Boundry Wall & Main Gate Calculation Sheet

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 12

BAR BENDING SCHEDULE

Name of Work : Boundry wall


work
Name of Client : M/s RIL
Location : Suratgarh
Date : 14-04-2024

Sl.
Description SHAPE
No.

1 Footing Main bar(Top & Bottom) 0.25m 1.5m 0.25m

2 Footing Distribution bar(Top&Bottom) 0.25m 1.1m 0.25m

3 Column 0.3m 0.3m


2.45m
4 Column
0.6m 0.3m
2.45m
0.310m
5 Column Stribs 0.310m 0.310m
0.310m
6 Corners/Expansion column 0.425 0.425
2.45

0.6m 0.425
2.45m
0.425
6 Column Stribs 0.425 0.425
0.425
7 Plinth Beam 0.35 0.35
950m
0.35 0.35
950m
0.3m
Plinth beam Stribs 0.35m 0.35m
0.3m
AR BENDING SCHEDULE

TOTAL LENGTH
Total
footing/Column CUTTING NO. OF 8 MM
10 MM TOR 12 MM TOR
LENGTH(M) BAR TOR

436 2 24 20928

436 1.6 14 9766

403 3.05 2 2458.3

403 3.05 2 2458.3

403 1.288 14 7266.896

33 3.3 3 326.7

33 3.48 3 344.025

33 1.7 14 23.8

950.7 4 3802.8

950.7 2 1901.4

1.28 6335.0 8108.8


Total Length : 15399.496 32596 9390.125
Unit Wt. ( Kg/m ) : 0.395 0.617 0.889
Total Wt. In Kg. : 6082.80092 20111.6086 8346.78
Grand Total(Kgs) 34541.19
Total Wt. In Ton 34.54
BAR BENDING SCHEDULE
Name of Work : Main gate

Name of Client : M/s RIL

Location : Suratgarh

Sl.
Description SHAPE
No.

1 Footing F1 Main bar(Top & Bottom) 0.35m 2.9m 0.35m

2 Footing F1 Main bar(Top & Bottom) 0.35 1.9m 0.35

1 Footing F2 Main bar(Top & Bottom) 0.35m 2.9m 0.35m

2 Footing F2 Main bar(Top & Bottom) 0.35 3.7m 0.35

3 Padestal 0.35 0.35


4.2
0.36

6 Stribs(outer) 0.36 0.36

0.36
0.25

7 Stribs(inner) 0.25 0.25

0.25m
8 Hook 0.05m 0.05m
0.35m
BENDING SCHEDULE

TOTAL LENGTH
Total
footing/Column CUTTING NO. OF 8 MM 10 MM 12 MM
LENGTH(M) BAR TOR TOR TOR
2 3.6 21 151.2

2 2.6 15 78

1 3.65 21 76.65

1 4.4 15 66

12 4.9 14 823.2

12 1.7 29 591.6

12 1.48 29 515.04

12 0.45 29 156.6

Total Length : 1263.24 0 1195.05


Unit Wt. ( Kg/m ) : 0.395 0.617 0.889
Total Wt. In Kg. : 498.9798 0 1062.27
Grand Tota(Kgs) 1561.25
Total Wt. In Ton 1.56
Concrete Qty calculation Sheet
Name of Work : Boundry wall work
Name of Client : M/s RIL
Name of Work : Boundry wall work
Location : Suratgarh
Boundry wall work
No of Footing
Sl. /Cloumn
Description Size
No.
L(M)
1 Excavtion 490 1.8
2 PCC 490 1.8
3 RCC
a Footing 490 1.6
b Column 470 0.35
c Expansion Joint Column 20 0.35
d Plinth beam 1030

4 Brick work 435 1.75


Main gate
1 Excavtion 2 3
1 3
2 PCC(Footing) 2 3
1 3

3 RCC(Footing) 2 3
1 3
4 Padestal 12 4.5
Plinth beam 6 2.25
1 3.11

Total Qty PCC(M3)


Total Qty RCC(M3)
Total Qty Brick Qty(M3)
et

Size Total QTY(M3)


W(M) D/H(M)
1.4 2.19 2704.21
1.4 0.1 123.48

1.2 0.3 282.24


0.35 2.25 129.54
0.475 2.25 7.48
0.4 0.35 144.20
Total 686.94
0.35 0.35 186.50

2 2.19 26.28
3.8 2.19 24.966
2 0.1 1.2
3.8 0.1 1.14
Total 2.34
2 0.4 4.8
3.8 0.4 4.56
0.4 0.4 8.64
0.23 0.23 0.71415
0.23 0.23 0.164519
Total 18.88

125.82
705.82
186.50
Construction Schedule Template
Project Name: Main gate and Boundry wall work Strart Date:21-04-2024
Location : Suratgarh Rajsthan End Date:05-07-2024
TASK DESCRIPTION STATUS START DATE
Planning Not Started 4/21/2024
Raw Material Supply Not Started 4/21/2024
Excavation In Progress 4/10/2024
PCC Not Started 4/24/2024
Reinforcement steel fixing Not Started 4/25/2024
RCC Not Started 4/26/2024
Brick work Not Started 5/1/2024
Pre-cast column fixing Not Started 5/1/2024
Pre-cast plank fixing Not Started 5/11/2024
Structural steel Not Started 5/20/2024
concerita fixing Not Started 5/26/2024
rt Date:21-04-2024
Total Duration: 75 Days
Date:05-07-2024
END DATE DURATION COMMENTS
7/5/2024 75
5/15/2024 24
5/20/2024 40
5/24/2024 30
5/30/2024 35
6/10/2024 45
5/31/2024 30
6/20/2024 50
6/25/2024 45
6/24/2024 35
7/1/2024 36
Construction Schedule Template
Project Name: Main gate Start date : 20-04-2024
Total Duration: 30 Days
Location : Suratgarh Rajsthan End date : 20-07-2024
TASK DESCRIPTION STATUS START DATE END DATE
Planning Not Started 4/20/2024 5/20/2024
Raw Material Supply Not Started 4/21/2024 5/8/2024
Excavation In Progress 4/10/2024 4/24/2024
PCC Not Started 4/23/2024 4/25/2024
Reinforcement steel fixing Not Started 4/25/2024 4/30/2024
RCC Not Started 4/26/2024 5/5/2024
Brick work Not Started 5/5/2024 6/5/2024
Structural steel Not Started 5/5/2024 5/20/2024
Total Duration: 30 Days
DURATION COMMENTS
30
17
14 60 % Done
2
5
9
31
15