 Open the resource usage profile

Now we have two activities at the same time with the same resource, each activity has a 6
units per day of this activity with budgeted units per day as a total equal 12 unit per day.

The allowable max units per day for this resource is 10 units per day so we need to level these
activities.

But first we need to determine the activity levelling priority, from columns select activity
levelling priority.

86 | P a g e
Eng. Hussien Mostafa Ahmed