Professional Documents
Culture Documents
All A0a 00 000 HST 0051
All A0a 00 000 HST 0051
All A0a 00 000 HST 0051
REVISIONS APPROVALS
REVISION CONTROL SHEET
4. REFERENCES .............................................................................................................................. 11
5. DEFINITIONS .............................................................................................................................. 11
6. ACRONYMS................................................................................................................................ 12
1. PURPOSE
The purpose of this document is to define the ConocoPhillips Canada (CPC) HSE (Health, Safety &
Environment) risk management requirements, in compliance with ConocoPhillips corporate HSE Risk
Matrix Standard, Section 7 - Risk Management Requirements and HSE Management System Standard,
Section 2.2 - Risk Assessment and Management.
2. SCOPE
The scope of this document includes HSE risk assessment(s) where CPC has operational control. This
includes:
All company activities and assets within Canada from inception through to decommissioning,
abandonment, remediation, and reclamation as applicable.
In instances where the company is precluded or cannot directly apply risk assessments (e.g. non-
operator); it will strive to influence those operations where practicable.
Specifically excluded from the scope are:
• Business Continuity and Emergency Response: addressed separately in the HSE
Management System Standard under section 3.4 Crisis Management and Emergency
Response (CM&ER).
• Sustainable Development risk management: governed by the corporate Sustainable
Development Risk Management Standard.
• Due Diligence risk management: governed by the corporate HSE & Social Issues Due
Diligence Standard.
• Industrial Hygiene exposure assessments: governed by the corporate Occupational Health
Standard.
• Project Risk Management: governed by the corporate Capital Projects Management System
– Project Management Standard (CPMS-PMT-MS-002) and the CPC Risk Management
Procedure (ALL-A0A-00-000-KPR-0001).
• Decision and risk analysis principles applied to exploration, reserves and associated
economic analysis.
• CPC Enterprise Risk Management.
3. HSE RISK MANAGEMENT REQUIREMENTS
Assess Risk
Determine the consequence, likelihood and risk rank as described in ConocoPhillips
corporate HSE Risk Matrix Standard, Sections 4, 5, 6
Approver’s Decision
Approver makes the decision to accept or not accept risk. Depending on the process
being utilized, there are various ways this can occur such as:
• Acceptance of PHA risks during PHA or at post-PHA risk acceptance meeting
• Verification of incident report
• Verification of incident ranking within Intelex
• Risk Assessment meeting or discussion
General Requirements
1. If the team/group is not using a tool which documents the approval of the risk assessment,
the CPC Risk Acceptance form ALL-A0A-00-000-HFR-0043 shall be used.
2. High and significant risks approved by a Delegate of Authority (DOA) require approval by
approver position upon their return to duty.
3. Some procedures exist that outline how certain risk-based activities are approved based on
a different qualifier than Table 1 (eg. Bypassing Safety Devices, Temporary Hose
Management, Permit to Work). This is acceptable.
Notes:
• Approval should be obtained at lower management levels before a risk can be
submitted for acceptance at the required level.
• An inform to the next approval level should be considered.
3.4 Timelines for Risk Approval
It is imperative that upon completion of a risk assessment, the risk is brought forward in
a timely manner for risk approval and subsequent implementation of necessary
mitigations. Table 2, Risk Assessment Timelines to Approval, outlines the required
timeline for risk approval for those risks that are most impactful to CPC. An
acknowledged inform to the risk approver must be done promptly, with approval to
follow when the risk assessment details can be discussed.
Lower-level risks not detailed in Table 2 should also be communicated and approved in a
manner commensurate with the risk implications.
Table 2: Risk Assessment Timelines to Approval
1. Identified significant and high risks shall have interim measures assigned when risks
cannot be immediately mitigated to an acceptable level.
Note: Un-resolved risks shall be revalidated after 12 months or on an annual basis.
3.6 HSE Risk Register Requirements
• HSE owns the HSE Risk Register
• Significant and high HSE risks, as determined through the HSE Risk Management
process, are forwarded to the Human Performance HSE Coordinator for inclusion in
the HSE Risk Register.
• The HSE Risk Register includes significant and high HSE risks as defined in CPC HSE
Management System Standard, ALL-A0A-00-000-HST-0022, element 2.
• HSE Risk Register is presented annually to the Senior Leadership Team, including
review of mitigations.
4. REFERENCES
# Reference
1 ConocoPhillips corporate HSE Management System Standard, Rev5.0
5. DEFINITIONS
Term Definition
HSE risks are defined by CPC as the negative effects of uncertain events on CPC’s
health, safety, and environmental objectives1.
HSE Risks In addition to HSE impacts, HSE risks often negatively affect other performance
objectives such as financials (e.g. clean-up costs, production downtime and/or
material damage), reputation and public perception, and regulatory compliance.
Tolerable Risk Considers the cost and benefits of action/inaction. This requires that effective
safeguards that could be implemented without undue cost or risk are
implemented.
[1]
Adapted from ISO Guide 73 – Definition of risk: “effect of uncertainty on objectives.”
6. ACRONYMS
RR Risk Rank
VP Vice President