Weekly Progress For Diggi

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Nos.

of Consent
work Diggies received Consent of Target Achieved upto
order to be upto Diggi 12.04.2024 Expenditure up
Name of the amount in construc 12.04.20 inform to to 12.04.2024
S.No Division Package Lakh ted 24 Contractor in Lakhs
Work Work in
completed progress
1 19th and SMGS JSM-AC1 4104 608 108 99 35 23 180.53
2 TMC and 23rd JSM-AC2 3248 529 169 120 65 3 444.53
3 19th JSM-BC1 7874 922 207 196 61 31 324.83
4 SMGS JSM-CC2 11529 1400 100 97 12 0 112.62
5 TMC JSM-DD1 3377 417 215 210 100 10 596.4
6 23rd JSM-DD2 4274 518 117 117 27 6 119.32
7 SMGS JSM-BC2 1942 236 40 30 0 19 3.24
8 Water Course JSM-BC3 2220 261 72 72 45 6 300.10
9 Water Course JSM-CC1 2403 298 150 150 30 75 300.00