Boundry Wall & Main Gate Calculation Sheet
Boundry Wall & Main Gate Calculation Sheet
Boundry Wall & Main Gate Calculation Sheet
Sl.
Description SHAPE
No.
0.6m 0.425
2.45m
0.425
6 Column Stribs 0.425 0.425
0.425
7 Plinth Beam 0.35 0.35
950m
0.35 0.35
950m
0.3m
Plinth beam Stribs 0.35m 0.35m
0.3m
AR BENDING SCHEDULE
TOTAL LENGTH
Total
footing/Column CUTTING NO. OF 8 MM
10 MM TOR 12 MM TOR
LENGTH(M) BAR TOR
436 2 24 20928
33 3.3 3 326.7
33 3.48 3 344.025
33 1.7 14 23.8
950.7 4 3802.8
950.7 2 1901.4
Location : Suratgarh
Sl.
Description SHAPE
No.
0.36
0.25
0.25m
8 Hook 0.05m 0.05m
0.35m
BENDING SCHEDULE
TOTAL LENGTH
Total
footing/Column CUTTING NO. OF 8 MM 10 MM 12 MM
LENGTH(M) BAR TOR TOR TOR
2 3.6 21 151.2
2 2.6 15 78
1 3.65 21 76.65
1 4.4 15 66
12 4.9 14 823.2
12 1.7 29 591.6
12 1.48 29 515.04
12 0.45 29 156.6
3 RCC(Footing) 2 3
1 3
4 Padestal 12 4.5
Plinth beam 6 2.25
1 3.11
2 2.19 26.28
3.8 2.19 24.966
2 0.1 1.2
3.8 0.1 1.14
Total 2.34
2 0.4 4.8
3.8 0.4 4.56
0.4 0.4 8.64
0.23 0.23 0.71415
0.23 0.23 0.164519
Total 18.88
125.82
705.82
186.50
Construction Schedule Template
Project Name: Main gate and Boundry wall work Strart Date:21-04-2024
Location : Suratgarh Rajsthan End Date:05-07-2024
TASK DESCRIPTION STATUS START DATE
Planning Not Started 4/21/2024
Raw Material Supply Not Started 4/21/2024
Excavation In Progress 4/10/2024
PCC Not Started 4/24/2024
Reinforcement steel fixing Not Started 4/25/2024
RCC Not Started 4/26/2024
Brick work Not Started 5/1/2024
Pre-cast column fixing Not Started 5/1/2024
Pre-cast plank fixing Not Started 5/11/2024
Structural steel Not Started 5/20/2024
concerita fixing Not Started 5/26/2024
rt Date:21-04-2024
Total Duration: 75 Days
Date:05-07-2024
END DATE DURATION COMMENTS
7/5/2024 75
5/15/2024 24
5/20/2024 40
5/24/2024 30
5/30/2024 35
6/10/2024 45
5/31/2024 30
6/20/2024 50
6/25/2024 45
6/24/2024 35
7/1/2024 36
Construction Schedule Template
Project Name: Main gate Start date : 20-04-2024
Total Duration: 30 Days
Location : Suratgarh Rajsthan End date : 20-07-2024
TASK DESCRIPTION STATUS START DATE END DATE
Planning Not Started 4/20/2024 5/20/2024
Raw Material Supply Not Started 4/21/2024 5/8/2024
Excavation In Progress 4/10/2024 4/24/2024
PCC Not Started 4/23/2024 4/25/2024
Reinforcement steel fixing Not Started 4/25/2024 4/30/2024
RCC Not Started 4/26/2024 5/5/2024
Brick work Not Started 5/5/2024 6/5/2024
Structural steel Not Started 5/5/2024 5/20/2024
Total Duration: 30 Days
DURATION COMMENTS
30
17
14 60 % Done
2
5
9
31
15