Document Number : PRE/PDS/D26D/ADM/23-007

PRODUCT DEVELOPMENT SCHEDULE


Issue & Revision Number : 01.00
Prepared Date : 10 APRIL 2023
Page : Of
PROJECT NUMBER : 23-ADM/PLS-D26D/06 PART NAME : CLAMP, HEATER
PROJECT NAME : D26D PART NO. : 87124-BZ180, 87124-BZ190

Year 2023 2024


Month MARET APRIL MEI JUNI JULY AGUSTUS SEPTEMBER OKTOBER NOVEMBER DESEMBER JANUARI FEBRUARI MARET APRIL MEI JUNI
Week and Date W.9 W.10 W.11 W.12 W.13 W.14 W.15 W.16 W.17 W.18 W.19 W.20 W.21 W.22 W.23 W.24 W.25 W.26 W.27 W.28 W.29 W.30 W.31 W.32 W.33 W.34 W.35 W.36 W.37 W.38 W.39 W.40 W.41 W.42 W.43 W.44 W45 W46 W47 W48 W49 W50 W51 W52 W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26

27-3 6-10 13-17 20-24 27-31 3-7 10-14 17-21 24-28 1-5 8-12 15-19 22-26 29-2 5-9 12-16 19-23 26-30 3-7 10-14 17-21 24-28 31-4 7-11 14-18 21-25 28-1 4-8 11-15 18-22 25-29 2-6 9-13 16-20 23-27 30-3 6-10 13-17 20-24 27-1 4-8 11-15 18-22 25-29 1-5 8-12 15-19 22-26 29-2 5-9 12-16 19-23 26-1 4-8 11-15 18-22 25-29 1-5 8-12 15-19 22-26 29-3 6-10 13-7 20-24 27-31 3-7 10-14 17-21 24-28

KS WTA PRE-PP PP SVP → W1


PROJECT MILESTONE Firs Delivery

DESIGN
T0.2
DESIGN TOOL MANUFACTURING
19/06 LINE
DESIGN T0.1 T1.2 T1.3 T2.1 T2.2 T2.3 T3.1 T3.2 T3.3 LVPT HVPT SVP → W3
DWA EVENT T1.1
18/04 12/07 24/07 07/08 21/08 25/08 20/11 22/01 18/04 15/04 29/04
14/06
CAD DATA PREPARATION 23/06

13/04
Project Name : D26D Ornament Wheel Hub Duration Plan : 970 Days Actual : 33 days
T Start
Enter Project
the name 27-Feb-23
of the Project Lead in cell B3. Enter: the Project Start date in cell E3. Pooject Start: label is in cell C3.
h Week
C : 1 2/27 3/6 3/13 3/20 3/27 4/3 4/10 4/17 4/24 5/1 5/8 5/15 5/22 5/29 6/5 6/12 6/19 6/26 7/3 7/10 7/17 7/24 7/31 8/7 8/14 8/21 8/28 9/4 9/11 9/18 9/25 10/2 10/9 #### #### 10/30 11/6 #### #### #### 12/4 #### #### 12/25 1/1 1/8 1/15 1/22 1/29 2/5 2/12 2/19 2/26 3/4 3/11 3/18 3/25 4/1 4/8 4/15 4/22 4/29 5/6 5/13 5/20 5/27 6/3 6/10 6/17 6/24
el # # # 30
T
hi M

T W T F S S M T W T F S S M T W T F S S M
T W
T F S S M T W T
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

NO ACTIVITY PIC START END DAYS


Do not delete this row. This row is hidden to preserve a formula that is used to highlight the curren day within the project schedule.

START PROJECT #REF! 30-Mar-23 17-Apr-24 275


C
el PRODUCT PLANNING SECT.
C
el 0% 30-Mar-23 30-Mar-23 1 PLAN
C 1 RECEIVED APQP YTO
el 100% 30-Mar-23 30-Mar-23 1 ACT
C
el PRODUCT DEVELOPMENT 6-Apr-23 11-Apr-23 5 PLAN
C 2 YTO
el
SCHEDULE (PDS) 0% 1 ACT
0% 27-Apr-23 28-Apr-23 2 PLAN
3 PBOM START TOOLING YTO
0% 1 ACT
0% 12-Apr-23 17-Apr-24 319 PLAN
4 MONITORING PDS YTO
0% 1 ACT

LOGSHEET DOC. APQP 12-Apr-23 17-Apr-24 319 PLAN


5 YTO
PROJECT ACT
C
el PRODUCT DESIGN SECT.
C
el 0% 10-Apr-23 10-Apr-23 1 PLAN
C 1 DESIGN INPUT AAN
el 100% 1 ACT
C
el 6-Apr-23 17-Apr-23 10 PLAN
C 2 DFMEA RPU+AAN
el 0% 1 ACT
0% 6-Apr-23 18-Apr-23 11 PLAN
3 3D DESIGN MAKING RPU+AAN
0% 1 ACT
0% 6-Apr-23 17-Apr-23 10 PLAN
4 DESIGN REVIEW RPU+AAN
0% 1 ACT
13-Apr-23 17-Apr-23 4 PLAN
5 2D DRAWING AAN
1 ACT
6-Apr-23 17-Apr-23 10 PLAN
6 SPC RPU+AAN
1 ACT
13-Apr-23 13-Apr-23 1 PLAN
7 PART LIST AAN
1 ACT
17-Apr-23 17-Apr-23 1 PLAN
8 DESIGN VERIFICATION AAN
1 ACT
27-Apr-23 28-Apr-23 2 PLAN
9 DESIGN VALIDASI AAN
1 ACT
18-Apr-23 18-Apr-23 1 PLAN
10 DRN GO TOOLING AAN
1 ACT
C
el MATARIAL CAPABILITY EVALUATION SECT.
C
el ESTIMASI MATERIAL 0% 1-May-23 3-May-23 3 PLAN
1 FSA
TRIAL 1 ACT
3-May-23 17-May-23 13 PLAN
2 CER + PO MATERIAL FSA
1 ACT

ORDER MATERIAL & 18-May-23 9-Jun-23 20 PLAN


3 FSA
COMPONENT 1 ACT
MATERIAL & 9-Jun-23 12-Apr-
9-Jun-23 11
1 PLAN
4 COMPONENT FSA
PREPARATION FOR TRIAL 1 ACT

VERIFIKASI MATERIAL 14-Jun-23 17-Apr-


14-Jun-23 11
1 PLAN
5 FSA
AKTUAL TRIAL 1 ACT
PBOM (PRELIMINERY T0 T1 T2 T3 PRE-PP
27-Jun-23 28-Mar-
27-Jun-23 51 PLAN
6 BILL OF MATERIAL) [T0, FSA
T1, T2] 1 ACT
17-Apr-24 26-Apr-24 9 PLAN
7 BOM (BILL OF MATERIAL) FSA
1 ACT
Document Number : PRE/PDS/D26D/ADM/23-007

PRODUCT DEVELOPMENT SCHEDULE


Issue & Revision Number : 01.00
Prepared Date : 10 APRIL 2023
Page : Of
PROJECT NUMBER : 23-ADM/PLS-D26D/06 PART NAME : CLAMP, HEATER
PROJECT NAME : D26D PART NO. : 87124-BZ180, 87124-BZ190

Year 2023 2024


Month MARET APRIL MEI JUNI JULY AGUSTUS SEPTEMBER OKTOBER NOVEMBER DESEMBER JANUARI FEBRUARI MARET APRIL MEI JUNI
Week and Date W.9 W.10 W.11 W.12 W.13 W.14 W.15 W.16 W.17 W.18 W.19 W.20 W.21 W.22 W.23 W.24 W.25 W.26 W.27 W.28 W.29 W.30 W.31 W.32 W.33 W.34 W.35 W.36 W.37 W.38 W.39 W.40 W.41 W.42 W.43 W.44 W45 W46 W47 W48 W49 W50 W51 W52 W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26

27-3 6-10 13-17 20-24 27-31 3-7 10-14 17-21 24-28 1-5 8-12 15-19 22-26 29-2 5-9 12-16 19-23 26-30 3-7 10-14 17-21 24-28 31-4 7-11 14-18 21-25 28-1 4-8 11-15 18-22 25-29 2-6 9-13 16-20 23-27 30-3 6-10 13-17 20-24 27-1 4-8 11-15 18-22 25-29 1-5 8-12 15-19 22-26 29-2 5-9 12-16 19-23 26-1 4-8 11-15 18-22 25-29 1-5 8-12 15-19 22-26 29-3 6-10 13-7 20-24 27-31 3-7 10-14 17-21 24-28

KS WTA PRE-PP PP SVP → W1


PROJECT MILESTONE Firs Delivery

DESIGN
T0.2
DESIGN TOOL MANUFACTURING
19/06 LINE
DESIGN T0.1 T1.2 T1.3 T2.1 T2.2 T2.3 T3.1 T3.2 T3.3 LVPT HVPT SVP → W3
DWA EVENT T1.1
18/04 12/07 24/07 07/08 21/08 25/08 20/11 22/01 18/04 15/04 29/04
14/06
CAD DATA PREPARATION 23/06

13/04
Project Name : D26D Ornament Wheel Hub Duration Plan : 970 Days Actual : 33 days
T Start
Enter Project
the name 27-Feb-23
of the Project Lead in cell B3. Enter: the Project Start date in cell E3. Pooject Start: label is in cell C3.
h Week
C : 1 2/27 3/6 3/13 3/20 3/27 4/3 4/10 4/17 4/24 5/1 5/8 5/15 5/22 5/29 6/5 6/12 6/19 6/26 7/3 7/10 7/17 7/24 7/31 8/7 8/14 8/21 8/28 9/4 9/11 9/18 9/25 10/2 10/9 #### #### 10/30 11/6 #### #### #### 12/4 #### #### 12/25 1/1 1/8 1/15 1/22 1/29 2/5 2/12 2/19 2/26 3/4 3/11 3/18 3/25 4/1 4/8 4/15 4/22 4/29 5/6 5/13 5/20 5/27 6/3 6/10 6/17 6/24
el # # # 30
T
hi M

T W T F S S M T W T F S S M T W T F S S M
T W
T F S S M T W T
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

NO ACTIVITY PIC START END DAYS


Do not delete this row. This row is hidden to preserve a formula that is used to highlight the curren day within the project schedule.

START PROJECT #REF! 30-Mar-23 17-Apr-24 275

TESTING MATERIAL 30-Jun-23 15-Sep-23 67 PLAN


8 FSA
PRODUCT 1 ACT
30-Jun-23 14-Jul-23 13 PLAN
8.a CER + PO TESTING HFD
1 ACT
14-Jul-23 1-Sep-23 43 PLAN
8.b TESTING PRODUCT HFD
1 ACT
4-Sep-23 15-Sep-23 11 PLAN
8.c REPORT TESTING HFD
1 ACT
C
el PACKAGING DEVELOPMENT SECT. DESIGN DESIGN MASSPRO
C
el 0% 1-May-23 30-Jun-23
12-May-23 11
20 PLAN
1 DESIGN PACKAGING DDA
1 ACT

SAMPLE PACKAGNG 15-May-23 2-Jun-23 17 PLAN


2 DDA
(MASTER) 1 ACT

PACKAGING TRIAL & 5-Jun-23 16-Jun-23 11 PLAN


3 DDA
EVALUATION 1 ACT
PACKAGING 3-Jul-23 28-Jul-23 23 PLAN
4 SPECIFICATION DDA
APPROVAL 1 ACT

BILL OF MATERIAL 31-Jul-23 11-Aug-23 11 PLAN


5 DDA
PACKAGING 1 ACT

PACKAGING RELEASE 14-Aug-23 14-Aug-23 1 PLAN


6 DDA
NOTE (PRN) 1 ACT
C
el NEW PRDUCT RESEARCH SECT.
C
el LIST STANDAR TEST 0% 10-Apr-23 18-Apr-23 8 PLAN
1 FSA
REQUIREMENT 1 ACT
10-Apr-23 19-Apr-23 9 PLAN
2 MRN / EMS AOK
1 ACT
Insert new rows ABOVE this one

Remarks:
REVISION DUE DATE DESCRIPTION CHECKED BY PPL CHECKED BY PDD CHECKED BY PDE CHECKED BY MCE CHECKED BY NPR APPROVED BY DH
: Plan
: New Plan
: Actual
: Finish
: Start Fabrication of Packaging

Page 2 of 2