGSL-PNG-PEP-0001