TIME SCHEDULE - SLIDE HOUSE

BULAN 1 BULAN 2 BULAN 3 BULAN 4 BULAN 5 BULAN 6 BULAN 7 BULAN 8 BULAN 9 BULAN 10 BULAN 11 BULAN 12 BULAN 13 BULAN 14 BULAN 15 BULAN 16 BULAN 17 BULAN 18 BULAN 19 BULAN 20 BULAN 21 BULAN 22 BULAN 23 BULAN 24
No. Item Jml Hari
1 2 3 4 1 2 3 4 1 2 4 5 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
HOTEL & Resto
1. Borepile
- Reinforcing Iron 7 Hari
- Formworking 5 Hari
- Concrete K-250 15 Hari
2. Footing Pilecap
- Soil Excavating (Manual) 14,9 Hari
- Reinforcing Iron 5,9 Hari
- Formworking Batako 11,3 Hari
- Formworking Multiplex 3,0 Hari
- Concrete K-250 (Manual) 25,8 Hari
3. Sloof D13 - Ø 8 -15
- Reinforcement 15,0 Hari
- Formworking 9,0 Hari
- Concrete K-200 (Manual) 4,8 Hari
4. Floor Plate (Ground Floor)
- Wiremesh M8 (2 Layer) 5,7 Hari
- Formworking 3,0 Hari
- Concrete K-200 (Manual) 36,0 Hari
5. Column D13 - Ø 8 -15 Ground Floor
- Reinforcement 15,0 Hari
- Formworking 7,0 Hari
- Concrete K-200 (Manual) 1,3 Hari
6. Beam D13 - Ø 8 -10
- Reinforcement 15,0 Hari
- Formworking 7,0 Hari
- Concrete K-200 (Manual) 4,8 Hari
7. Floor Plate (First Floor)
- Bonedeck 3,0 Hari
- Wiremesh M6 (1 Layer) 3,0 Hari
- Formworking 7,0 Hari
- Concrete K-200 (Manual) 16,4 Hari
8. Column D13 - Ø 8 -15 First Floor
- Reinforcement 15,0 Hari
- Formworking 7,0 Hari
- Concrete K-200 (Manual) 1,3 Hari
9. Beam D13 - Ø 8 -10
- Reinforcement 15,0 Hari I
- Formworking 7,0 Hari N
- Concrete K-200 (Manual) 4,8 Hari
10. Stairs Structure T
- Reinforcement 3,0 Hari E
- Formworking 3,0 Hari
- concrete K-200 (Manual) 15,0 Hari R
11. Roof Structure I
- Reinforcing 13,6 Hari
- Installation Alderon 13,6 Hari O
12. Wall Bricks R
- Installation wall (Ecoblock) 23,6 Hari
- Rough Plaster 31,5 Hari
- Smooth Plaster 31,5 Hari
13. Pipe Installation
14. Cables Installation
180 Hari
- Outdoor Cable
- Indoor Cable
15. Ceiling Installation 12,6 Hari
16. Floor Finish
- Rough Plaster 27,4 Hari
- Ceramic Tile 27,4 Hari
- Stone 27,4 Hari
17. Painting
- Wall Painting 31,5 Hari
- Ceiling Painting 31,5 Hari
18. Door and Window Installation 60,0 Hari
19. Alderon Canopy Installation 20,0 Hari
20. Accessories Installation 20 Hari
21. Parking Area
- Paving Block 26,6 Hari
22. Slide Structure
- Concrete 20 Hari
- Smooth Plaster 15,6 Hari
23. Swimming Pool
- Rough Plaster 9,8 Hari
- Smooth Render 9,8 Hari
- Pebblewash
24. Fence Hari
- Reinforcement 7 Hari
- Formworking 7 Hari
- Concrete 7 Hari
- Batako 25 Hari
- Install Kalsi Plank 14 Hari
- Painting 14 Hari
25. Yard Garden
- Additional Soil 5,3 Hari
- Additional Grasses 5,3 Hari

NOTE :
1. Jadwal tidak mengikat
2. Waktu bisa berubah tergantung ketersediaan material
3. Waktu bisa berubah tergantung faktor cuaca dan bencana alam lainnya