Professional Documents
Culture Documents
7009 How To Price and Document
7009 How To Price and Document
7009 How To Price and Document
Distribution of the webinar materials outside of your site is prohibited. Reproduction of the materials and pictures without a written permission of the
copyright holder is a violation of the U.S. law.
Bill Haydt
Director and Shareholder
Trauner Consulting Services, Inc.
Qualified Expert in
Construction Scheduling and
Delay Analysis
1
DAY 1:
Distribution of the webinar materials outside of your site is prohibited. Reproduction of the materials and pictures without a written permission of the
copyright holder is a violation of the U.S. law.
Webinar Outcomes
2
Problem: Project Delays
As old as deadlines.
As project complexity increases, the risk of delay
increases.
Delays carry real and significant costs.
Critical Path
Longest Path
Float
3
Critical Path
4
The Critical Path
Total Float
5
Float Misconceptions
10
11
11
6
Who Owns Float?
If contract is silent:
The project “owns the float.”
Available for use on a “first come, first served” basis.
Presumes use of float does not result in additional cost to either
party.
Float ownership clauses:
Should seek to address what float ownership means in terms of
cost.
For example, if the owner “owns the float,” then has the owner
procured the right to delay any non-critical activities without the
risk of being responsible for additional costs that result from that
non-critical delay?
12
Contract Provisions
13
13
7
Relevant Contract Provisions
Changes Clauses
Change Order Pricing Provisions
Claims Provisions
Scheduling Provisions
Time Extension Provisions
Delay Damage or Cost Provisions
14
Contract Provisions
15
8
TM
AIA Document A201 – 2007
16
TM
AIA Document A201 – 2007
17
9
TM
ConsensusDOCS 200 – 2007
18
TM
ConsensusDOCS 200 – 2007
19
10
Excusable, Non-compensable
Delays
Excusable, non-compensable delays are, typically, delays
that are not the Contractor’s or the Owner’s fault or
responsibility, and that could not have been foreseen by the
Contractor. Typically, the Owner will not compensate the
Contractor for excusable, non-compensable delays.
20
Examples of Excusable,
Non-compensable Delays
1. Delays due to fires, floods, tornadoes, lightning strikes,
earthquakes
2. Delays due to weather
3. Extraordinary delays in material deliveries
4. Delays due to civil disturbances
5. Delays due to acts of the public enemy
6. Delays due to labor strikes
21
11
Excusable, Compensable Delays
22
23
12
1904.6.B Allowable Delay Costs*
24
Delay Damages
25
25
13
Methods of Calculation
Contract
Estimates
Actual cost
Total cost
Modified total cost
26
Delay Damages
27
14
Owner Delay Costs
28
29
15
Owner Delay Costs: Actual Costs
30
Other Parties
31
16
Contractor Delay Costs
32
Idle Labor
Extended Labor
Labor Cost Escalation
33
17
Contractor Delay Costs: Idle
Labor
34
35
18
Contractor Delay Costs:
Labor Cost Escalation
36
Idle Equipment
Extended Equipment
37
19
Contractor Delay Costs:
Idle Equipment
38
39
20
Contractor Delay Costs: Material
40
41
21
Contractor Delay Costs:
Overheads
42
43
22
FOOH Example
Objective
Evaluate the costs submitted by a contractor and
determine whether or not each is a field overhead cost
recoverable in the event of a compensable delay.
Background
On a bridge project a contractor submitted a claim to
recover its field overhead costs for a 1-month delay on
a 12-month project. The table below summarizes the
costs.
44
45
23
HOOH Example
46
Allocable Overhead
= Daily Overhead
Total Days of Contract Performance
Unabsorbed
Daily Overhead x Days of Compensable Delay = Overhead
47
24
HOOH Eichleay Example
Objective
Based on the background information provided, calculate the
unabsorbed home office overhead using the Eichleay method. Be
prepared to discuss your answer with the class.
Background
An owner suspends operations for 100 days on a $3 million
project. The final project duration was 500 days.
During the suspension period, the contractor has no other work
that can accommodate the workers or equipment.
Audit of contractor’s financial records document:
Total company billing during the contract period is $12 million.
Actual home office overhead cost during the same period is
$400,000.
48
Step 1:
Step 2:
Step 3:
49
25
Summary
50
Questions
bill.haydt@traunerconsulting.com
51
26
How to Price and Document
Your Delay Claims
Live 2-Day Online Training
Bill Haydt
Director/Shareholder, Trauner Consulting Services, Inc.
bill.haydt@traunerconsulting.com
Distribution of the webinar materials outside of your site is prohibited. Reproduction of the materials and pictures without a written permission of the
copyright holder is a violation of the U.S. law.
52
DAY 2:
Distribution of the webinar materials outside of your site is prohibited. Reproduction of the materials and pictures without a written permission of the
copyright holder is a violation of the U.S. law.
53
27
Webinar Outcomes
54
Presentation Overview
1. Why do we care?
2. Electronic or Paper?
3. Pre-construction/Bid Phase Documentation
4. Standard Project Documentation
5. Communications
6. Summary
7. Questions and Answers
55
28
1. Why do we care?
56
1. Why do we care?
57
29
1. Why do we care?
58
1. Why do we care?
59
30
1. Why do we care?
60
Presentation Overview
1. Why do we care?
2. Electronic or Paper?
3. Pre-construction/Bid Phase Documentation
4. Standard Project Documentation
5. Communications
Summary
Questions and Answers
61
31
2. Electronic or Paper?
62
2. Electronic or Paper?
63
32
2. Electronic or Paper?
64
2. Electronic or Paper?
65
33
And finally,
(as an experienced construction litigator once put it):
66
67
34
What Does “Contemporaneous”
Mean?
68
69
35
Presentation Overview
1. Why do we care?
2. Electronic or Paper?
3. Pre-construction/Bid Phase Documentation
4. Standard Project Documentation
5. Communications
Summary
Questions and Answers
70
3. Pre-construction/Bid Phase
Documentation
71
36
3. Pre-construction/Bid Phase
Documentation
Example:
The contractor could create a pre-bid “observations &
assumptions log” that accompanies the bid documents
through the estimating phase of the project right up to the
time the bid or proposal leaves your office.
72
3. Pre-construction/Bid Phase
Documentation
Examples:
Value Engineering
Assumptions regarding the effect of inclement weather on
the project
Notes from estimators or designers about anything that, in
their experience, seems strange or unusual
73
37
3. Pre-construction/Bid Phase
Documentation
74
Presentation Overview
1. Why do we care?
2. Electronic or Paper?
3. Pre-construction/Bid Phase Documentation
4. Standard Project Documentation
5. Communications
Summary
Questions and Answers
75
38
4. Standard Project
Documentation
Meeting Minutes
Daily Reports
Notes to File
E-mail
RFI and Submittal Logs
Digital Photos
Videos
76
4. Standard Project
Documentation
77
39
4. Standard Project
Documentation
78
4. Standard Project
Documentation
79
40
4. Standard Project
Documentation
80
4. Standard Project
Documentation
81
41
4. Standard Project
Documentation
82
4. Standard Project
Documentation
83
42
4. Standard Project
Documentation
84
4. Standard Project
Documentation
85
43
4. Standard Project
Documentation
86
4. Standard Project
Documentation
87
44
4. Standard Project
Documentation
88
4. Standard Project
Documentation
89
45
4. Standard Project
Documentation
90
4. Standard Project
Documentation
91
46
4. Standard Project
Documentation
92
4. Standard Project
Documentation
Daily Reports
We recommend that someone at project management level
spot check at least one daily report per week from each
jobsite. Do this in order to maintain a continuous dialog with
the people responsible for writing daily reports and offer
guidance on their choice of words.
93
47
4. Standard Project
Documentation
Notes to File
Document an unusual occurrence
Document a telephone conversation
Document the status of something at a particular point in
time
But note – Notes to File are incomplete communications
94
4. Standard Project
Documentation
95
48
4. Standard Project
Documentation
96
4. Standard Project
Documentation
97
49
Presentation Overview
1. Why do we care?
2. Electronic or Paper?
3. Pre-construction/Bid Phase Documentation
4. Standard Project Documentation
5. Communications
Summary
Questions and Answers
98
5. Communications
Emails
Schedules
Letters
Oral Communication
Anything shared
99
50
5. Communications
Emails:
Considered contemporaneous documentation
Every bit as important as hard copy correspondence
Admissible in legal proceedings
Discoverable
Texts:
Fast, but can it readily be stored or retrieved?
Incomplete communication?
100
5. Communications
Emails:
Treat incoming e-mail as you would a letter or a fax
print it! (including the attachment)
file it!
Because e-mail is a quick and easy method of communication, it’s
easy to lose perspective of the importance of the document.
101
51
5. Communications
Schedules:
Are a contemporaneous communication by the contractor
to the owner of the contractor’s current plan for
performing the work
Each Schedule and Update needs to be preserved in its
original form
Are the preferred source of information when analyzing
delay claims
Electronic Schedule file contains a lot more information
than is shown on a paper print-out
102
5. Communications
Schedules:
Most scheduling software operates in “real time,” which
means that any changes made to schedules are effective
immediately.
Always save a pristine copy of your baseline schedule
and every schedule update for the duration of the project.
Never “WRITE OVER” original schedules or
schedule updates!
103
52
5. Communications
Oral Communications
Examples of situations in which we rely on oral
communications
Telephone conversations
Field meetings
Inspections with the AHJ
104
5. Communications
Oral Communications
Whenever oral direction is given or received, or when
something is agreed to or promised during a conversation,
the best practice is to follow up with a written confirmation.
105
53
5. Communications
Oral Communications
Here is an example of a subcontractor confirming direction given
by the general contractor:
“Yesterday in the supers meeting, you told me to set up my scaffold and
start laying block at the SE corner of the building. This morning out on site
you told me to set up and start block at SW corner. The scaffold arrives
today. I will set up at the SW corner per your direction.”
Signed & Dated & Copied for Sub’s File
106
5. Communications
Oral Communications
What do you do when you are given direction by someone not
authorized to do so?
107
54
5. Communications
Oral Communications
What do you do when you are given direction by someone not
authorized to do so?
Dear Owner,
Today your interior designer was at the jobsite for a tour. She decided
that the meditation room should not be painted fire-engine red as
shown in the room finish schedule. She directed us to repaint the room
a soft mauve color. However, since the room is already painted, there
will be a cost to repaint the room. Please advise if you would like us to
prepare a proposal for your review.
Sincerely,
Your Favorite Contractor
How to Price and Document Your Delay Claims 108
108
5. Communications
Letters
A good construction letter should:
Have an introduction, a body, and a summary.
Be limited to one and only one subject.
State the facts or questions clearly. (State why the letter is being
written).
Discuss the subject in as few words as possible.
Employ your best technical writing skills (omit the prose).
Exclude emotion, sarcasm, threats, and profanity.
109
55
5. Communications
110
5. Communications
111
56
5. Communications
112
5. Communications
113
57
5. Communications
114
5. Communications
Letters
A good construction letter should exclude sarcasm:
I questioned why my firm was paid only 90% of our Change Orders #2, 4
and 5. This work was authorized by the Developer to be performed on a
T&M basis. We did just that; we did follow instructions.
I have thought of an easy solution for the Owner. They have only paid
90% of these extra work tickets. I don’t want the balance of the 10%. I can
take 10% of the piping back that I have installed and with the escalation of
material costs in the last year, I will install it at a job that is actually willing
to pay me.
Can you please indicate what 10% of the piping I can remove? I would
like to start this process on Monday July 14th.
115
58
5. Communications
Letters
A good construction letter should not poke a finger in the recipient’s
eye:
Due to discrepancies in the plans and the information provided by you the
architect, we are being forced to react to solve a problem with the tie
beams at the tops of the masonry shearwalls … If we encounter any
resistance from the City of ________ or the Threshold Inspector we would
hope that you will provide the assistance necessary to satisfy their
requirements.
116
5. Communications
Letters
A good construction letter might address this issue this way:
We are currently working with the City and the Threshold Inspector to
resolve the issue with the tie beams at the tops of the masonry walls. As
the designer-of-record, your assistance may be required. To keep you
informed of our progress, we will copy you on all correspondence related
to this issue.
117
59
5. Communications
Memo to File
A good memo to file should exclude threats:
I have made a list of the following items which you may wish to take action
on, in response to the contractor’s claim:
1. Deny contractor’s claim and work with the attorneys to make up some
countersuit for a similar amount.
2. Work closely with the Resident Engineer and make a long punch list
which includes every possible small nit-picking item.
3. Advise the contractor to remove his batch plant from the job site within
the next seven days or threaten to charge him ground rent.
118
5. Communications
Letters
A good construction letter should exclude threats:
4. Review the number of rain days this year compared to previous years
and if it is substantially lower, decrease his contract time accordingly.
5. Review the Superintendent Daily Reports and see if there are any
items documented that can be used against him.
119
60
5. Communications
Letters
A good construction letter should exclude profanity:
In regard to your letter, dated November 22, _____, concerning possible
erosion of slopes on the contract captioned above, please be advised that
we are of the opinion that you are full of &!#%.
If you have any questions concerning this matter, please do not hesitate to
contact me. I remain
Very sincerely yours,
120
Presentation Overview
1. Why do we care?
2. Electronic or Paper?
3. Pre-construction/Bid Phase Documentation
4. Standard Project Documentation
5. Communications
Summary
Questions and Answers
121
61
Summary
122
Summary
123
62
Summary
124
Documenting Delays
Provide Notice
Often required.
If required, provide it in the specified form.
Adhere to contract specification requirements.
If not required, provide it anyway, in writing.
125
63
Documenting Delays
Contemporaneous Documents
Often more credible.
Closer to the event; less memory dependent.
Fixed, story can’t change.
Remember to date and sign.
May appear to be less biased.
126
Documenting Delays
127
64
Documenting Delays
128
129
65
Summary
Documenting Impacts
Approved Baseline Schedule
Schedule Updates and Revisions
Provide Timely Notice
Daily Reports, Logs, & Diaries
Meeting Minutes
Categorize and Present Costs
130
Questions
bill.haydt@traunerconsulting.com
131
66