Method of Statement For Backfilling Works
Method of Statement For Backfilling Works
• Client : Al Wasl
2. Scope: This method statement covers the backfilling activities for Al Qusais
Residential Development at Plot No. 232-499. It includes the backfilling of trenches,
foundation excavations, and any other designated areas as per the project requirements.
3. Responsibilities:
5. Procedure:
• The area where backfilling to be started, to be cleaned well, accessible and safe.
• Ensure that the area to be backfilled is marked to appear the layer of backfilling.
• Conduct a pre-start safety briefing with the backfilling team.
• Ensure that the area to be backfilled is inspected and approved for backfilling.
• Place warning signs and barricades to secure the backfilled area.
• Ensure that damp-proofing, water proofing and perimeter insulation are
completed in construction below finish grading.
• Remove all concrete form work, trash and debris
“5.2 Backfilling Process:
• Place and compact backfill material in layers (25mm thick) to required elevations
as follows :
- Under footing and foundation, use engineered fill
- Under building slabs, use engineered fill.
- Under Steps and ramps, use Engineered fill.
- Under Walks and pavements, use satisfactory soil material
- Under grass and planted areas, use satisfactory soil material.
• Grade and level the backfilled area to match the surrounding terrain or as per
project specifications.
5.6 Inspection:
• Ensure that the compaction test drove where required according to the specs for
each layer
• Ensure that the compaction test test results comply with specifications and
project requirements
• Ensure that the compaction test results submitted to the consultant.
• Conduct a final inspection to ensure the backfilled area meets project
requirements.
6. Records: