Betong Byggnadsverk
Aktivitet / Arbetsberedning för Startdatum Slutdatum Nr
- Earlier experiences of both Skanska and Lambda have been worked into the methodology
INTERN INFORMATION
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 2 (17)
2. Startläge 3. Slutläge
Tidigare aktiviteter, tillgänglighet och skick arbetsområde, krav enligt handlingar, material, Förutsättningar för nästkommande aktivitet, färdigställda arbeten, kvarstående arbeten och färdiga
arbetskraft och maskiner samt yttre omständigheter. Ta med tillämpbart normalläge. kontrollplaner.
(Previous activities, availability and condition work area, requirements according to documents, (Prerequisites for next activity, completed work, remaining work and completed control plans.)
materials, labor and machinery and external circumstances. Bring the applicable normal position.)
- Lambda responsible to complete Site Induction for own personnel (both - All permanent works completed including patching & defect rectification
digital & physical inductions) before starting any works. (where/if necessary).
- Ground excavation and foundation preparation completed by civil, clear - Joint inspection of the works by Skanska & subcontractor, for acceptance,
approval, and/or defect notification.
space 2 meters outside of bottom slab around the bridge and 5-7 cm lower
- BIM Checklist’s complete.
under slab plus 50 cm around slab for lean concrete. - Removal of temporary works, equipment & materials (scaffold, formwork
- Crane assembly completed by Skanska Rental. etc).
Checklist environment (checklista miljö) performed
2. Metodbeskrivning / Methodology
Tillvägagångssätt, strategi eller teknik för att gå från startläge till slutläge (Approach, strategy, or technology to move from start to finish mode)
• Site Establishment
- Survey / site set-out
- Pour blinding concrete 5-7 cm and around 50 cm outside of bottom slab.
- Delivery of materials & equipment
- Establish storage container facilities
- Fence around site establishment
- Establish saw workstation
- When different quality of wood is used on site the better version (C24) will be sprayed and stored separately to no mix qualities.
INTERN INFORMATION
• Bottom Slab
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 3 (17)
2. Metodbeskrivning / Methodology
Tillvägagångssätt, strategi eller teknik för att gå från startläge till slutläge (Approach, strategy, or technology to move from start to finish mode)
- Formwork is made out of prefabricated form pieces that will be reused on the slabs, formwork from bridge 12/4 with height 1200 mm will be reused as slab is
around 630-800 mm height.
INTERN INFORMATION
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 4 (17)
2. Metodbeskrivning / Methodology
Tillvägagångssätt, strategi eller teknik för att gå från startläge till slutläge (Approach, strategy, or technology to move from start to finish mode)
- Form oil is applied to forms before they are mounted.
- Weld nuts for fromties will be welded to an 8 mm steel rod that will connect to the opposite side to another weld nut and glasfiber form ties will go through the
formwork to take the pressure from casting and will be placed on two different levels. This can also be done by connecting the 8 mm rod to one of the montage
bars in the bottom.
- Important that glasfiber rods are long enough that no part of the weld nut or 8 mm steel rod reaches into the concrete cover.
- All sharp cornes will be softened with the use of a 21 mm wodden triangle list montaged in the form except for the open ends of the bridge where a 75 mm list
will be used. Signs of this 75 mm list can be seen on the bottom right of picture above. Beware of concrete cover after placement of triangle lists.
- Concrete cover to the bottom is 50 mm including the montage bars, 16 mm on the bottom and 12 mm on the sides of the slab.
- Concrete cover for sides and top are 35 mm.
- Through the bottom slab there are both a pipe for lights in the bridge (32 mm) but also 5 pc. of fi110 mm pipes going straight through the slab. These needs to be
tied down so that they do not risk to float up during casting.
- ‘Norskor’ will be used for setting the height of the top layer, these will have a safety bend to avoid injuries and will later be cut to the correct height, see picture.
After setting heights of montage bars on norskor, check heights with surveryor so we get correct top level of steel.
- Bars larger than fi16 mm cannot be joint at the same cut. See BMUK EBC for details.
- Space for concrete sampling and casting spots need to be prepared and measured by surveyor.
- Perform works required for earthing.
- Survey tolerance check of both steel and formwork including measuring the spot for concrete sampling. Cubes for sampling will be taken
during casting but as a backup we also measure a spot where a cylinder can be taken if necessary.
- If tempertures during casting will be sub zero we need to place cables for concrete computer, see document “Temperaturspricksberäkning”
- Prior to casting a cast meeting will be held where detailed man power planning will be done. Sufficient plans will also be made for possible
weather scenarios and for any other problem that might occur during casting.
- Lambda will notify Skanska when the works are ready for visual inspection, during this checklist 1 will be filled out by Lambda.
- The client will be notified about castings in advance and be given a possibility for a joint inspection.
- For detailed planning regarding the casting a cast program and schedule will be developed.
- Concrete pump will be placed and installed according to ETS from Skanska Teknik.
INTERN INFORMATION
2. Metodbeskrivning / Methodology
Tillvägagångssätt, strategi eller teknik för att gå från startläge till slutläge (Approach, strategy, or technology to move from start to finish mode)
- Cut form ties along the concrete surface and repair as necessary.
scaffolding should be 440 mm x 440 mm and minimum 90 mm thick, if drawing requires thicker the rest
of the height can be done with a 170x170x45 mm board.
- Safety harness with approved anchor point must be used during montage of scaffolding. All personnel
shall be familiarized with the fall rescue procedure explained under section 11. Risk Inventory.
- Safety harness with approved anchor point must be used during montage of formwork and/or anytime
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 6 (17)
2. Metodbeskrivning / Methodology
Tillvägagångssätt, strategi eller teknik för att gå från startläge till slutläge (Approach, strategy, or technology to move from start to finish mode)
where an unprotected edge exists (i.e. valv form, edge beam etc).
- Top floor will be completely floored and railing put up where there is a risk of falling.
- Three crowns should be put to the correct height before wooden beams are placed, surveyor will assist with this.
- Construct formwork for bridge roadway arch including edgebeam, see sketches for dimensions.
- Formties cannot be but inside the edgebeam.
- ‘Flytbräda’ on the bottom inside of edgebeam form should be minimum 150 mm and have a small
inclination away from edgebeam, this to make it easier to cast and vibrate edgebeam but also to
prevent and gathering of water close to edgebeam.
- Under formwork a plastic will be placed to minimize cleaning of scaffolding.
- Lay reinforcement and make room for casting spots and concrete sampling.
- Before finishing reinforcement make sure that all pipes for cables have been installed including the
cut outs for lights
- Make sure reinforcement for consoles can be installed before putting up too much formwork.
- See sketch for formwork solution for consoles and follow dimensions from designer.
- Bolts on edgebeam and wings on top of bridge SHOULD have electrical contact with
reinforcement, this will be done through earthing and the railing.
- Part of bolts outside of concrete is taped to protect them from splash of concrete.
- Montage EKP according to model, OK to weld where EKP is placed in model.
- Montage cables for concrete computer according to “Temperaturspricksåtgärder”.
- Perform works required for earthing in superstructure.
- Inspection of loadbearing form support will be done by Skanska and third party inspector.
- Survey tolerance check including measuring spot for concrete sampling.
- Cast concrete
- Prior to casting a cast meeting will be held where detailed man power planning will be done. Sufficient plans will also be made for possible weather scenarios
INTERN INFORMATION
2. Metodbeskrivning / Methodology
Tillvägagångssätt, strategi eller teknik för att gå från startläge till slutläge (Approach, strategy, or technology to move from start to finish mode)
- Cooling pipes and measurement of temperature will be started as casting begins.
- During casting checklist 2 will be controlled and filled out by Lambda.
- Surface will be machined with ‘helicopters’ with the use of steel plate, finished surface will be covered as soon as possible with plastic and if applicable some
water on top. If necessary sprinklers will be used to keep concrete from drying.
- Edgebeam will be troweled by hand with filterboard and covered with plastic.
- After casting
- Mount handrails & screens before striking working platforms.
- Start of striking form & form support after OK from Skanska supervision.
- Scaffolding is lowered in the top so that the formwork can be dismantled from the top level floor.
- After formwork have been dismantled concrete surfaces are inspected and fixed as necessary.
- Once surfaces are ok scaffolding is dismantled.
- Formwork for walls will be dismantled after the scaffolding is out on the inside and outside it can go along at the same time.
- When all formwork is done the rest of the structure is repaired where necessary before final inspection of the concrete works.
TO BE CONTINUED IN REVISION 2
• Retaining wall (under bridge) –Construct formwork (first side)
- fix reinforcement & cast-in’s
- perform works required for earthing
- construct formwork (second side)
- Survey tolerance check
- Cast concrete (need to order extra hose?)
- strike formwork
- Measure contact and mount railing
INTERN INFORMATION
-
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 8 (17)
2. Installation and striking of formwork and form support: 2. Installation of form support must be in accordance with
Falling materials manufacturers instructions and temporary works design
Working at height drawings. Check equipment and do not use damaged
Manual handling items. Harness & fall restraint with approved anchor
Noise point must be used when not on a working platform.
Failure of temporary structure Avoid manual handling where possible by mechanical
means. Lift materials in a team to lighten the load per
person. Use good technique when lifting (bend at the
legs, do not twist). Know your lifting capacity - do not
exceed it. Wear ear protection, especially when striking.
Follow drawings for temp form support and use
specified materials only. Check temporary structure
before loading. Check concrete test strength results
before unloading & striking.
3. Installation of steel reinforcement & cast-in items:
Injuries from working with reinforcement 3. Protect ends of protruding rebar with caps. Follow
INTERN INFORMATION
4. Perform works required for earthing: 4. Obtain hot works permit before starting. Only
Hot works trained/competent personnel to use equipment. Use
correct fire resistant PPE. Equipment shall be
checked/serviced regularly. Fire Extinguishers to be at
the workface ready for emergency use. Inspect/monitor
area for 1 hour after hot works complete.
personnel.
2. Risk of defects, deformation, deflection, damages 2. Survey tolerance checks before casting. Temperature
monitoring. Prepour inspections must be carried out by
UE & Skanska and checklists completed/approved
before casting. Casting operations to be in accordance
with “Krav Brobyggande, version 2.0” and “SS-
EN_13670_2009 Execution of Concrete Structures”.
Control rise rate, pour height, vibration. Ensure
temporary works are sufficient.
3. Traditional form 3. Only new materials to be used for ‘board form’ concrete
surfaces which are exposed and seen as final product.
Take care to ensure consistency in finish across project
entirety. Plywood form may be reused <5 times.
4. Winter castings
4. Planning based on temperature cracking measures.
Planning in casting schedule.
Miljö / Environment
1. Material useage & sustainability 1. Reuse materials where possible. Planning meetings to
identify opportunity to share material resources between
INTERN INFORMATION
4. Waterway contamination 4. Control water run-off from work site. Only pump out
water to approved locations.
3. EMERGENCY PROCEDURE & CONTACT 3. All personnel on the project shall install the “SOS
NUMBERS Alarm” application on their mobile phone device. This
app is the preferred method of raising an emergency call.
If not working - For AMBULANCE call 112
INTERN INFORMATION
8. Kapaciteter och tider. / Capacities and times. Åtgärder för att säkerställa kapaciteterna. / Measures to ensure capacities Uppföljning. 7
Vad finns i kalkylen? Follow-up
Kapaciteter
Text Text
Text
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 12 (17)
Tider
Text Text Text
9. Material, Resurser och kompetens / Materials, Resources and Competence Mängd / Finns. Säkerställ att materialet finns tills momentet startar. Ansvarig Klart till
Förteckna material, maskiner,Utbildningar, YA och UE Amount Ja/Nej (Ensure the resource is available when the task begins).
Material
Formwork (Traditional)
Form support (Layher)
Working platform (Layher)
Steel reinforcing bar (loose bar, pre-bent, cages prefab’d)
Concrete (Sydsten)
Cast-in items (pipes, bolts, earthing items etc)
Chemicals (eg. Deseil, retarder, form oil, bitumen board etc)
Resourses
Crane supplier (Skanska Rental)
Crane operator (UE Concrete – Lambda)
Logistics Team (Skanska)
UE Form/rebar/concrete (Lambda)
UE Form support & working platform (Lambda)
Competence
Personnel requiring task specific education and competency:
- Crane Operator
- Rigger/banksman
- Hot works personnel (cutting, welding, etc)
- Machine/vehicle operators
- Site specific safety introduction
- Råd och skydd training (railway education)
INTERN INFORMATION
- Scaffolding education
- Personnel installing & inspecting Layher form support
- Personnel installing & inspecting working platform scaffold
- Personnel installing any load bearing temporary works of any kind
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 13 (17)
10. Kommunikation
Säkerställ att all berörd personal har full kännedom hur aktiviteten ska utföras (Ensure that all relevant personnel are fully aware of how to perform the activity).
Skanska will deliver Toolbox talks to communicate important safety information throughought the project duration.
Lambda take responsibility for translating the information in this document and assurance that their personnel understand the content.
Register of signatures
11. Säkerhetsgenomgång
Inventera risker som kan vara aktuella vid arbetsmomentet. Bocka i rutan ”Ja” först efter att åtgärder från AMP hanterats i arbetsberedningen,
(Inventory risks that may be relevant at the time of the operation. Check the box "Yes" only after handling measures from AMP in the work preparation,)
Uppdatering
Riskinventering (Risk Inventory) Nej Ja Ytterligare åtgärder/Kommentarer (Additional Actions/Comments) AMP?
1. Arbete med risk för fall från högre höjd än två meter. ☐ ☒ Consrtuct & use working platform where risk is present. Use harness & fall ☐
Work with risk of falling from a height greater than two metres. restraint with approved anchor point when not on a working platform.
Rescue plan in the case where a person falls and is hanging by harness:
1. If the person can be safely reached from an adjacent working platform, they
can be lifted by hand by persons on to that platform. Those performing the rescue
should also be protected by wearing a harness if they need to reach/climb outside
of the platform.
2. If the person hangs out of reach, crane hook is lowered to the person who
connects himself by the harness to be lifted safely to the nearest working platform
2. Arbete som innebär risk att begravas under jordmassor eller sjunka ner i lös ☒ ☐ ☐
mark.
Work that involves the risk of being buried under soil or sinking into loose ground.
3. Arbete som kan medföra exponering för kemiska och biologiska ämnen. ☐ ☒ Protective clothing should be worn to protect skin against concrete burns. Wash ☐
Work likely to involve exposure to chemical and biological substances. concrete off if splashed. Before working with any chemical, check material data
sheet and follow manutacturers instructions for use & protective measures.
INTERN INFORMATION
5. Arbete i närheten av högspänningsledning (samt övriga ledningar i mark). ☐ ☒ Site briefing to notify personnel of services to be aware of & avoid. Such services ☐
Work in the vicinity of a high-voltage line (as well as other lines in the ground). are to be demarcated with warning signs/barriers.
11. Säkerhetsgenomgång
Inventera risker som kan vara aktuella vid arbetsmomentet. Bocka i rutan ”Ja” först efter att åtgärder från AMP hanterats i arbetsberedningen,
(Inventory risks that may be relevant at the time of the operation. Check the box "Yes" only after handling measures from AMP in the work preparation,)
Uppdatering
Riskinventering (Risk Inventory) Nej Ja Ytterligare åtgärder/Kommentarer (Additional Actions/Comments) AMP?
11. Arbete vid vilket lansering, montering och nedmontering av tunga byggelement ☐ ☒ Avoid manual handling where possible to lift by mechanical means. Lift materials ☐
eller tunga formbyggnadselement ingår. in a team to lighten the load per person. Use good technique when lifting (bend at
Work involving the launch, assembly and dismantling of heavy building elements the legs, do not twist). Know your lifting capacity - do not exceed it.. Follow
or heavy formwork building elements. drawings for temporary form support, temporary structure must be checked by
Layher before loading.
12. Arbete på plats eller område med passerande fordonstrafik. ☐ ☒ Separate working area from trafficked areas with barriers & reduce traffic speed ☐
Work on site or area with passing vehicle traffic. with signage.
13. Rivning av bärande konstruktioner eller hälsofarliga material eller ämnen ☐ ☒ Removal of load bearing form support must be authorized by Skanska’s Work ☐
Demolition of load-bearing structures or hazardous materials or substances Supervisor, Project Engineer, or Block Manager.
14. Rörelse av maskiner och fordon ☐ ☒ Only trained personnel to operate machines and vehicles. Use a spotter (assistant ☐
Movement of machines and vehicles person) to help when reversing in a congested area.
15. Arbetsmaskiner (inkl utrustning) ☐ ☒ Only trained personnel to operate machines & equipment. ☐
Work machines (incl. Equipment)
16. Arbete med risk för kläm-, såg- och skärskador ☐ ☒ Only trained operatives to use powertools. Use guards on tools where there is a ☐
Work with risk of crushing, sawing and cutting injuries risk of cutting. Keep fingers clear of potential crushing areas. Good housekeeping
(keep area tidy and free of loose material lying around).
17. Arbete med temporära konstruktioner ☐ ☒ Drawing details and manufacturers instructions must be followed when installing ☐
Work with temporary constructions temporary works. Temporary structures must not be loaded without prior
inspection & approval from Layher’s representative and Skanska’s Work
Supervisor, Project Engineer, or Block Manager.
INTERN INFORMATION
19. Heta arbeten, brand- och explosionsskydd ☐ ☒ Obtain hot works permit before starting. Only trained/competent personnel to use ☐
Hot works, fire and explosion protection equipment. Use correct fire resistant PPE. Equipment shall be checked/serviced
regularly. Fire Extinguishers to be at the workface ready for emergency use.
Inspect/monitor area for 1 hour after hot works complete.
20. Risker för fall till samma nivå ☐ ☒ Keep worksite clean and tidy. Don’t leave unused materials lying around. Don’t ☐
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 15 (17)
11. Säkerhetsgenomgång
Inventera risker som kan vara aktuella vid arbetsmomentet. Bocka i rutan ”Ja” först efter att åtgärder från AMP hanterats i arbetsberedningen,
(Inventory risks that may be relevant at the time of the operation. Check the box "Yes" only after handling measures from AMP in the work preparation,)
Uppdatering
Riskinventering (Risk Inventory) Nej Ja Ytterligare åtgärder/Kommentarer (Additional Actions/Comments) AMP?
Risks of falls to the same level walk around congested areas while using a mobile phone.
22. Arbete med ergonomiska risker ☐ ☒ Avoid manual handling where possible to lift by mechanical means. Lift materials ☐
Work with ergonomic risks in a team to lighten the load per person. Use good technique when lifting (bend at
the legs, do not twist). Know your lifting capacity - do not exceed it.
23. Arbete med exponering för buller ☐ ☒ Wear ear protection when using noisy equipment or striking formwork. Wear ear ☐
Work with exposure to noise protection when working near noisy equipment/activities. Tell people around you if
you plan to start using noisy equipment.
24. Arbete med exponering för vibrationer ☐ ☒ Rotate personnel using vibrating equipment to minimize exposure. ☐
Work with exposure to vibrations
25. Arbete i dammande miljö ☐ ☒ Always wear respiratory protection when working with / near dusty activities. ☐
Work in a dusty environment
26. Risker för tredje man i anslutning till arbetsplatsen ☐ ☒ Separate work area and restrict access from public with barriers & signage. ☐
Risks to third parties in connection with the workplace
28. Arbete vid järnväg och spårbunden trafik ☐ ☒ Ensure exclusion zones are used, fenced off with barrier and all site personnel ☐
Work near railway tracks and rail traffic are familiar with exclusion zones.
30. Etableringsytor - Konflikt mellan transporter och oskyddade personer(Arbetare) ☐ ☒ Ensure positive communication between transporters and site personnel. ☐
Establishment areas - Interface between transport and unprotected persons Transporters should be accompanied by a site inducted person.
(Workers)
31. Tidplan-risk för försämrad arbetsmiljö på grund av kort byggtid och begränsade ☒ ☐ ☐
Tider för spåravstängning(tågstopp). (B AMP)
Risk of deterioration of work environment due to over-ambitious
program/capacities and/or limited times for track closure (train stop). (B AMP)
INTERN INFORMATION
12. Signering
Följande produktionspersonal har tagit del av aktuell arbetsberedning
(The following production staff have read, understood and agree with this arbetsberedning)
Efter utfört arbete stängs upprättad arbetsberedning i syfte att vara en del av vår egenkontroll samt förbättra arbetet med arbetsberedningar.
Nedanstående rubriker diskuteras tillsammans med de som utfört arbetet och varit med att upprätta arbetsberedningen
After the work has been completed, the established work preparation is closed in order to be part of our own control and to improve the work with work preparations.
The following headings are discussed together with those who carried out the work and helped to establish the work preparation