Task Jun Jul Aug

Project Proposal Meeting with PS, 1 Jun 2021


Confirm Project topic, 8 Jun 2021
Initial Report (TMA1) submission, 1 Jul 2021
Interim Report (TMA2) submission, 26 Jul 2021
Oral Presentation, 1 Sept 2021
Final Report submission, 4 October 2021
Oral Examination (if required), 22 November 2021
Aug Sep Oct Nov Dec
Commercial Project

Initiation Planning Execution

Erection Scaffolding
Evaluation Scope Statement

Project Team
Charter

Plan Schedule

Budget finishing /Touch up


painting
Execution Control Closeout

Erection Scaffolding
Resource Management Audit

Removing activities

Site cleanup
Installation Cost Management

finishing /Touch up Risk Management Document hand over


painting