Methodology of Laying of Bedding and Padding Material. Rev.01
Methodology of Laying of Bedding and Padding Material. Rev.01
Employer
Consultant
Contractor
Chapter
SN Engineer’s Comment Contractor’s Response (Rev.01)
(Rev.00)
1
Chapter
SN Engineer’s Comment Contractor’s Response (Rev.01)
(Rev.00)
Names are required for Contractor and
Chapter 6
8 Consultant Rectified.
Page 5 to 12
Methodology for removal of S2 bedding and padding material for laid pipeline refer to
Chapter 7.1 This request another MS and Risk CHEC-AFI/PL1-MS-024
9
Page 14 Assessment for removal of S2 material. HSE Plan for removal of S2 bedding and padding material for laid pipeline ial refer to
CHEC-AFI-PL1-HSEP- 005
Chapter 7.1 Please note: Slightly compacted for
10 Rectified.
Page 14 bedding layer
Chapter 7.1
11 No Water to use by Bedding Noted.
Page 14
Methodology for removal of S2 bedding and padding material for laid pipeline refer to
Separate MS required as well as Risk
Chapter 7.1 CHEC-AFI/PL1-MS-024
12 Assessment for
Page 15 HSE Plan for removal of S2 bedding and padding material for laid pipeline ial refer to
CHEC-AFI-PL1-HSEP- 005
Chapter 7.2
13 20 to max 30 cm Rectified.
Page 15
2
CONTENTS
I
1 Scope of work
Documents cover the method, for bedding and padding with screening material under
the pipeline in accordance with standards and specification. This method ensures
2 Basis of Compilation
KIV PL1 - Volume II-Specifications - Civil Works
3 Preparation
According to the construction drawings, after the excavation has achieved the
required bottom level of trench, the formation level elevations shall be checked by the
surveyor. After confirmation of these elevations the screening material or any other
suitable material as approved by the Engineer will be used to prepare the bedding and
padding layer. Slight compacted for bedding material, Water will be used if Padding
4 Manpower
According to site situation, 4~6 groups along pipeline will be arranged for screening
material. One foreman , two labour and one HSE supervisor of each groups should be
present at site.
5 Equipment
The equipment used for each group is shown in below table .
1
6 Material
Screening in-situ or borrow material (Permission by Consultant) will be used for
laying of bedding and padding layers, and the reports and pictures of above materials
2
3
4
5
6
7
8
9
10
7. Construction Technology
CHEC-AFI/PL1-MS-024.
The access road to trench will be made between the existing access road and trench at
every 500m to 1000m depending on site condition, then the bedding material will be
Access Access
Slope
Bedding Bedding
Bedding material will be laid on the formation level and it will be spread using loader
or grader. Sticks will be installed at the edges and center of the trench at a distance of
20m each. Elevation will be marked on these bamboo sticks. Initially elevation of
Stone, Debris, weeds, etc. will be removed after placing and spreading the bedding
material. Manually labor will be used with picking tools to remove any unwanted
material from the layer. Stones of bigger size will also be removed from the top
surface of the bedding layer. Slightly compacted for bedding material. Surveyors will
11
be used to check the final elevation of the bedding layer.
In areas where S2 material for bedding or padding has been placed, screened material
Padding material from stockpile will be transferred to site using dumpers and loaders.
Loader or excavator will be used to place the material inside the trench. Stone, debris,
weeds etc. will be removed after placing and spreading if any, for each layer
compaction.
8 QA/QC management
Screening in-situ or borrow material shall be checked by engineer, all corresponding
file. Before any preparation or execution of the work, ICRF will be submitted to the
consultant.
12