SUMMARY TIME SHEET

Lokasi : PT. Kencana Sinergi Jaya Site Electra Global


ID Unit : EX1110 CAT320
Periode : 01 April - 30 April 2024

Hours Meter HM Check Break Available


Tanggal EWH (W) Standby Remark
Start Stop Total By Mech Down (B) Hours
1-Mar-24 0,00 24,00 0,00 0,00 24 TRACK RH LOOSEN, ADJUSTER NGEJIM
2-Mar-24 0,00 24,00 0,00 0,00 24 TRACK RH LOOSEN, ADJUSTER NGEJIM
3-Mar-24 0,00 24,00 0,00 0,00 24 TRACK RH LOOSEN, ADJUSTER NGEJIM
4-Mar-24 0,00 24,00 0,00 0,00 24 TRACK RH LOOSEN, ADJUSTER NGEJIM
5-Mar-24 0,00 24,00 0,00 0,00 24 TRACK RH LOOSEN, ADJUSTER NGEJIM
6-Mar-24 0,00 24,00 0,00 0,00 24 TRACK RH LOOSEN, ADJUSTER NGEJIM
7-Mar-24 0,00 0,00 24,00 24
8-Mar-24 3978,8 3997,8 19,00 19,00 5,00 24
9-Mar-24 3997,8 4002,4 4,60 1,50 4,60 17,90 24 SOLENOID PROBLEM
10-Mar-24 0,00 0,00 24,00 24
11-Mar-24 0,00 0,00 24,00 24
12-Mar-24 4002,4 4021,5 19,10 19,10 4,90 24
13-Mar-24 4021,9 4031,9 10,00 10,00 14,00 24
14-Mar-24 4031,9 4036,4 4,50 4,50 19,50 24
15-Mar-24 4036,4 4054,8 18,40 18,40 5,60 24
16-Mar-24 4054,8 4069,7 14,90 1,27 14,90 7,83 24 SERVICE PM 4000
17-Mar-24 4069,7 4085,4 15,70 15,70 8,30 24
18-Mar-24 4085,4 4099,1 13,70 1,00 13,70 9,30 24 LOCK PIN BUCKET BROKEN
19-Mar-24 4099,1 4113,1 14,00 14,00 10,00 24
20-Mar-24 4113,1 4128,0 14,90 5,00 14,90 4,10 24 LOCK PIN BUCKET BROKEN
21-Mar-24 4128,0 4145,7 17,70 17,70 6,30 24
22-Mar-24 4145,7 4164,7 19,00 19,00 5,00 24
23-Mar-24 0,00 0,00 24,00 24
24-Mar-24 0,00 0,00 24,00 24
25-Mar-24 0,00 0,00 24,00 24
26-Mar-24 0,00 0,00 24,00 24
27-Mar-24 0,00 0,00 24,00 24
28-Mar-24 0,00 0,00 24,00 24
29-Mar-24 0,00 0,00 24,00 24
30-Mar-24 0,00 0,00 24,00 24
31-Mar-24 0,00 0,00 24,00 24
Total 185,50 0,00 152,77 185,50 405,73 744

Physical Availability = (W+S)/MOOH 79,47%


Use of Avalability = W/(W+S) 31,38%

Patas 1, 1 November 2023

Yudi Ariyanto ( )
PT. Kencana Sinergi Jaya CV. Berkah Betang Jaya