Professional Documents
Culture Documents
Pro 626 XXXX
Pro 626 XXXX
Pro 626 XXXX
(Print Names)
MODE OF OPERATION
Shutdown Mode
The Asset must be de-energized and locked out.
The intent is to replace the complete drive assembly on Conveyor # 34.
SAFETY
Complete Work Order FLRA with Foreman.
If you are unsure of something or a particular task, ask your Foreman.
System must be locked out to complete work as required.
REFERENCE MATERIALS
LOTO Form – Asset 626 Conveyor 34
LOTO Form – Asset 625 Conveyor 33
TOOLS
Torque Wrench Screwdrivers Set, Wrench Set
2T Chain Slings (3EA), Shackles 3/4” to 1-1/8” Thin Wall Socket Set
5T Trolleys (2EA), 2T Come-alongs (2EA) 5T Nylon Slings
Laser Alignment Tool Dunnage
MATERIAL
INV15570 Isolation Pad 12EA - 7/8-9X2 NC GR8 HEX C/S PLTD + Nuts, Wshr, Lck.
INV10928 Bolts Kit Coupling Hydraulic Hoses HPU
INV10858 Drive Assembly
SCOPE
Replacement of Drive Assembly on Conveyor # 34.
PROCEDURE
Any brief preliminary instructions, if applicable
If any steps need to be edited, write the proposed changes on the procedure form so it can be revised.
If any item appears abnormal, contact your Foreman, and explain what you observed.
2. Job Procedure
Step Required Action Visual Aids / Additional Information
2. Job Procedure
Step Required Action Visual Aids / Additional Information
2. Job Procedure
Step Required Action Visual Aids / Additional Information
2.15 Now proceed with the base lifting and finally transfer
the load to the crane following same steps as done
with the motor and reducer. Drive Base weight is
1488 lbs.
2. Job Procedure
Step Required Action Visual Aids / Additional Information
2.17 Repeat steps 2.3 to 2.6 with the new drive assembly.
2.18 Lifting procedure for the new assembly starts with the
base. Secure the load to the crane and lift it up to the
transfer area. Secure the load to be transferred to the
5 Tons Trolleys by attaching the chain slings to the
new base, release the crane. Move the base to the
final position. Secure the base to the structure,
dunnage required to securely support the base.
2.19 Lift the new gear reducer; safely secure the new
reducer to the crane, and then crane to lift it up to the
transfer area. Receive the load with the 5 Tons
Trolleys by attaching the chain slings to each lifting
point in the reducer and transferring the load from
the crane, when is safe release the crane. Secure the
gear reducer to the base. Start assembling the new
coupling-brake system, dunnage required to support
the coupling-brake assembly.
2.20 Lift the new motor; secure the new motor to the
crane, after this, crane will take the motor to the
transfer area. Secure the motor for the lifting; crane
to lift it up to the transfer area. Once there attach the
motor to 5 Tons Trolleys using the chain slings. Safely
transfer the load to the trolleys and release the crane.
Now move the motor to its final position.
2. Job Procedure
Step Required Action Visual Aids / Additional Information
2. Job Procedure
Step Required Action Visual Aids / Additional Information
2.30 Document the startup process, including any issues
faced and actions taken.
NOTES
Trades Initials:
Annex 1
Annex 2
Annex 3
Annex 4
Revision: 1.0 Revision Date: October 24, 2023 Page 13 of 14
PRO-626-XXXX – Conveyor # 34 Drive Replacement