Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 1 (17)

. Projekt Projektnummer Upprättad av Datum

Ängelholm – Maria, Dubbelspårsutbyggnad 207271 Markus Johansson 20210628


Block: Granskad av PC: Datum

Betong Byggnadsverk
Aktivitet / Arbetsberedning för Startdatum Slutdatum Nr

Portal frame bridge construction BRO19 v.34_2021 v.51_2021 Rev.01

1. Aktuella handlingar och tillstånd / Relevant documents and permits

- Krav Brobyggande, version 2.0


- -14A-052-BRO_18-4001.pdf Teknisk Beskrivning
- SS-EN_13670_2009 Execution of Concrete Structures
- 144113-05-025-0001 GESTALTNINGSÅTGÄRDER
- AF_Ängelholm_Helsingborg_TE
- Bro 18 Lyftplan 1 Armering och Byggmaterial
- Kommunikationsflöde Olycka & Tillbud
- BIM360 Field Management Checklist’s
- Arbetsmiljöplan / Health & Safety Plan, version 2.0
- ETS for Tower crane
- ETS for Concrete pump.
- Gjutplan / Casting plan (attached)

1. Tidigare erfarenheter / Past Experiences

Did we learn anything from prior bridge constructions?

- Earlier experiences of both Skanska and Lambda have been worked into the methodology
INTERN INFORMATION
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 2 (17)

2. Startläge 3. Slutläge
Tidigare aktiviteter, tillgänglighet och skick arbetsområde, krav enligt handlingar, material, Förutsättningar för nästkommande aktivitet, färdigställda arbeten, kvarstående arbeten och färdiga
arbetskraft och maskiner samt yttre omständigheter. Ta med tillämpbart normalläge. kontrollplaner.

(Previous activities, availability and condition work area, requirements according to documents, (Prerequisites for next activity, completed work, remaining work and completed control plans.)
materials, labor and machinery and external circumstances. Bring the applicable normal position.)
- Lambda responsible to complete Site Induction for own personnel (both - All permanent works completed including patching & defect rectification
digital & physical inductions) before starting any works. (where/if necessary).
- Ground excavation and foundation preparation completed by civil, clear - Joint inspection of the works by Skanska & subcontractor, for acceptance,
approval, and/or defect notification.
space 2 meters outside of bottom slab around the bridge and 5-7 cm lower
- BIM Checklist’s complete.
under slab plus 50 cm around slab for lean concrete. - Removal of temporary works, equipment & materials (scaffold, formwork
- Crane assembly completed by Skanska Rental. etc).
Checklist environment (checklista miljö) performed

2. Metodbeskrivning / Methodology
Tillvägagångssätt, strategi eller teknik för att gå från startläge till slutläge (Approach, strategy, or technology to move from start to finish mode)
• Site Establishment
- Survey / site set-out
- Pour blinding concrete 5-7 cm and around 50 cm outside of bottom slab.
- Delivery of materials & equipment
- Establish storage container facilities
- Fence around site establishment
- Establish saw workstation
- When different quality of wood is used on site the better version (C24) will be sprayed and stored separately to no mix qualities.
INTERN INFORMATION

• Bottom Slab
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 3 (17)

2. Metodbeskrivning / Methodology
Tillvägagångssätt, strategi eller teknik för att gå från startläge till slutläge (Approach, strategy, or technology to move from start to finish mode)
- Formwork is made out of prefabricated form pieces that will be reused on the slabs, formwork from bridge 12/4 with height 1200 mm will be reused as slab is
around 630-800 mm height.
INTERN INFORMATION
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 4 (17)

2. Metodbeskrivning / Methodology
Tillvägagångssätt, strategi eller teknik för att gå från startläge till slutläge (Approach, strategy, or technology to move from start to finish mode)
- Form oil is applied to forms before they are mounted.
- Weld nuts for fromties will be welded to an 8 mm steel rod that will connect to the opposite side to another weld nut and glasfiber form ties will go through the
formwork to take the pressure from casting and will be placed on two different levels. This can also be done by connecting the 8 mm rod to one of the montage
bars in the bottom.
- Important that glasfiber rods are long enough that no part of the weld nut or 8 mm steel rod reaches into the concrete cover.
- All sharp cornes will be softened with the use of a 21 mm wodden triangle list montaged in the form except for the open ends of the bridge where a 75 mm list
will be used. Signs of this 75 mm list can be seen on the bottom right of picture above. Beware of concrete cover after placement of triangle lists.
- Concrete cover to the bottom is 50 mm including the montage bars, 16 mm on the bottom and 12 mm on the sides of the slab.
- Concrete cover for sides and top are 35 mm.
- Through the bottom slab there are both a pipe for lights in the bridge (32 mm) but also 5 pc. of fi110 mm pipes going straight through the slab. These needs to be
tied down so that they do not risk to float up during casting.
- ‘Norskor’ will be used for setting the height of the top layer, these will have a safety bend to avoid injuries and will later be cut to the correct height, see picture.
After setting heights of montage bars on norskor, check heights with surveryor so we get correct top level of steel.
- Bars larger than fi16 mm cannot be joint at the same cut. See BMUK EBC for details.
- Space for concrete sampling and casting spots need to be prepared and measured by surveyor.
- Perform works required for earthing.
- Survey tolerance check of both steel and formwork including measuring the spot for concrete sampling. Cubes for sampling will be taken
during casting but as a backup we also measure a spot where a cylinder can be taken if necessary.
- If tempertures during casting will be sub zero we need to place cables for concrete computer, see document “Temperaturspricksberäkning”
- Prior to casting a cast meeting will be held where detailed man power planning will be done. Sufficient plans will also be made for possible
weather scenarios and for any other problem that might occur during casting.
- Lambda will notify Skanska when the works are ready for visual inspection, during this checklist 1 will be filled out by Lambda.
- The client will be notified about castings in advance and be given a possibility for a joint inspection.
- For detailed planning regarding the casting a cast program and schedule will be developed.
- Concrete pump will be placed and installed according to ETS from Skanska Teknik.
INTERN INFORMATION

- During casting checklist 2 will be controlled and filled out by Lambda.


- After/during casting wall/slab connections will be sprayed with retarder for a coarse surface. If cold/rainy weather prohibits this, joints will be sand blasted later.
- Concrete surface will be machined with ‘helicopters’ with the use of steel plate, when surface is finished it will be covered with tarps and/or plastic.
- Retarder will be cleaned off the day after casting.
- Strike formwork after OK from Skanska supervisor.
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 5 (17)

2. Metodbeskrivning / Methodology
Tillvägagångssätt, strategi eller teknik för att gå från startläge till slutläge (Approach, strategy, or technology to move from start to finish mode)
- Cut form ties along the concrete surface and repair as necessary.

• Frame Legs, Wings walls & Superstructure


- Make sure connection between wall and slab is cleaned of retarder and sufficiently coarse before continuing works.
- Construct formwork for legs & wings starting with the inside. Follow dimensions of approved drawings for form.
- Formwork panels are prepared on the ground and lifted down with crane.
- Formwork will be supported by supports connecting to the bottom slab with concrete screws. These will be placed
to not collide with scaffolding towers, surveyor marks towers on the bottom slab before mounting form supports.
See sketches for dimensions of formwork and typical solutions.
While opening the formwork work on heights will be done with the use of a scaffolding.
Form oil is applied to formwork, where new planks are used it is sprayed twice to minimize the amount of wood
getting stuck in the concrete surface. Don,’t forget to put oil on triangular lists as well.
- Erect working platform on the outside, inspection including ‘green sign’ must be signed and mounted before use.
- Concrete cover for walls are 35 mm on the inside and 35 mm on the outside.
- Montage bars for walls will be done with fi12 mm bars.
- Cooling pipes should be installed according to document ‘Temperatursprickåtgärder’. Before formwork is closed
make sure that cooling pipes are connected with double hose clamps and tested to be waterproof.
- Cables for measuring temperature also needs to be installed before closing of the formwork.
- Perform works required for earthing in frame legs & wings
- Construct formwork for frame legs/wings on the outside AFTER cleaning out the bottom.
- Construct supporting scaffolding for bridge roadway arch.
- A piece of wood (45x170) should be placed under each feet of the scaffolding and correct height of the
feet should be adjusted before continuing, feets should also be placed so that it is later easy to hit wedge
with a sledge hammer when lowering the scaffolding. When outside the bottomslab the wood under
INTERN INFORMATION

scaffolding should be 440 mm x 440 mm and minimum 90 mm thick, if drawing requires thicker the rest
of the height can be done with a 170x170x45 mm board.
- Safety harness with approved anchor point must be used during montage of scaffolding. All personnel
shall be familiarized with the fall rescue procedure explained under section 11. Risk Inventory.
- Safety harness with approved anchor point must be used during montage of formwork and/or anytime
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 6 (17)

2. Metodbeskrivning / Methodology
Tillvägagångssätt, strategi eller teknik för att gå från startläge till slutläge (Approach, strategy, or technology to move from start to finish mode)
where an unprotected edge exists (i.e. valv form, edge beam etc).
- Top floor will be completely floored and railing put up where there is a risk of falling.
- Three crowns should be put to the correct height before wooden beams are placed, surveyor will assist with this.
- Construct formwork for bridge roadway arch including edgebeam, see sketches for dimensions.
- Formties cannot be but inside the edgebeam.
- ‘Flytbräda’ on the bottom inside of edgebeam form should be minimum 150 mm and have a small
inclination away from edgebeam, this to make it easier to cast and vibrate edgebeam but also to
prevent and gathering of water close to edgebeam.
- Under formwork a plastic will be placed to minimize cleaning of scaffolding.
- Lay reinforcement and make room for casting spots and concrete sampling.
- Before finishing reinforcement make sure that all pipes for cables have been installed including the
cut outs for lights
- Make sure reinforcement for consoles can be installed before putting up too much formwork.
- See sketch for formwork solution for consoles and follow dimensions from designer.
- Bolts on edgebeam and wings on top of bridge SHOULD have electrical contact with
reinforcement, this will be done through earthing and the railing.
- Part of bolts outside of concrete is taped to protect them from splash of concrete.
- Montage EKP according to model, OK to weld where EKP is placed in model.
- Montage cables for concrete computer according to “Temperaturspricksåtgärder”.
- Perform works required for earthing in superstructure.
- Inspection of loadbearing form support will be done by Skanska and third party inspector.
- Survey tolerance check including measuring spot for concrete sampling.

- Cast concrete
- Prior to casting a cast meeting will be held where detailed man power planning will be done. Sufficient plans will also be made for possible weather scenarios
INTERN INFORMATION

and for any problem that might occur during casting.


- Before casting a visual inspection will be done and checklist 1 will be finished and signed before casting.
- The client will be notified about castings in advance and be given a possibility for a joint inspection.
- For detailed planning regarding the casting a cast program will be developed.
- Concrete pump will be placed and installed according to ETS from Skanska Teknik.
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 7 (17)

2. Metodbeskrivning / Methodology
Tillvägagångssätt, strategi eller teknik för att gå från startläge till slutläge (Approach, strategy, or technology to move from start to finish mode)
- Cooling pipes and measurement of temperature will be started as casting begins.
- During casting checklist 2 will be controlled and filled out by Lambda.
- Surface will be machined with ‘helicopters’ with the use of steel plate, finished surface will be covered as soon as possible with plastic and if applicable some
water on top. If necessary sprinklers will be used to keep concrete from drying.
- Edgebeam will be troweled by hand with filterboard and covered with plastic.

- After casting
- Mount handrails & screens before striking working platforms.
- Start of striking form & form support after OK from Skanska supervision.
- Scaffolding is lowered in the top so that the formwork can be dismantled from the top level floor.
- After formwork have been dismantled concrete surfaces are inspected and fixed as necessary.
- Once surfaces are ok scaffolding is dismantled.
- Formwork for walls will be dismantled after the scaffolding is out on the inside and outside it can go along at the same time.
- When all formwork is done the rest of the structure is repaired where necessary before final inspection of the concrete works.

TO BE CONTINUED IN REVISION 2
• Retaining wall (under bridge) –Construct formwork (first side)
- fix reinforcement & cast-in’s
- perform works required for earthing
- construct formwork (second side)
- Survey tolerance check
- Cast concrete (need to order extra hose?)
- strike formwork
- Measure contact and mount railing
INTERN INFORMATION

-
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 8 (17)

3. Kritiska arbeten / Critical works


Ange alla kritiska aktiviteter avseende produktivitet, Kvalitet, Miljö, Arbetsmiljö mm .
(Enter all critical activities related to productivity, Quality, Environment, Work
environment, etc. .) Förebyggande åtgärder / Preventative & mitigation measures Ansvarig Klar till
Produktivitet / Productivity
1. Crane mob/demob, operation, and lifting operations: 1. Mob/demob according to manufacturers instructions
Equipment failure only. Crane operator and riggers must be trained &
Falling materials competent. All team members to be briefed on lift plans.
Loads to be slung according to industry standards. All
lifting equipment/plant to be certified, rated & inspected
regularly. Use tag lines where necessary. Positive
communication between rigger & operator at all times
(radio/signals). Don’t lift loads above site personnel.
Involve lifting coordinators for special lifts.

2. Installation and striking of formwork and form support: 2. Installation of form support must be in accordance with
Falling materials manufacturers instructions and temporary works design
Working at height drawings. Check equipment and do not use damaged
Manual handling items. Harness & fall restraint with approved anchor
Noise point must be used when not on a working platform.
Failure of temporary structure Avoid manual handling where possible by mechanical
means. Lift materials in a team to lighten the load per
person. Use good technique when lifting (bend at the
legs, do not twist). Know your lifting capacity - do not
exceed it. Wear ear protection, especially when striking.
Follow drawings for temp form support and use
specified materials only. Check temporary structure
before loading. Check concrete test strength results
before unloading & striking.
3. Installation of steel reinforcement & cast-in items:
Injuries from working with reinforcement 3. Protect ends of protruding rebar with caps. Follow
INTERN INFORMATION

Slips/trips/falls correct installation sequence and ensure reinforcement is


Manual handling injuries adequately fixed before moving on (especially important
for vertical bars). Only use approved equipment for
cutting rebar, by a trained/competent person, after
obtaining a hot works permit. Lift as a team where
possible. Keep fingers clear of potential crushing areas.
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 9 (17)

3. Kritiska arbeten / Critical works


Ange alla kritiska aktiviteter avseende produktivitet, Kvalitet, Miljö, Arbetsmiljö mm .
(Enter all critical activities related to productivity, Quality, Environment, Work
environment, etc. .) Förebyggande åtgärder / Preventative & mitigation measures Ansvarig Klar till
Good housekeeping (keep area tidy and free of loose
material lying around).

4. Perform works required for earthing: 4. Obtain hot works permit before starting. Only
Hot works trained/competent personnel to use equipment. Use
correct fire resistant PPE. Equipment shall be
checked/serviced regularly. Fire Extinguishers to be at
the workface ready for emergency use. Inspect/monitor
area for 1 hour after hot works complete.

5. Concrete works: 5. Prior inspection/approval of pump operating location.


Concrete pump set-up, ground bearing capacity GEO temporary works if required to increase foundation
Concrete leakage bearing capacity. Cooling pipes need to be installed with
Failure of temporary works Double clamps in connection points and leak test before
Concrete burns doubling. Follow IFC drawings only for temporary form
Leakage of cooling pipes support and use specified, undamaged materials only.
Check temporary structure against IFC drawings before
loading. Monitor during casting. Protective clothing
should be worn to protect skin against concrete burns.
Wash concrete off if splashed. Use barriers to protect
personnel from hazardous areas.

6. Material deliveries: 6. Inform delivery drivers where (and whom) to report to


Personnel not inducted by Skanska when they arrive. Inform delivery drivers of minimum
Delivery driver(s) not familiar with site PPE required on site. Site supervisors should brief
Unloading materials from truck drivers of any specific hazards to be aware of. Delivery
personnel are to be escorted by site inducted personnel.
Materials are to be unloaded by site crane and site
INTERN INFORMATION

personnel.

7. Ensure exclusion zones are well demarcated, fenced off


7. Interface with other trades: with barrier and all site personnel are familiar with
Working in close proximity to a live railway line exclusion zones.
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 10 (17)

3. Kritiska arbeten / Critical works


Ange alla kritiska aktiviteter avseende produktivitet, Kvalitet, Miljö, Arbetsmiljö mm .
(Enter all critical activities related to productivity, Quality, Environment, Work
environment, etc. .) Förebyggande åtgärder / Preventative & mitigation measures Ansvarig Klar till
Kvalitet / Quality
1. Incorrect/unapproved materials 1. Ensure the correct documentation when ordering
materials. Ensure materials are approved where required
by design. Obtain material data from supplier where
required (incl. CE marking, material certificate, data
sheet, manufacturers instructions, concrete mix design).

2. Risk of defects, deformation, deflection, damages 2. Survey tolerance checks before casting. Temperature
monitoring. Prepour inspections must be carried out by
UE & Skanska and checklists completed/approved
before casting. Casting operations to be in accordance
with “Krav Brobyggande, version 2.0” and “SS-
EN_13670_2009 Execution of Concrete Structures”.
Control rise rate, pour height, vibration. Ensure
temporary works are sufficient.

3. Traditional form 3. Only new materials to be used for ‘board form’ concrete
surfaces which are exposed and seen as final product.
Take care to ensure consistency in finish across project
entirety. Plywood form may be reused <5 times.
4. Winter castings
4. Planning based on temperature cracking measures.
Planning in casting schedule.

Miljö / Environment
1. Material useage & sustainability 1. Reuse materials where possible. Planning meetings to
identify opportunity to share material resources between
INTERN INFORMATION

different bridge locations. Keep material/equipment


schedule to help conserve and keep stock of available
material. Recycle materials after use where possible.

2. Oil Spills 2. Have spill kits readily available at each worksite.


Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 11 (17)

3. Kritiska arbeten / Critical works


Ange alla kritiska aktiviteter avseende produktivitet, Kvalitet, Miljö, Arbetsmiljö mm .
(Enter all critical activities related to productivity, Quality, Environment, Work
environment, etc. .) Förebyggande åtgärder / Preventative & mitigation measures Ansvarig Klar till
3. Concrete wasteage 3. Volume calculations shall be made carefully to avoid
eccessive wasteage from over ordering. Extra ‘fresh’
concrete should be returned to batching plant. Extra over
concrete which has been through the pump should be
tipped neatly on site for later removal by excavator.

4. Waterway contamination 4. Control water run-off from work site. Only pump out
water to approved locations.

5. Vehicles and machines are logged (fordonslista)

Arbetsmiljö / Working environment


1. Covid-19 1. Maintain social distancing. Use hand sanitizer. Keep
good personal hygene, wash hands regularly,
cough/sneeze in elbow (not in hands), stay home if
feeling unwell, notify supervisor if start to feel unwell at
work. Adhere to the reccommendations of the Swedish
health authority.

2. Housekeeping 2. Maintain a clean and tidy worksite area. Minimum score


of 3/5 is required from Skanskas inspection regime.

3. EMERGENCY PROCEDURE & CONTACT 3. All personnel on the project shall install the “SOS
NUMBERS Alarm” application on their mobile phone device. This
app is the preferred method of raising an emergency call.
If not working - For AMBULANCE call 112
INTERN INFORMATION

8. Kapaciteter och tider. / Capacities and times. Åtgärder för att säkerställa kapaciteterna. / Measures to ensure capacities Uppföljning. 7
Vad finns i kalkylen? Follow-up
Kapaciteter
Text Text
Text
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 12 (17)

Tider
Text Text Text

9. Material, Resurser och kompetens / Materials, Resources and Competence Mängd / Finns. Säkerställ att materialet finns tills momentet startar. Ansvarig Klart till
Förteckna material, maskiner,Utbildningar, YA och UE Amount Ja/Nej (Ensure the resource is available when the task begins).
Material
Formwork (Traditional)
Form support (Layher)
Working platform (Layher)
Steel reinforcing bar (loose bar, pre-bent, cages prefab’d)
Concrete (Sydsten)
Cast-in items (pipes, bolts, earthing items etc)
Chemicals (eg. Deseil, retarder, form oil, bitumen board etc)

Resourses
Crane supplier (Skanska Rental)
Crane operator (UE Concrete – Lambda)
Logistics Team (Skanska)
UE Form/rebar/concrete (Lambda)
UE Form support & working platform (Lambda)

Competence
Personnel requiring task specific education and competency:
- Crane Operator
- Rigger/banksman
- Hot works personnel (cutting, welding, etc)
- Machine/vehicle operators
- Site specific safety introduction
- Råd och skydd training (railway education)
INTERN INFORMATION

- Scaffolding education
- Personnel installing & inspecting Layher form support
- Personnel installing & inspecting working platform scaffold
- Personnel installing any load bearing temporary works of any kind
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 13 (17)

10. Kommunikation
Säkerställ att all berörd personal har full kännedom hur aktiviteten ska utföras (Ensure that all relevant personnel are fully aware of how to perform the activity).

Skanska will deliver Toolbox talks to communicate important safety information throughought the project duration.

Lambda take responsibility for translating the information in this document and assurance that their personnel understand the content.

Register of signatures

UE/arbetsledare to help deliver

11. Säkerhetsgenomgång
Inventera risker som kan vara aktuella vid arbetsmomentet. Bocka i rutan ”Ja” först efter att åtgärder från AMP hanterats i arbetsberedningen,
(Inventory risks that may be relevant at the time of the operation. Check the box "Yes" only after handling measures from AMP in the work preparation,)
Uppdatering
Riskinventering (Risk Inventory) Nej Ja Ytterligare åtgärder/Kommentarer (Additional Actions/Comments) AMP?

1. Arbete med risk för fall från högre höjd än två meter. ☐ ☒ Consrtuct & use working platform where risk is present. Use harness & fall ☐
Work with risk of falling from a height greater than two metres. restraint with approved anchor point when not on a working platform.
Rescue plan in the case where a person falls and is hanging by harness:
1. If the person can be safely reached from an adjacent working platform, they
can be lifted by hand by persons on to that platform. Those performing the rescue
should also be protected by wearing a harness if they need to reach/climb outside
of the platform.
2. If the person hangs out of reach, crane hook is lowered to the person who
connects himself by the harness to be lifted safely to the nearest working platform

2. Arbete som innebär risk att begravas under jordmassor eller sjunka ner i lös ☒ ☐ ☐
mark.
Work that involves the risk of being buried under soil or sinking into loose ground.

3. Arbete som kan medföra exponering för kemiska och biologiska ämnen. ☐ ☒ Protective clothing should be worn to protect skin against concrete burns. Wash ☐
Work likely to involve exposure to chemical and biological substances. concrete off if splashed. Before working with any chemical, check material data
sheet and follow manutacturers instructions for use & protective measures.
INTERN INFORMATION

4. Arbete som kan medföra exponering för joniserande strålning. ☒ ☐ ☐


Work that may result in exposure to ionizing radiation.

5. Arbete i närheten av högspänningsledning (samt övriga ledningar i mark). ☐ ☒ Site briefing to notify personnel of services to be aware of & avoid. Such services ☐
Work in the vicinity of a high-voltage line (as well as other lines in the ground). are to be demarcated with warning signs/barriers.

6. Arbete med risk för drunkning. ☒ ☐ ☐


Work with risk of drowning.
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 14 (17)

11. Säkerhetsgenomgång
Inventera risker som kan vara aktuella vid arbetsmomentet. Bocka i rutan ”Ja” först efter att åtgärder från AMP hanterats i arbetsberedningen,
(Inventory risks that may be relevant at the time of the operation. Check the box "Yes" only after handling measures from AMP in the work preparation,)
Uppdatering
Riskinventering (Risk Inventory) Nej Ja Ytterligare åtgärder/Kommentarer (Additional Actions/Comments) AMP?

7. Arbete i brunnar eller tunnlar samt anläggningsarbete under jord. ☒ ☐ ☐


Work in wells or tunnels or underground construction work.

8. Undervattensarbete med dykarutrustning. ☒ ☐ ☐


Underwater work with diving equipment.

9. Arbete i kassun under förhöjt lufttryck. ☒ ☐ ☐


Work in a caisson under elevated air pressure.

10. Arbete vid vilket sprängämnen används. ☒ ☐ ☐


Work involving the use of explosives.

11. Arbete vid vilket lansering, montering och nedmontering av tunga byggelement ☐ ☒ Avoid manual handling where possible to lift by mechanical means. Lift materials ☐
eller tunga formbyggnadselement ingår. in a team to lighten the load per person. Use good technique when lifting (bend at
Work involving the launch, assembly and dismantling of heavy building elements the legs, do not twist). Know your lifting capacity - do not exceed it.. Follow
or heavy formwork building elements. drawings for temporary form support, temporary structure must be checked by
Layher before loading.
12. Arbete på plats eller område med passerande fordonstrafik. ☐ ☒ Separate working area from trafficked areas with barriers & reduce traffic speed ☐
Work on site or area with passing vehicle traffic. with signage.

13. Rivning av bärande konstruktioner eller hälsofarliga material eller ämnen ☐ ☒ Removal of load bearing form support must be authorized by Skanska’s Work ☐
Demolition of load-bearing structures or hazardous materials or substances Supervisor, Project Engineer, or Block Manager.

14. Rörelse av maskiner och fordon ☐ ☒ Only trained personnel to operate machines and vehicles. Use a spotter (assistant ☐
Movement of machines and vehicles person) to help when reversing in a congested area.

15. Arbetsmaskiner (inkl utrustning) ☐ ☒ Only trained personnel to operate machines & equipment. ☐
Work machines (incl. Equipment)

16. Arbete med risk för kläm-, såg- och skärskador ☐ ☒ Only trained operatives to use powertools. Use guards on tools where there is a ☐
Work with risk of crushing, sawing and cutting injuries risk of cutting. Keep fingers clear of potential crushing areas. Good housekeeping
(keep area tidy and free of loose material lying around).
17. Arbete med temporära konstruktioner ☐ ☒ Drawing details and manufacturers instructions must be followed when installing ☐
Work with temporary constructions temporary works. Temporary structures must not be loaded without prior
inspection & approval from Layher’s representative and Skanska’s Work
Supervisor, Project Engineer, or Block Manager.
INTERN INFORMATION

18. Arbete med VA-system, FJV etc. ☒ ☐ ☐


Work with VA system, FJV etc.

19. Heta arbeten, brand- och explosionsskydd ☐ ☒ Obtain hot works permit before starting. Only trained/competent personnel to use ☐
Hot works, fire and explosion protection equipment. Use correct fire resistant PPE. Equipment shall be checked/serviced
regularly. Fire Extinguishers to be at the workface ready for emergency use.
Inspect/monitor area for 1 hour after hot works complete.
20. Risker för fall till samma nivå ☐ ☒ Keep worksite clean and tidy. Don’t leave unused materials lying around. Don’t ☐
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 15 (17)

11. Säkerhetsgenomgång
Inventera risker som kan vara aktuella vid arbetsmomentet. Bocka i rutan ”Ja” först efter att åtgärder från AMP hanterats i arbetsberedningen,
(Inventory risks that may be relevant at the time of the operation. Check the box "Yes" only after handling measures from AMP in the work preparation,)
Uppdatering
Riskinventering (Risk Inventory) Nej Ja Ytterligare åtgärder/Kommentarer (Additional Actions/Comments) AMP?
Risks of falls to the same level walk around congested areas while using a mobile phone.

21. Arbete med knackning av skut ☒ ☐ ☐


Work with blasting or hammering boulders

22. Arbete med ergonomiska risker ☐ ☒ Avoid manual handling where possible to lift by mechanical means. Lift materials ☐
Work with ergonomic risks in a team to lighten the load per person. Use good technique when lifting (bend at
the legs, do not twist). Know your lifting capacity - do not exceed it.
23. Arbete med exponering för buller ☐ ☒ Wear ear protection when using noisy equipment or striking formwork. Wear ear ☐
Work with exposure to noise protection when working near noisy equipment/activities. Tell people around you if
you plan to start using noisy equipment.
24. Arbete med exponering för vibrationer ☐ ☒ Rotate personnel using vibrating equipment to minimize exposure. ☐
Work with exposure to vibrations

25. Arbete i dammande miljö ☐ ☒ Always wear respiratory protection when working with / near dusty activities. ☐
Work in a dusty environment

26. Risker för tredje man i anslutning till arbetsplatsen ☐ ☒ Separate work area and restrict access from public with barriers & signage. ☐
Risks to third parties in connection with the workplace

27. Elektriska arbeten ☒ ☐ ☐


Electrical work

28. Arbete vid järnväg och spårbunden trafik ☐ ☒ Ensure exclusion zones are used, fenced off with barrier and all site personnel ☐
Work near railway tracks and rail traffic are familiar with exclusion zones.

29. Organisation (B AMP) ☒ ☐ ☐


Organization (B AMP)

30. Etableringsytor - Konflikt mellan transporter och oskyddade personer(Arbetare) ☐ ☒ Ensure positive communication between transporters and site personnel. ☐
Establishment areas - Interface between transport and unprotected persons Transporters should be accompanied by a site inducted person.
(Workers)

31. Tidplan-risk för försämrad arbetsmiljö på grund av kort byggtid och begränsade ☒ ☐ ☐
Tider för spåravstängning(tågstopp). (B AMP)
Risk of deterioration of work environment due to over-ambitious
program/capacities and/or limited times for track closure (train stop). (B AMP)
INTERN INFORMATION

32. Arbete med risk att utsättas för hot ☒ ☐ ☐


Work with a risk of being exposed to public threats

33. Projektspecifik risk ☒ ☐ ☐


Project specific risk
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 16 (17)

12. Signering
Följande produktionspersonal har tagit del av aktuell arbetsberedning
(The following production staff have read, understood and agree with this arbetsberedning)

13. Godkännande / Approval


PC (eller motsvarande, tex Blockchef) godkänner arbetsberedningen / PC (or equivalent, e.g. Block Manager) approves the work preparation
Signatur Datum
INTERN INFORMATION
Arbetsberedning med Säkerhetsgenomgång Väg o Anläggning Syd 17 (17)

Efter utfört arbete stängs upprättad arbetsberedning i syfte att vara en del av vår egenkontroll samt förbättra arbetet med arbetsberedningar.
Nedanstående rubriker diskuteras tillsammans med de som utfört arbetet och varit med att upprätta arbetsberedningen

After the work has been completed, the established work preparation is closed in order to be part of our own control and to improve the work with work preparations.
The following headings are discussed together with those who carried out the work and helped to establish the work preparation

14. Uppföljning, erfarenheter och övrigt. / Follow-up, experiences and other.


Lista de problem som stötts på under arbetsmomentet, erfarenheter vi bör sprida. / List the problems encountered during the work, experiences we should share.
INTERN INFORMATION