Download as pdf or txt
Download as pdf or txt
You are on page 1of 10

Tremie concreting

 The most satisfactory method of placing


concret under water is by the use of tremie
pipe.
 The word tremie is derived from the French
word hopper.
Tremie method

 A tremie is a watertight pipe.

 Generally 250mm in dia.

 Funnel shaped hopper at its upper


end and a loose plug at the bottom.
 It is supported on a working
platform above water level.
Method of tremie concreting

 A tremie pipe of 200mm to 250mm diameter is used. The length of pipe


can be easily increased or deceased by using coupling. A funnel is provide
at the top end of pipe to facilitate pouring of concrete. The bottom end is
closed with a plug or thick polyethylene sheet to prevent entry of water
into the pipe.
 The pipe is lowered and made to rest at the point where the concrete is
going to be placed. The concrete having a very high slump of about 15 to
20 cm is poured into the funnel. When the whole length of pipe is filled up
with the concrete. The tremie pipe is lifted up and a slight jerk the plug is
forced out and the concrete gets discharged.
 After concreting has started the lower end of the tremie should be kept as
deeply submerged in the previously placed concrete to prevent entry of water
into the pipe from bottom end.
 The tremie should be lifted slowly to prermit the concrete to flow out, care
being taken not to loose the seal at the bottom. In this way, concrete work is
progressed without stopping till the concrete level comes above the water
level.
Precautions to be taken during
concreting by tremie method
 Cofferdams or forms should be sufficiently tight to reduce the flow of
water to less than 3m per minute through the space to be concreted.
 All the time, the lower end of the tremie pipe should be kept well
embedded in the wet concrete.
 Once concreting has started the tremie should not be moved laterally
through the deposited concrete as this will again disturb the concrete. If it
is necessary to shift the tremie. It should be lifted out and moved to the
new position.
 Pumping of water should not be allowed whilst concrete is being placed, nor
24hr thereafter. If simultaneous pumping is done it may suck the cement
particles.
 Under water concreting need not be compacted. As concrete gets
automatically compacted by the hydrostatic pressure of water.
 High water ratio is required for high consistency which reduces the strength
of concrete. But at present with the use of super plasticizers it is possible to
place a concrete with as low a water ratio as 0.3.
 When large quantities of concrete are required to be placed over an extensive
area it is advisable to use a number of tremies.
Thank you

You might also like