20. In the first step of SAFe’s Continuous Delivery Pipeline, Product Owners and Managers
do what activity?
a. Ensure the architecture team has sufficient capacity
b. Hypothesize on what would create value to their Customers
c. Prioritize the backlog
d. Negotiate Supplier contracts to ensure projected capacity requirements are met
Quiz Q
21. When should innovation activities be conducted by teams on the Agile Release Train?
a. Throughout the Program Increment
b. Only when innovation Stories rise to the top of the backlog
c. At a consistent time each day during the Iteration
d. Only during the Innovation and Planning Iteration