Beam Shallowing Detail

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

EXISTING BEAM DEPTH TO BE HACKED OFF &

REDUCED TO FLUSH WITH 1B9. 75MM


OVERHACK TO PLANT IN NEW REBAR WITH
ROUGHEN SURFACE AND CLEAN OF DUST. TO
CAST BACK WITH SIKA 215

REBAR DRILLED IN HOLE


2100 FILLED WITH HILTI
2T16 DRILLED IN HOLE
FILLED WITH HILTI RE-500V4
A EXISTING TOP BAR B A RE-500V4 MIN. 80mm
DEPTH

REBAR DRILLED IN HOLE FILLED


WITH HILTI RE-500V4 MIN. 80mm
DEPTH AND CAST BACK WITH NEW R6-225 TO DRILL INTO EXISTING BEAM

600
SIKA 215

300
800

75

75
EXISTING LINK TO CUT
SECTION A
BEAM AREA TO
BE CUT

SCALE : 1:25

EXISTING BOTTOM BAR


A
NEW 2T16 B SECTION B
A SCALE : 1:25

125x600