Quality Assurance Plan

Customer Name Date


Project Name Work Order No
Panel Name Panel Serial No

Testing
Parameter To Inspection or Test Inspection By
result
A) INCOMING
Panel fabrication check in terms of Measure Tape/Vernier calliper/Wire
dimensions,thickness as per submit drawings gauge
Powder coating by appearance visually and thickness
between 80‐110micron Powder coat micron meter
Switchgear and other electrical parts visually and
quantity in ref to PO,BOM Visually and Quantity
Visually dimensions check by vernier
Busbars in terms of current density as per amperes calliper and measure tape
B) IN PROCESS
Visually check as per drawings and
Assembly switchgear ratings
Visually check as per drawings and
Alignment switchgear ratings
C) FINAL INSPECTION
Power supply operation check Visually and multimeter
Electrical Factory type test on panels like operation
test,Insulation resistance test,Phase sequence Test Batch/Multimeter/HV
test,HV test,Functional test tester/Meggar
Comments description in brief to rectify (if any)

For, Advait Panels

OFFICE & FACTORY – 87, Gajanan‐3 Industrial Park, Kathwada‐Singarva Road,


Kathwada, Ahmedabad ‐ 382430
Mobile – +91 9427230910, Email ID – advaitpanels@gmail.com
Website: www.advaitpanels.com

You might also like