Uji Laboratorium Sample Tanah Bahan Perbaikan

Jalan dan
Activity ID Activity Name Original Plan Actual BL1 Start BL1 Finish Start Finish November 2023 December 2023 January 2024 February 2024 March 2024 April 2024 May 2024
Duration
29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 03 10 17 24 31 07 14 21 28 05 12
80
Uji Lab Uji Laboratorium Sample Tanah Bahan Perbaikan 0% dan
Jalan 0% 10-Nov-23 29-Feb-24 10-Nov-23 29-Feb-24 29-Feb-24, Uji Lab Uji Laboratorium Sample Tanah Bahan Perbaikan Jalan

Uji Lab.1 Milestone 8 0% 0% 10-Nov-23 21-Nov-23 10-Nov-23 21-Nov-23 21-Nov-23, Uji Lab.1 Milestone
A1000 Start Project 0 0% 0% 10-Nov-23 10-Nov-23 Start Project, 10-Nov-23
A1010 CEP 8 0% 0% 10-Nov-23 21-Nov-23 10-Nov-23 21-Nov-23 CEP
A1020 KOM 1 0% 0% 10-Nov-23 10-Nov-23 10-Nov-23 10-Nov-23 KOM
Uji Lab.2 Construction 58 0% 0% 13-Nov-23 31-Jan-24 13-Nov-23 31-Jan-24 31-Jan-24, Uji Lab.2 Construction

Uji Lab.2.1 Benny Bronson BP 33 0% 0% 13-Nov-23 28-Dec-23 13-Nov-23 28-Dec-23 28-Dec-23, Uji Lab.2.1 Benny Bronson BP
A1170 Analisa Saringan 1 0% 0% 13-Nov-23 13-Nov-23 13-Nov-23 13-Nov-23 Analisa Saringan
A1180 Atterberg limit 1 0% 0% 14-Nov-23 14-Nov-23 14-Nov-23 14-Nov-23 Atterberg limit
A1190 Moisture Density test 1 0% 0% 15-Nov-23 15-Nov-23 15-Nov-23 15-Nov-23 Moisture Density test
A1200 CBR Soaked 7 0% 0% 16-Nov-23 24-Nov-23 16-Nov-23 24-Nov-23 CBR Soaked
A1210 CBR Un soaked 1 0% 0% 17-Nov-23 17-Nov-23 17-Nov-23 17-Nov-23 CBR Un soaked
A1220 UCS 28 0% 0% 20-Nov-23 28-Dec-23 20-Nov-23 28-Dec-23 UCS
Uji Lab.2.2 KSA BP 39 0% 0% 22-Nov-23 15-Jan-24 22-Nov-23 15-Jan-24 15-Jan-24, Uji Lab.2.2 KSA BP
A1290 Analisa Saringan 1 0% 0% 22-Nov-23 22-Nov-23 22-Nov-23 22-Nov-23 Analisa Saringan
A1300 Atterberg limit 1 0% 0% 23-Nov-23 23-Nov-23 23-Nov-23 23-Nov-23 Atterberg limit
A1310 Moisture Density test 1 0% 0% 24-Nov-23 24-Nov-23 24-Nov-23 24-Nov-23 Moisture Density test
A1320 CBR Soaked 7 0% 0% 27-Nov-23 05-Dec-23 27-Nov-23 05-Dec-23 CBR Soaked
A1330 CBR Un soaked 1 0% 0% 06-Dec-23 06-Dec-23 06-Dec-23 06-Dec-23 CBR Un soaked
A1340 UCS 28 0% 0% 07-Dec-23 15-Jan-24 07-Dec-23 15-Jan-24 UCS
Uji Lab.2.3 Bangko Bakti BP 39 0% 0% 08-Dec-23 31-Jan-24 08-Dec-23 31-Jan-24 31-Jan-24, Uji Lab.2.3 Bangko Bakti BP
A1230 Analisa Saringan 1 0% 0% 08-Dec-23 08-Dec-23 08-Dec-23 08-Dec-23 Analisa Saringan
A1240 Atterberg limit 1 0% 0% 11-Dec-23 11-Dec-23 11-Dec-23 11-Dec-23 Atterberg limit
A1250 Moisture Density test 1 0% 0% 12-Dec-23 12-Dec-23 12-Dec-23 12-Dec-23 Moisture Density test
A1260 CBR Soaked 7 0% 0% 13-Dec-23 21-Dec-23 13-Dec-23 21-Dec-23 CBR Soaked
A1270 CBR Un soaked 1 0% 0% 22-Dec-23 22-Dec-23 22-Dec-23 22-Dec-23 CBR Un soaked
A1280 UCS 28 0% 0% 25-Dec-23 31-Jan-24 25-Dec-23 31-Jan-24 UCS
Uji Lab.3 MAC 21 0% 0% 31-Jan-24 29-Feb-24 31-Jan-24 29-Feb-24 29-Feb-24, Uji Lab.3 MAC
A1140 Punchlist & Closing Punchlist 1 0% 0% 31-Jan-24 01-Feb-24 31-Jan-24 01-Feb-24 Punchlist & Closing Punchlist
A1145 JS Final 1 0% 0% 01-Feb-24 02-Feb-24 01-Feb-24 02-Feb-24 JS Final
A1150 MAC approval 19 0% 0% 05-Feb-24 29-Feb-24 05-Feb-24 29-Feb-24 MAC approval
A1160 Finish Project 0 0% 0% 29-Feb-24 29-Feb-24 Finish Project,

Actual Level of Effort summary Prepared By Review By Approved by


Actual Work
Remaining Work
Critical Remaining Work
(..........................................................) (................................................................) (................................................)
Milestone