Sooraj - Oct-2023 Time Sheet - SIEMENS

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

CUSTOMER SIEMENS ENERGY

BUSINESS CONTINUITY- MONTH Oct-23


PROJECT CONTAINERIZED SS PACKAGE
TIME WORKED Total
DATE OT REMARKS
working hrs
FROM TO
01-Oct-23 SUNDAY HOLIDAY
Trafo/Motor Feeder scheme verification, Missing labels preparation and traffolyte listings, Taking
02-Oct-23 7.30 5.30 10.00
Punch points
Trafo/Motor Feeder, Incomer scheme verification, Missing labels preparation and traffolyte listings,
03-Oct-23 7.30 5.30 10.00
Taking Punch points
RCP, Incomer scheme verification, Missing labels preparation and traffolyte listings, Taking Punch
04-Oct-23 7.30 5.30 10.00
points
Incomer scheme verificaion, General arrangement verification for switchgear, RCP operations check,
05-Oct-23 7.30 5.30 10.00
Switchgear operations check
Breaker, Voltage transformer operational checks, operational checks for transformer and motor
06-Oct-23 7.30 5.30 10.00
feeders,

07-Oct-23 7.30 5.30 10.00 Relay setting verification and internal testing, OCC file preparation, Relay internal testing

08-Oct-23 SUNDAY HOLIDAY


CB racking out verification, and Relay setting verification and internal testing, OCC file preparation,
09-Oct-23 7.30 5.30 10.00
Relay internal testing
10-Oct-23 7.30 5.30 10.00 BUS earth switch operation check, drawing red markup and scanning, report preparation for MV IFAT

11-Oct-23 7.30 5.30 10.00 Report prepration for MV IFAT, CT testing using CT analyzer, Timing test for vacuum contactor

Report prepration for MV IFAT-AC/DC Scheme checks, CBCT Test report, Lockout relay, MFM,
12-Oct-23 7.30 5.30 10.00
Ammeter, Voltmeter
Report prepration for MV IFAT-Electrical /Mechanical checks, Interlock checks, Functional Checks,
13-Oct-23 7.30 5.30 10.00
Auxiliary DB Test reports
Report prepration for MV IFAT-Relay test reports, Red mark up drawings,HV test report preparation
14-Oct-23 7.30 5.30 10.00

15-Oct-23 SUNDAY HOLIDAY


16-Oct-23 7.30 5.30 10.00 IFAT Punch point closeout for LV1, LV2, DB Container, IFAT Report preparation and verification

17-Oct-23

18-Oct-23

19-Oct-23

20-Oct-23

21-Oct-23

22-Oct-23 SUNDAY HOLIDAY

23-Oct-23

24-Oct-23

25-Oct-23

26-Oct-23

27-Oct-23

28-Oct-23

29-Oct-23 SUNDAY HOLIDAY


30-Oct-23

31-Oct-23
Total (Hours) 130.00
B C E REPRESENTIVE SIEMENS ENERGY
Name:Sooraj Name:

Signature: Signature: